- 0 permits filed
4 permits since 2000: 2 completed, 2 never finaled.
Of the 2 never-finaled permits, 1 is 3 to 5 years old, 1 is 5 to 10 years old.
This is the city’s permit record, not a license check. It does not show whether the state license is active, bonded or insured. How to read these records
Permits filed each year
How long permits take
Each point is the quarter the permits were filed, for all building permits across San Francisco. A median counts only permits that have finished, so the shaded recent quarters look faster than they will end up: their slow permits have not finished yet. Hover a point for the slowest 10%. Gaps mean fewer than 5 permits. A rise in the issue line is the city’s review backlog, not the contractor. Too few of this contractor’s permits have finished to plot them.
Most recent permits
| Filed | Outcome | Address | Work described on the permit | Declared cost |
|---|---|---|---|---|
| Jun 26, 2023 | Never finaled issued Jul 2023, no final | 833 Mission St | repair of 7 stair traids and 3 small concrete spalls to be repaired (small section of stairs near basement, small section between floors 3-4). correction notice #202307575 issued by chris francis, cited code 102.a. repair in-kindDetails
repair of 7 stair traids and 3 small concrete spalls to be repaired (small section of stairs near basement, small section between floors 3-4). correction notice #202307575 issued by chris francis, cited code 102.a. repair in-kind | $8,500 |
| Mar 27, 2018 | Never finaled issued Aug 2018, no final | 285 Winston Dr | concrete spall repairs will be performed on the parking structure to existing ramp barriers will be replaced and designed per code, including post tension cable structural repairs.Details
concrete spall repairs will be performed on the parking structure to existing ramp barriers will be replaced and designed per code, including post tension cable structural repairs. | $322,750 |
| May 7, 2015 | Completed final sign-off Jun 2015 | 602 Mission St | 6th,9th and 10th floor: concrete patching at existing floor slabs. repair concrete spalls on topping slabs. no demolition/removal of existing framing members. maher n/a.Details
6th,9th and 10th floor: concrete patching at existing floor slabs. repair concrete spalls on topping slabs. no demolition/removal of existing framing members. maher n/a. | $150,000 |
| Aug 2, 2013 | Completed final sign-off Dec 2013 | 270 Cresta Vista Dr | repair concrete columns with carbon fiber fabric (sika wrap hex 103c). total 6 pier columns.Details
repair concrete columns with carbon fiber fabric (sika wrap hex 103c). total 6 pier columns. | $36,000 |