Permit GraphShortlistSan Francisco building permits since 2000

Blake Dilsworth

License
S3929
Look the license up with the state
Listed as
engineer
Firm
Kpff Consulting Engineers
Based in
San Francisco
On San Francisco permits
Oct 2005 to Sep 2024

21 permits since 2000 (engineer on 21 permits): 14 completed, 1 in progress, 4 never finaled, 2 expired or cancelled.

CompletedIn progressNever finaledExpired or cancelled

This is the city’s permit record, not a license check: the role and the number come from what was written on each permit (the number spelled one way). It does not show whether the license is current. How to read these records

Most recent permits

FiledOutcomeAddressContractorWork described on the permitDeclared cost
Sep 20, 2024Completed
final sign-off May 2026
580 Beach StRdl Construction, Inc.building 1 and 2 (west) building. selective store front replacment , art displays, lighting, cosmetic repairs, railing repairs and upgrade. sharing plans with 500 beach st
Details
Permit
202409201298
Status
complete
Filed
Sep 20, 2024
Permit issued
Dec 27, 2024
Final sign-off
May 26, 2026
Declared cost
$1,700,000
Address
580 Beach St

building 1 and 2 (west) building. selective store front replacment , art displays, lighting, cosmetic repairs, railing repairs and upgrade. sharing plans with 500 beach st

Open the permit page

$1,700,000
Sep 20, 2024Completed
final sign-off May 2026
500 Beach StRdl Construction, Inc.garage (east) building. selective store front replacment , art displays, lighting, cosmetic repairs. sharing plans with 580 beach st
Details
Permit
202409201297
Status
complete
Filed
Sep 20, 2024
Permit issued
Dec 27, 2024
Final sign-off
May 21, 2026
Declared cost
$1,700,000
Address
500 Beach St

garage (east) building. selective store front replacment , art displays, lighting, cosmetic repairs. sharing plans with 580 beach st

Open the permit page

$1,700,000
Nov 7, 2022In progress
issued Sep 2024
2270 Mckinnon AvPlant Construction Co, Lpto erect a 5-story, type iiib & ia building. occupancy class b, s-1, f-1, s-2.
Details
Permit
202211076023
Status
issued
Filed
Nov 7, 2022
Permit issued
Sep 9, 2024
Declared cost
$20,000,000
Address
2270 Mckinnon Av

to erect a 5-story, type iiib & ia building. occupancy class b, s-1, f-1, s-2.

Open the permit page

$20,000,000
Nov 4, 2022Completed
final sign-off Mar 2024
48 Stockton StPlant Construction Co, Lp4/f: construction new non structural partitions, new operable partitions, new accoustical grid and tile and gyp bd ceilings, new finishes throughout. pantry millwork, equipment, and plumbing fixtures also included. mep and life safety deferred submittals
Details
Permit
202211045949
Status
complete
Filed
Nov 4, 2022
Permit issued
Dec 5, 2022
Final sign-off
Mar 15, 2024
Declared cost
$2,000,000
Address
48 Stockton St

4/f: construction new non structural partitions, new operable partitions, new accoustical grid and tile and gyp bd ceilings, new finishes throughout. pantry millwork, equipment, and plumbing fixtures also included. mep and life safety deferred submittals

Open the permit page

$2,000,000
Aug 17, 2022Completed
final sign-off Jul 2023
1012 Scott St(n) bathroom @ l1, (e) remodel of bedroom and l1 and (n) partial stair extention interior.
Details
Permit
202208170742
Status
complete
Filed
Aug 17, 2022
Permit issued
Jan 12, 2023
Final sign-off
Jul 26, 2023
Declared cost
$60,000
Address
1012 Scott St

(n) bathroom @ l1, (e) remodel of bedroom and l1 and (n) partial stair extention interior.

