26 permits since 2000: 22 completed, 2 never finaled, 2 expired or cancelled.
Of the 2 never-finaled permits, 2 are over 10 years old.
This is the city’s permit record, not a license check. It does not show whether the state license is active, bonded or insured. How to read these records
Permits filed each year
How long permits take
Each point is the quarter the permits were filed, for all building permits across San Francisco. A median counts only permits that have finished, so the shaded recent quarters look faster than they will end up: their slow permits have not finished yet. Hover a point for the slowest 10%. Gaps mean fewer than 5 permits. A rise in the issue line is the city’s review backlog, not the contractor.
Most recent permits
| Filed | Outcome | Address | Work described on the permit | Declared cost |
|---|---|---|---|---|
| Sep 21, 2016 | Completed final sign-off Nov 2016 | 151 Beaver St | to comply with physical inspection report #cc-8129.Details
to comply with physical inspection report #cc-8129. | $3,000 |
| Jan 26, 2016 | Completed final sign-off Feb 2016 | 8 Steuart St | super bowl city - install temp tent structure. install floor system w/ incorporated access comply - 1/28/16-2/10/2016. maher naDetails
super bowl city - install temp tent structure. install floor system w/ incorporated access comply - 1/28/16-2/10/2016. maher na | $5,000 |
| Jan 26, 2016 | Completed final sign-off Feb 2016 | 8 Steuart St | super bowl city - install temp tent structure. modified container, install access ramps- 1/28/16-2/10/2016. maher naDetails
super bowl city - install temp tent structure. modified container, install access ramps- 1/28/16-2/10/2016. maher na | $3,000 |
| Jan 22, 2016 | Completed final sign-off Feb 2016 | 1 Avenue Of The Palms | reference pa 2016-01136986, temporary platform (floor) - date from: 1/22/16 thru 2/9/2016. maher naDetails
reference pa 2016-01136986, temporary platform (floor) - date from: 1/22/16 thru 2/9/2016. maher na | $50,000 |
| Jan 20, 2016 | Completed final sign-off Feb 2016 | 8 Steuart St | super bowl city temp 1/22/16-2/11/16 -install 4 stage temp structures, tv transmission trucks, office maher naDetails
super bowl city temp 1/22/16-2/11/16 -install 4 stage temp structures, tv transmission trucks, office maher na | $100,000 |
| Jan 20, 2016 | Completed final sign-off Feb 2016 | 8 Steuart St | super bowl city temp 1/22/16-2/11/16 - install pre-fab tent structure and led board. maher naDetails
super bowl city temp 1/22/16-2/11/16 - install pre-fab tent structure and led board. maher na | $95,000 |
| Jan 20, 2016 | Completed final sign-off Feb 2016 | 8 Steuart St | super bowl city temp 1/22/16-2/11/16 - install container at various locations. commercial & kitchen containers maher naDetails
super bowl city temp 1/22/16-2/11/16 - install container at various locations. commercial & kitchen containers maher na | $5,000 |
| Jan 20, 2016 | Completed final sign-off Feb 2016 | 8 Steuart St | super bowl city temp 1/22/16-2/11/16 - build a modular steel archway that frames entrance to super bowl city maher naDetails
super bowl city temp 1/22/16-2/11/16 - build a modular steel archway that frames entrance to super bowl city maher na | $12,500 |
| Jan 20, 2016 | Completed final sign-off Feb 2016 | 8 Steuart St | super bowl city temp 1/22/16-2/11/16 - install cargo container remodeled for office occupancy . install deck & ramp maher naDetails
super bowl city temp 1/22/16-2/11/16 - install cargo container remodeled for office occupancy . install deck & ramp maher na | $3,000 |
| Jan 20, 2016 | Completed final sign-off Feb 2016 | 8 Steuart St | super bowl city temp 1/22/16-2/11/16 - install structure based on two cargo containers it is a walk thru assembly maher naDetails
super bowl city temp 1/22/16-2/11/16 - install structure based on two cargo containers it is a walk thru assembly maher na | $7,500 |
| Jan 20, 2016 | Completed final sign-off Feb 2016 | 8 Steuart St | super bowl city temp 1/22/16-2/11/16 - install temp structure and build a deck at front door, maher naDetails
super bowl city temp 1/22/16-2/11/16 - install temp structure and build a deck at front door, maher na | $12,000 |
| Jan 20, 2016 | Completed final sign-off Feb 2016 | 8 Steuart St | super bowl city temp 1/22/16-2/11/16 - install cargo container - remodeled for merchantile. temp maher naDetails
