Daniel Conrad
- Listed as
- authorized agent-others, engineer
- Firm
- Aedifica Engineering
- Based in
- St. Louis
- On San Francisco permits
- May 2019 to Jul 2026
12 permits since 2000 (engineer on 11 permits, authorized agent-others on 1 permit): 7 completed, 4 in progress, 1 never finaled.
This is the city’s permit record, not a license check: the role and the number come from what was written on each permit (the number spelled one way). It does not show whether the license is current. How to read these records
Most recent permits
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Jul 2, 2026 | In progress issued Aug 2026 | 1868 Lombard St | Hauswerks Construction Inc | formula retail ground floor tenant improvement - excercise use. interior work includes new non-bearning partitions, doors, finishes, ceilings, lighting, mep. exterior signage shown under seperate permit.Details
formula retail ground floor tenant improvement - excercise use. interior work includes new non-bearning partitions, doors, finishes, ceilings, lighting, mep. exterior signage shown under seperate permit. | $285,038 |
| Feb 19, 2026 | In progress filed Feb 2026, not yet issued | 1976 Innes Av | Browncoconstruction And Development Inc | tenant fitout of existing showroom in pre-engineered warehouse. scope includes new offices, showroom. structural, mechanical, electrical, and plumbing work. exterior modification to (e) storefront including demo (e) storefront. new storefront. new overhead doors. new exterior main entrance door.Details
tenant fitout of existing showroom in pre-engineered warehouse. scope includes new offices, showroom. structural, mechanical, electrical, and plumbing work. exterior modification to (e) storefront including demo (e) storefront. new storefront. new overhead doors. new exterior main entrance door. | $1,000,000 |
| Jan 26, 2026 | In progress issued Jun 2026 | 3251 20th Av | Discount Signs & Neon Inc | space #169:prop h - remodel of an existing jamba juice. scope to include architectural, electrical, mechanical, and plumbing design. scope of improvements include complete finish out of the interior to include new non-load bearing walls, ceiling, floor finishes, and millwork.Details
space #169:prop h - remodel of an existing jamba juice. scope to include architectural, electrical, mechanical, and plumbing design. scope of improvements include complete finish out of the interior to include new non-load bearing walls, ceiling, floor finishes, and millwork. | $325,000 |
| Nov 12, 2025 | Completed final sign-off Mar 2026 | 3407 California St | Build Group Inc. | formula retail ground floor tenant improvement - exercise use. interior work including new non-bearing partitions, finishes, ceilings, lighting, mep. exterior signage under separate permit.Details
formula retail ground floor tenant improvement - exercise use. interior work including new non-bearing partitions, finishes, ceilings, lighting, mep. exterior signage under separate permit. | $205,000 |
| Oct 31, 2025 | Completed final sign-off Jul 2026 | 301 Howard St | Kr Johnston Construction Inc, Harvey Usa Llc | suite 120 1st fl: tenant improvement of empty shell for new low impact fitness studio including 2 new restrooms. change of use from office to fitness.Details
suite 120 1st fl: tenant improvement of empty shell for new low impact fitness studio including 2 new restrooms. change of use from office to fitness. | $565,000 |
| Nov 27, 2023 | In progress issued Jan 2024 | 3998 18th St | Sd Design Construction Corp. | interior alterations only: replacement of (e) ceiling; (n) subflooring w/ slab infill work; (n) flooring; (n) finishes; minor repair/replacement of (e) duct system; installation of coolers/freezers; bring unise toilet from ada to requirements; provide (e) electrical panel with (n) service;Details
interior alterations only: replacement of (e) ceiling; (n) subflooring w/ slab infill work; (n) flooring; (n) finishes; minor repair/replacement of (e) duct system; installation of coolers/freezers; bring unise toilet from ada to requirements; provide (e) electrical panel with (n) service; | $225,000 |
| May 26, 2023 | Completed final sign-off Nov 2023 | 2355 Market St | Adam Lewis Construction Company | revision to permit 2022-1028-5383 discovery of shear walls leads to layout changes. revised meps to align with new architectural floor plan. no new sfDetails
revision to permit 2022-1028-5383 discovery of shear walls leads to layout changes. revised meps to align with new architectural floor plan. no new sf | |
| Oct 24, 2022 | Never finaled issued Dec 2022, no final | 2300 16th St | Husher Inc Dba Husher Construction | space 320: interior tenant improvement to (e) building consists of new interior walls, finishes, and fixtures.Details
space 320: interior tenant improvement to (e) building consists of new interior walls, finishes, and fixtures. | $175,000 |
| Feb 9, 2021 | Completed final sign-off Jun 2021 | 2 West Portal Av | Adam Lewis Construction Company | revision to pa# 202005117379. tenant improvement on gronud floor of existing building. new non-structural partitions, ceilings, case work. finishes. enclose raised portion of mezz. enclosed portion (334sf) shall not be used for any purpose.Details
revision to pa# 202005117379. tenant improvement on gronud floor of existing building. new non-structural partitions, ceilings, case work. finishes. enclose raised portion of mezz. enclosed portion (334sf) shall not be used for any purpose. | |
| Nov 6, 2020 | Completed final sign-off Nov 2021 | 845 Market St | James M Barb Construction Co | suite 204. interior tenant fit-out incl storefornt, finishes, lighting & millwork. (n) lighting, power & data supply for millwork & boh. (n) hvac unit, ductwork & distribution system. (n) washroom plumbing, mop sink & drinking fountain. (n) structure for storefront & suspended equipment.Details
suite 204. interior tenant fit-out incl storefornt, finishes, lighting & millwork. (n) lighting, power & data supply for millwork & boh. (n) hvac unit, ductwork & distribution system. (n) washroom plumbing, mop sink & drinking fountain. (n) structure for storefront & suspended equipment. | $289,000 |
| Jul 16, 2019 | Completed final sign-off Jan 2020 | 559 Clay St | Bcci Construction Company | ti on 1st and 2nd flr of 4 story bld including demo of (e) space, non structural partition, ceiling, casework, finishes and mep work, signage deferred.Details
ti on 1st and 2nd flr of 4 story bld including demo of (e) space, non structural partition, ceiling, casework, finishes and mep work, signage deferred. | $750,000 |
| May 13, 2019 | Completed final sign-off Jul 2020 | 1275 04th St | Novo Construction Inc | ti of 1st fl medical office: non structural partitons, ceilings, casework, casework finishes, mep work. exterior signage for ref only. exterior signage will be under sep permit, maher n/a.Details
ti of 1st fl medical office: non structural partitons, ceilings, casework, casework finishes, mep work. exterior signage for ref only. exterior signage will be under sep permit, maher n/a. | $495,000 |