Gray Dougherty
- Listed as
- architect
- Firm
- Gensler
- Based in
- San Francisco
- On San Francisco permits
- Mar 2019 to Mar 2020
28 permits since 2000 (architect on 28 permits): 27 completed, 1 never finaled.
This is the city’s permit record, not a license check: the role and the number come from what was written on each permit (the number spelled one way). It does not show whether the license is current. How to read these records
Most recent permits
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Mar 12, 2020 | Completed final sign-off May 2021 | 250 Howard St | Webcor Construction Lp | 27th fl - revision to pa 2019-0717-6121 to document catering storageDetails
27th fl - revision to pa 2019-0717-6121 to document catering storage | |
| Aug 19, 2019 | Completed final sign-off Jul 2021 | 250 Howard St | Webcor Construction Lp | 12th floor defered structural . reference app#201903226019. n/a for maherDetails
12th floor defered structural . reference app#201903226019. n/a for maher | |
| Aug 1, 2019 | Completed final sign-off Jul 2021 | 250 Howard St | Webcor Construction Lp | health review only previously approve ti ref 201903276415Details
health review only previously approve ti ref 201903276415 | |
| Jul 23, 2019 | Completed final sign-off Jul 2021 | 250 Howard St | Webcor Construction Lp | mep for new kitchen and dining area on 25th floor. arch app#201904269208. n/a for maher. revision to arch for 2-hr rated horizontal enclosure around grease duct. type 1 kitchen hoods to be submitted under separate permit.Details
mep for new kitchen and dining area on 25th floor. arch app#201904269208. n/a for maher. revision to arch for 2-hr rated horizontal enclosure around grease duct. type 1 kitchen hoods to be submitted under separate permit. | $800,000 |
| Jul 23, 2019 | Completed final sign-off Jul 2021 | 250 Howard St | Webcor Construction Lp | mep for new pantry dining area on 26th floor. arch app#201904269211. n/a for maher. 08/22/19 - revision to arch for 2-hr rated horizontal enclosure around type ii duct.Details
mep for new pantry dining area on 26th floor. arch app#201904269211. n/a for maher. 08/22/19 - revision to arch for 2-hr rated horizontal enclosure around type ii duct. | $800,000 |
| Jun 27, 2019 | Never finaled issued Aug 2019, no final | 250 Howard St | Webcor Construction Lp | 44th fl - installation of a new gas water heaters & assoc equipmentDetails
44th fl - installation of a new gas water heaters & assoc equipment | $50,000 |
| Jun 17, 2019 | Completed final sign-off Jun 2021 | 250 Howard St | Webcor Construction Lp | 10th flr. (n) non-structural partitions. acoustical grid and tile and gyp board ceiling, lightfixtures, millwork and finishes.Details
10th flr. (n) non-structural partitions. acoustical grid and tile and gyp board ceiling, lightfixtures, millwork and finishes. | $2,000,000 |
| Jun 17, 2019 | Completed final sign-off Jul 2021 | 250 Howard St | Webcor Construction Lp | 7th fl - new non structural parititons. acoustical grid & tile and gyp board ceilings, light fixtures, millwork & finishesDetails
7th fl - new non structural parititons. acoustical grid & tile and gyp board ceilings, light fixtures, millwork & finishes | $2,100,000 |
| Jun 17, 2019 | Completed final sign-off Jul 2021 | 250 Howard St | Webcor Construction Lp | 8th flr. (n) non-structural partitions. acoustical grid and tile and gyp board ceiling, lightfixtures, millwork and finishes.Details
8th flr. (n) non-structural partitions. acoustical grid and tile and gyp board ceiling, lightfixtures, millwork and finishes. | $2,000,000 |
| Jun 5, 2019 | Completed final sign-off May 2021 | 250 Howard St | Webcor Construction Lp | 4th flr - construction of new non structural partitions acoustical grid & tile & gypboard ceiling, light fixtures,millwork finishes maher naDetails
