Charles Zhou Hui Li
- Listed as
- architect, engineer
- Firm
- Miyamoto
- Based in
- San Francisco
- On San Francisco permits
- Nov 2019 to Oct 2024
12 permits since 2000 (engineer on 10 permits, architect on 2 permits): 5 completed, 1 in progress, 6 never finaled.
This is the city’s permit record, not a license check: the role and the number come from what was written on each permit (the number spelled one way). It does not show whether the license is current. How to read these records
Most recent permits
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Oct 29, 2024 | In progress filed Oct 2024, not yet issued | 2 Folsom St | 4th fl- installation of 6 single phone booths and associated electrical & structural. no change in occupancy, use or areaDetails
4th fl- installation of 6 single phone booths and associated electrical & structural. no change in occupancy, use or area | $100,000 | |
| Sep 28, 2023 | Completed final sign-off Apr 2024 | 2 Folsom St | Swinerton Builders | 9/f: revision to pa# 202307202579, reduced scope updated lighting & finishes, added equipmenmt & power locations, revised room layout, added structural details.Details
9/f: revision to pa# 202307202579, reduced scope updated lighting & finishes, added equipmenmt & power locations, revised room layout, added structural details. | |
| Sep 28, 2023 | Completed final sign-off May 2024 | 2 Folsom St | Swinerton Builders | 12/f: revision to pa# 202308295512, reduced scope of work no longer done in designed accessDetails
12/f: revision to pa# 202308295512, reduced scope of work no longer done in designed access | |
| Aug 29, 2023 | Never finaled issued Sep 2023, no final | 2 Folsom St | Swinerton Builders | 12/f - interior ti incudes new non-load bearing partitions, lighting, & finishes. mep deferred.Details
12/f - interior ti incudes new non-load bearing partitions, lighting, & finishes. mep deferred. | $717,000 |
| Dec 16, 2021 | Completed final sign-off May 2022 | 2 Folsom St | Swinerton Builders | 6th fl - revision to pa 2021-1007-0031 change of egress, additional structural scope and new partitionsDetails
6th fl - revision to pa 2021-1007-0031 change of egress, additional structural scope and new partitions | |
| Dec 16, 2021 | Completed final sign-off May 2022 | 2 Folsom St | Swinerton Builders | 8th fl - revision to pa 2021-0923-9023 additional structural scope and new partitionsDetails
8th fl - revision to pa 2021-0923-9023 additional structural scope and new partitions | |
| Jul 6, 2021 | Completed final sign-off Aug 2023 | 560 Powell St | Hathaway Dinwiddie Co. | replacement of existing elevator due to elevator failure. scope includes modernized elevator in existing shaft and new machine room per code requirements. this is a barrier removal project. mep and life safety deferred permitsDetails
replacement of existing elevator due to elevator failure. scope includes modernized elevator in existing shaft and new machine room per code requirements. this is a barrier removal project. mep and life safety deferred permits | $100,000 |
| Oct 15, 2020 | Never finaled filed Oct 2020, never issued | 2209 Van Ness Av | replace existing retaing wall approximate 40 lfDetails
replace existing retaing wall approximate 40 lf | $5,000 | |
| Mar 6, 2020 | Never finaled filed Mar 2020, never issued | 79 New Montgomery St | priority process - close and abate enforcement case #2015-013579. the project proposes to change the use of 77-79 new montgomery from the last legal use of general office to post-secondary educational institutional. work includes security cameras, new bike parking, exterior clean up.Details
priority process - close and abate enforcement case #2015-013579. the project proposes to change the use of 77-79 new montgomery from the last legal use of general office to post-secondary educational institutional. work includes security cameras, new bike parking, exterior clean up. | $65,000 | |
| Mar 2, 2020 | Never finaled filed Mar 2020, never issued | 601 Brannan St | priority process - pursuant to case #2008.0586, change use of 601 brannan to last legal use of general office to post-secondary educational institutinal. abate/close enforcement cases 9114 & 2015-012595. conditional use authorization requested to institute post-secondary educational services use inDetails
priority process - pursuant to case #2008.0586, change use of 601 brannan to last legal use of general office to post-secondary educational institutinal. abate/close enforcement cases 9114 & 2015-012595. conditional use authorization requested to institute post-secondary educational services use in | $75,000 | |
| Feb 28, 2020 | Never finaled filed Feb 2020, never issued | 180 New Montgomery St | priority process - abate / close enforcement case# 2015-013540. pursuant to case# 20080586, change of use from last legas use of general office to a post-secondary institution use. permit includes exterior work such as legalization of windows & panel replacement. bike parking added in bldg.Details
priority process - abate / close enforcement case# 2015-013540. pursuant to case# 20080586, change of use from last legas use of general office to a post-secondary institution use. permit includes exterior work such as legalization of windows & panel replacement. bike parking added in bldg. | $85,000 | |
| Nov 12, 2019 | Never finaled issued Nov 2019, no final | 550 Terry A Francois Bl | Bcci Construction Company | 6th floor: structural only deferred submittal for operable partition anchorage. reference pa# 2019-1028-5758Details
6th floor: structural only deferred submittal for operable partition anchorage. reference pa# 2019-1028-5758 |