Open the permit page

$60,000
Jan 24, 2022Completed
final sign-off Sep 2023
360 Spear StHitt Contracting Inc.3rd fl: single floor tenant improvement. existing structure, egress staor enclosures to remain. non structural partitions, ceiling, wall and floor finishes only. related mechanical, electrical, plumbing workm change of use from office/internet service exchange to office /laboratory/wholesale sales.
Details
Permit
202201246538
Status
complete
Filed
Jan 24, 2022
Permit issued
May 18, 2022
Final sign-off
Sep 13, 2023
Declared cost
$5,000,000
Address
360 Spear St

3rd fl: single floor tenant improvement. existing structure, egress staor enclosures to remain. non structural partitions, ceiling, wall and floor finishes only. related mechanical, electrical, plumbing workm change of use from office/internet service exchange to office /laboratory/wholesale sales.

Open the permit page

$5,000,000
Apr 8, 2021Never finaled
issued Jan 2022, no final
120 Stockton StPlant Construction Co, Lpaddition of a scissor lift in the loading dock and (2) hour rated glazing on the north facade, level 6 & 7. revision to pa#201805048215 & #202008101490(arch) / #202008131716(str).
Details
Permit
202104088200
Status
issued
Filed
Apr 8, 2021
Permit issued
Jan 4, 2022
Declared cost
$50,000
Address
120 Stockton St

addition of a scissor lift in the loading dock and (2) hour rated glazing on the north facade, level 6 & 7. revision to pa#201805048215 & #202008101490(arch) / #202008131716(str).

Open the permit page

$50,000
Aug 13, 2020Never finaled
issued Feb 2021, no final
120 Stockton StPlant Construction Co, Lprevisions to bpa# 201805048215 addenda 2 structural - superstructure include the following: 1) new passenger elevator servicing levels 1-5. 2) mep shaft updates at the northwest mechanical room. 3) revised dead and live loading at levels 2-5.
Details
Permit
202008131716
Status
issued
Filed
Aug 13, 2020
Permit issued
Feb 1, 2021
Declared cost
$250,000
Address
120 Stockton St

revisions to bpa# 201805048215 addenda 2 structural - superstructure include the following: 1) new passenger elevator servicing levels 1-5. 2) mep shaft updates at the northwest mechanical room. 3) revised dead and live loading at levels 2-5.

Open the permit page

$250,000
Dec 28, 2015Completed
final sign-off Oct 2017
345 Spear StBcci Construction Company5th flr: partial floor t.i. including minor demolition,new partitions,finishes & associated mep, fire ls under separate permit; maher n/a
Details
Permit
201512285994
Status
complete
Filed
Dec 28, 2015
Permit issued
Jan 7, 2016
Final sign-off
Oct 4, 2017
Declared cost
$795,000
Address
345 Spear St

5th flr: partial floor t.i. including minor demolition,new partitions,finishes & associated mep, fire ls under separate permit; maher n/a

Open the permit page

$795,000
Dec 21, 2015Completed
final sign-off Aug 2016
1 Market StDpr Construction7th floor: structural work associated with arch permit #201511031519. work includes nelson stud welding. also new floating slab for acoustic purpose only (not structural). n/a for maher.
Details
Permit
201512215621
Status
complete
Filed
Dec 21, 2015
Permit issued
Dec 22, 2015
Final sign-off
Aug 30, 2016
Declared cost
$225,000
Address
1 Market St

7th floor: structural work associated with arch permit #201511031519. work includes nelson stud welding. also new floating slab for acoustic purpose only (not structural). n/a for maher.