4th flr - construction of new non structural partitions acoustical grid & tile & gypboard ceiling, light fixtures,millwork finishes maher na | $2,000,000 |
| Jun 5, 2019 | Completed final sign-off May 2021 | 250 Howard St | Webcor Construction Lp | 5th fl - construction of new non-structural partitions, acoustical grid & tile & gyp board ceilings, light fixtures, millwork & finishesDetails
5th fl - construction of new non-structural partitions, acoustical grid & tile & gyp board ceilings, light fixtures, millwork & finishes | $2,000,000 |
| Jun 5, 2019 | Completed final sign-off May 2021 | 250 Howard St | Webcor Construction Lp | 6th flr - construction of new non structural partitions acoustical grid & tile & gypboard ceiling, light fixtures,millwork finishes maher naDetails
6th flr - construction of new non structural partitions acoustical grid & tile & gypboard ceiling, light fixtures,millwork finishes maher na | $2,000,000 |
| May 10, 2019 | Completed final sign-off Jul 2021 | 250 Howard St | Webcor Construction Lp | create seperate ats room on 44th flr ref 201903014193. n/a for maher.Details
create seperate ats room on 44th flr ref 201903014193. n/a for maher. | |
| May 3, 2019 | Completed final sign-off Jul 2021 | 250 Howard St | Webcor Construction Lp | new tenant generator with belly tank on level 44. ** maher: n/a **Details
new tenant generator with belly tank on level 44. ** maher: n/a ** | $65,000 |
| May 2, 2019 | Completed final sign-off Jul 2021 | 250 Howard St | Webcor Construction Lp | b1 - revision to 201903276418 to update card reader matrix, proviced card readers & emergency/door relaese buttons, panic hardware will be removed and replaced with doorsDetails
b1 - revision to 201903276418 to update card reader matrix, proviced card readers & emergency/door relaese buttons, panic hardware will be removed and replaced with doors | $1,000 |
| May 2, 2019 | Completed final sign-off Nov 2021 | 250 Howard St | Webcor Construction Lp | b2 - revision to 201903276415 to update card reader matrix, proviced card readers & emergency/door relaese buttons, panic hardware will be removed and replaced with doorsDetails
b2 - revision to 201903276415 to update card reader matrix, proviced card readers & emergency/door relaese buttons, panic hardware will be removed and replaced with doors | $1,000 |
| Apr 29, 2019 | Completed final sign-off Jul 2021 | 250 Howard St | Webcor Construction Lp | 28th fl - arch only. new kitchen and dining areas. construction of new non-structural partition, acoustical grid & tile gyp board ceiings, millwork finishes, fire alarm, sprinklers, ansul & mep on separate permitDetails
28th fl - arch only. new kitchen and dining areas. construction of new non-structural partition, acoustical grid & tile gyp board ceiings, millwork finishes, fire alarm, sprinklers, ansul & mep on separate permit | $1,315,440 |
| Apr 29, 2019 | Completed final sign-off Jul 2021 | 250 Howard St | Webcor Construction Lp | 25th fl - arch only. new kitchen and dining areas. construction of new non-structural partition, acoustical grid & tile gyp board ceiings, millwork finishes, fire alarm, sprinklers, ansul & mep on separate permitDetails
25th fl - arch only. new kitchen and dining areas. construction of new non-structural partition, acoustical grid & tile gyp board ceiings, millwork finishes, fire alarm, sprinklers, ansul & mep on separate permit | $1,315,440 |
| Apr 29, 2019 | Completed final sign-off Jul 2021 | 250 Howard St | Webcor Construction Lp | 26th fl - arch only. new kitchen and dining areas. construction of new non-structural partition, acoustical grid & tile gyp board ceiings, millwork finishes, fire alarm, sprinklers, ansul & mep on separate permitDetails