super bowl city temp 1/22/16-2/11/16 - install cargo container - remodeled for merchantile. temp maher na | $8,000 |
| Jan 20, 2016 | Completed final sign-off Feb 2016 | 8 Steuart St | super bowl city temp 1/22/16-2/11/16 - install pre-fab kiosks at 7 locations. maher naDetails
super bowl city temp 1/22/16-2/11/16 - install pre-fab kiosks at 7 locations. maher na | $3,000 |
| Jan 13, 2016 | Completed final sign-off Feb 2016 | 1 Avenue Of The Palms | lantier tent structures will be providing the tent (shell only) 131'x197' for the nfl's commisioners party at one avenue of the palms (parking lot)treasure island.installation 1/25/16-2/4/16 for an event date of 2/5/16, removal will take place from 2/6/16-2/9/16; maher n/aDetails
lantier tent structures will be providing the tent (shell only) 131'x197' for the nfl's commisioners party at one avenue of the palms (parking lot)treasure island.installation 1/25/16-2/4/16 for an event date of 2/5/16, removal will take place from 2/6/16-2/9/16; maher n/a | $18,000 |
| Sep 21, 2015 | Completed final sign-off Apr 2016 | 1821 Grant Av | kitchen remodel, fixtures & finishes only, no alteration of wall, window and door.Details
kitchen remodel, fixtures & finishes only, no alteration of wall, window and door. | $60,000 |
| Mar 26, 2015 | Completed final sign-off Dec 2015 | 4 Montezuma St | remodel 2 bathroms. no walls to be moved. finished & fixtures.Details
remodel 2 bathroms. no walls to be moved. finished & fixtures. | $30,000 |
| May 19, 2014 | Completed final sign-off Nov 2015 | 2830 20th St | comply w/complaints #201154589,201475903,201474431,201474371 -no final completion until permit 200806134352 is complete; sep mep permit; add ada bathrms & kitchenette, replace stairs, repair broken windows. add walls. (n) windows @ north elevation under separate permit. n/a maher ordinance 155-13.Details
comply w/complaints #201154589,201475903,201474431,201474371 -no final completion until permit 200806134352 is complete; sep mep permit; add ada bathrms & kitchenette, replace stairs, repair broken windows. add walls. (n) windows @ north elevation under separate permit. n/a maher ordinance 155-13. | $100,000 |
| Nov 24, 2004 | Never finaled issued Nov 2004, no final | 1821 Grant Av | remodel 2nd bathroom,new tile,sink tub & toilet.no structural work.other permit for 1st bathroomDetails
remodel 2nd bathroom,new tile,sink tub & toilet.no structural work.other permit for 1st bathroom | $5,000 |
| Nov 24, 2004 | Never finaled issued Nov 2004, no final | 1821 Grant Av | #301 - remodel 1st bathroom,new tile,shower pan,sink tub & toilet.no structural work.Details
#301 - remodel 1st bathroom,new tile,shower pan,sink tub & toilet.no structural work. | $5,000 |
| Oct 5, 2004 | Expired or cancelled expired Oct 2007 | 65 Burnett Av | reside with hardiplank concrete siding, 4 exterior wallsDetails
reside with hardiplank concrete siding, 4 exterior walls | $50,000 |
| Feb 10, 2003 | Completed final sign-off Feb 2003 | 2651 16th Av | renew#200203262382 for final inspectionDetails
renew#200203262382 for final inspection | |
| Dec 23, 2002 | Completed final sign-off Jan 2003 | 795 Rockdale Dr | to renew app#2002/03/26/2386 for final inspection.Details
to renew app#2002/03/26/2386 for final inspection. | |
| Dec 9, 2002 | Completed final sign-off Dec 2002 | 795 Rockdale Dr | revision to app #200203262385 for final inspectionDetails
revision to app #200203262385 for final inspection | $500 |
| Mar 26, 2002 | Expired or cancelled expired Dec 2002 | 795 Rockdale Dr | remodel basement, add a family room & a bathroom.new sheetrock, electrical & plumbingDetails
remodel basement, add a family room & a bathroom.new sheetrock, electrical & plumbing | $25,000 |
| Mar 26, 2002 | Completed final sign-off Feb 2003 | 2651 16th Av | remodel basement add a master bedroom, bathroom & storage rooms, new sheetrock, electrical & plumbinDetails
remodel basement add a master bedroom, bathroom & storage rooms, new sheetrock, electrical & plumbin | $35,000 |
| Mar 26, 2002 | Completed final sign-off Oct 2002 | 734 23rd Av | replacement of an existing deck. no increase in (e) deck footage area. replace one (e) door w/(n) wiDetails
replacement of an existing deck. no increase in (e) deck footage area. replace one (e) door w/(n) wi | $10,000 |