Open the permit page

$225,000
Oct 7, 2015Completed
final sign-off Sep 2016
4 Embarcadero CenterGci, Increnovate and extend existing egress access stair between the 17/f & 18/f down to 16/f, removal of two (2) existing egress access stairs, all of which are not part of the required egress system. n/a ordinance #155-13
Details
Permit
201510079050
Status
complete
Filed
Oct 7, 2015
Permit issued
Oct 9, 2015
Final sign-off
Sep 27, 2016
Declared cost
$52,200
Address
4 Embarcadero Center

renovate and extend existing egress access stair between the 17/f & 18/f down to 16/f, removal of two (2) existing egress access stairs, all of which are not part of the required egress system. n/a ordinance #155-13

Open the permit page

$52,200
Jun 24, 2015Never finaled
issued Nov 2015, no final
625 Market StG Swanson Constr. Inc., Evans & Son Incremodel of (e) bank space including new 24 hour vestible, new millwork, walls, lighting and finishes as well as new bank equipment. no change to use or occupancy. mep included- sprinklers and fire alarm separate-
Details
Permit
201506249734
Status
issued
Filed
Jun 24, 2015
Permit issued
Nov 12, 2015
Declared cost
$1,200,000
Address
625 Market St

remodel of (e) bank space including new 24 hour vestible, new millwork, walls, lighting and finishes as well as new bank equipment. no change to use or occupancy. mep included- sprinklers and fire alarm separate-

Open the permit page

$1,200,000
Apr 23, 2015Completed
final sign-off Dec 2016
945 Market StSwinerton Builders, Plant Construction Co, Lprevision to pa#201011084497 s2 to modify super structure design due to infield conditions. design evalution changes include modification to brace line, slabs for fuel tanks and mechanical equipment, elevator & escalator openings. n/a ordinance #155-13
Details
Permit
201504234434
Status
complete
Filed
Apr 23, 2015
Permit issued
Apr 30, 2015
Final sign-off
Dec 19, 2016
Address
945 Market St

revision to pa#201011084497 s2 to modify super structure design due to infield conditions. design evalution changes include modification to brace line, slabs for fuel tanks and mechanical equipment, elevator & escalator openings. n/a ordinance #155-13

Open the permit page

Dec 17, 2014Expired or cancelled
cancelled Aug 2016
222 Mason StGoike Construction Managementlevel b1, b2 & b3- install (3) 5o-hp steam boilers to replace district steam source on level b2 within the existing valet parking garage and provide (4) parking lifts near new boiler enclosure. fire alarm, fire sprinkler, flue vent detail will be deferred submittal.
Details
Permit
201412173899
Status
cancelled
Filed
Dec 17, 2014
Permit issued
Dec 19, 2014
Declared cost
$200,000
Address
222 Mason St

level b1, b2 & b3- install (3) 5o-hp steam boilers to replace district steam source on level b2 within the existing valet parking garage and provide (4) parking lifts near new boiler enclosure. fire alarm, fire sprinkler, flue vent detail will be deferred submittal.

Open the permit page

$200,000
Feb 12, 2014Completed
final sign-off Jan 2015
50 03rd StPlant Construction Company Lpconvert 1 conference room on 33/f & 2 suites on 36/f into 7 guest rooms. work includes new showers, plumbing fixtures, finishes, millwork, partitions. electrical, plumbing, mechanical as required to complete the project scope. work also includes infill an (e) opening in 36/f structural slab.
Details
Permit
201402128356
Status
complete
Filed
Feb 12, 2014
Permit issued
Feb 24, 2014
Final sign-off
Jan 23, 2015
Declared cost
$210,000
Address
50 03rd St

convert 1 conference room on 33/f & 2 suites on 36/f into 7 guest rooms. work includes new showers, plumbing fixtures, finishes, millwork, partitions. electrical, plumbing, mechanical as required to complete the project scope. work also includes infill an (e) opening in 36/f structural slab.