26th fl - arch only. new kitchen and dining areas. construction of new non-structural partition, acoustical grid & tile gyp board ceiings, millwork finishes, fire alarm, sprinklers, ansul & mep on separate permit | $1,315,440 |
| Apr 24, 2019 | Completed final sign-off Jun 2021 | 250 Howard St | Webcor Construction Lp | 23rd fl: construction of new non structural partitions aloustical grid tile, & gyp board and ceilings, light fixture, millwork and finishesDetails
23rd fl: construction of new non structural partitions aloustical grid tile, & gyp board and ceilings, light fixture, millwork and finishes | $1,800,000 |
| Apr 24, 2019 | Completed final sign-off Jul 2021 | 250 Howard St | Webcor Construction Lp | 24th fl fl: construction of new non structural partitions aloustical grid tile, & gyp board and ceilings, light fixture, millwork and finishes n/a maherDetails
24th fl fl: construction of new non structural partitions aloustical grid tile, & gyp board and ceilings, light fixture, millwork and finishes n/a maher | $1,800,000 |
| Apr 24, 2019 | Completed final sign-off Jun 2021 | 250 Howard St | Webcor Construction Lp | 21st floor: construction of new non structural partitions, acoustical grid, tile & gyp board ceiling, light fixtures & millwork and finishesDetails
21st floor: construction of new non structural partitions, acoustical grid, tile & gyp board ceiling, light fixtures & millwork and finishes | $1,800,000 |
| Apr 10, 2019 | Completed final sign-off Jun 2021 | 250 Howard St | Webcor Construction Lp | 20th flr - construction of new non structural partition, acoustical gride & tile & gyp board veilings,light fixtures, millwork and finishes. maher n/a.Details
20th flr - construction of new non structural partition, acoustical gride & tile & gyp board veilings,light fixtures, millwork and finishes. maher n/a. | $1,800,000 |
| Apr 10, 2019 | Completed final sign-off Jun 2021 | 250 Howard St | Webcor Construction Lp | 17th flr - construction of new non structural partition, acoustical gride & tile & gyp board veilings,., light fixtures, millwork and finishes. maher naDetails
17th flr - construction of new non structural partition, acoustical gride & tile & gyp board veilings,., light fixtures, millwork and finishes. maher na | $1,800,000 |
| Apr 10, 2019 | Completed final sign-off Jun 2021 | 250 Howard St | Webcor Construction Lp | 18th flr - construction of new non structural partitions, acoustical grid & tile & gyp board ceilings, light fixtures, millwork and finishes. maher naDetails
18th flr - construction of new non structural partitions, acoustical grid & tile & gyp board ceilings, light fixtures, millwork and finishes. maher na | $1,800,000 |
| Apr 10, 2019 | Completed final sign-off Jul 2021 | 250 Howard St | Webcor Construction Lp | 19th flr - construction of new non structural partition, acoustical gride & tile & gyp board veilings,., light fixtures, millwork and finishes. maher naDetails
19th flr - construction of new non structural partition, acoustical gride & tile & gyp board veilings,., light fixtures, millwork and finishes. maher na | $1,800,000 |
| Mar 22, 2019 | Completed final sign-off Jun 2021 | 250 Howard St | Webcor Construction Lp | new connecting feature stair between levels 11 & 12. ref t.i pa's 201903226017-11/f & 201903226019-12/fDetails
new connecting feature stair between levels 11 & 12. ref t.i pa's 201903226017-11/f & 201903226019-12/f | $619,000 |
| Mar 22, 2019 | Completed final sign-off Jun 2021 | 250 Howard St | Webcor Construction Lp | 12th fl - ti with new kitchen and servery. new bearing partitions, horizontal exiting, patio seating, fire alarm, sprinklers & convenience stairs on separate permitDetails
12th fl - ti with new kitchen and servery. new bearing partitions, horizontal exiting, patio seating, fire alarm, sprinklers & convenience stairs on separate permit | $3,800,000 |