Open the permit page

$210,000
Dec 13, 2012Completed
final sign-off Mar 2016
33 Powell StThe Hatch Group Incscope of work includes non-bearing interior partition walls, (n) floor finishes, (n) paint, (n) casework & furniture, electrical work, mechanical work & plumbing work.sprinkler and fire alarm permit on seperate permits. n/a ordinance #155-13
Details
Permit
201212136108
Status
complete
Filed
Dec 13, 2012
Permit issued
Feb 27, 2015
Final sign-off
Mar 30, 2016
Declared cost
$1,070,000
Address
33 Powell St

scope of work includes non-bearing interior partition walls, (n) floor finishes, (n) paint, (n) casework & furniture, electrical work, mechanical work & plumbing work.sprinkler and fire alarm permit on seperate permits. n/a ordinance #155-13

Open the permit page

$1,070,000
Apr 17, 2012Completed
final sign-off Oct 2012
400 Post StLorentz Bruun Co., Inc.rev to pa# 2011/11/01/8054. 3539 sqft interior t.i for a retail banking center, this project was previously approved/permited, but client asked gensler to redesign. project includes 24 hr atm vestiblue, sliding glass nanwall system, lobby, hospitality area for customers, teller line, offices,
Details
Permit
201204178495
Status
complete
Filed
Apr 17, 2012
Permit issued
May 2, 2012
Final sign-off
Oct 26, 2012
Address
400 Post St

rev to pa# 2011/11/01/8054. 3539 sqft interior t.i for a retail banking center, this project was previously approved/permited, but client asked gensler to redesign. project includes 24 hr atm vestiblue, sliding glass nanwall system, lobby, hospitality area for customers, teller line, offices,

Open the permit page

Oct 21, 2011Never finaled
issued Mar 2012, no final
400 Post StLorentz Bruun Co., Inc.building alteration - minor: replacement of storefront system, entrances & bulkhead, addition of canopy at corner of building. replace a portion of existing sidewalk in r.o.w. to meet accessibility codes.
Details
Permit
201110217364
Status
issued
Filed
Oct 21, 2011
Permit issued
Mar 15, 2012
Declared cost
$400,000
Address
400 Post St

building alteration - minor: replacement of storefront system, entrances & bulkhead, addition of canopy at corner of building. replace a portion of existing sidewalk in r.o.w. to meet accessibility codes.

Open the permit page

$400,000
Aug 24, 2011Expired or cancelled
cancelled Jan 2026
400 Howard Stnew starbucks t-i build out inside an existing shell building.construction of cafe front bar & back. construction of new partition walls & overhead soffit. relocation of 2 (e) doors. painting. installation of new flooring,new wall covering finishes.new furniture & casework. installation of new floor
Details
Permit
201108243151
Status
cancelled
Filed
Aug 24, 2011
Declared cost
$300,000
Address
400 Howard St

new starbucks t-i build out inside an existing shell building.construction of cafe front bar & back. construction of new partition walls & overhead soffit. relocation of 2 (e) doors. painting. installation of new flooring,new wall covering finishes.new furniture & casework. installation of new floor

Open the permit page

$300,000
Mar 5, 2007Completed
final sign-off Oct 2007
67 Turk Ststrucutral upgrade to existing parking lot, provide 3 handicap parking stalls 1 handicap van stall. modify handrails.
Details
Permit
200703055447
Status
complete
Filed
Mar 5, 2007
Permit issued
Apr 11, 2007
Final sign-off
Oct 4, 2007
Declared cost
$60,000
Address
67 Turk St

strucutral upgrade to existing parking lot, provide 3 handicap parking stalls 1 handicap van stall. modify handrails.

Open the permit page

$60,000
Oct 11, 2005Completed
final sign-off Jul 2006
345 California StGci, Incdemolition of 33rd/fl. conference room space and construction of convenience/non egress stair connecting to 32nd/fl.
Details
Permit
200510115180
Status
complete
Filed
Oct 11, 2005
Permit issued
Dec 27, 2005
Final sign-off
Jul 6, 2006
Declared cost
$200,000
Address
345 California St

demolition of 33rd/fl. conference room space and construction of convenience/non egress stair connecting to 32nd/fl.

Open the permit page

$200,000