Walls Construction And Contracting Inc
- Based in
- San Anselmo
- On San Francisco permits
- Dec 2016 to Sep 2026
- Last 24 months
- 10 permits filed
18 permits since 2000: 9 completed, 9 in progress.
This is the city’s permit record, not a license check. It does not show whether the state license is active, bonded or insured. How to read these records
Permits filed each year
How long permits take
Each point is the quarter the permits were filed, for all building permits across San Francisco. A median counts only permits that have finished, so the shaded recent quarters look faster than they will end up: their slow permits have not finished yet. Hover a point for the slowest 10%. Gaps mean fewer than 5 permits. A rise in the issue line is the city’s review backlog, not the contractor.
Most recent permits
| Filed | Outcome | Address | Work described on the permit | Declared cost |
|---|---|---|---|---|
| Sep 10, 2026 | In progress issued Sep 2026 | 144 02nd St | 2&3/fl ti work to replace (e) breakroom to include (n) non bearing wall and applicances.Details
2&3/fl ti work to replace (e) breakroom to include (n) non bearing wall and applicances. | $45,500 |
| Aug 31, 2026 | In progress issued Sep 2026 | 370 Townsend St | tenant interior work at ground floor & basement, adding new non-bearing interior partition walls, kitchenettes, cleaned up finishes, existing restroom plumbing fixtures and finishes to be replaced in kind.Details
tenant interior work at ground floor & basement, adding new non-bearing interior partition walls, kitchenettes, cleaned up finishes, existing restroom plumbing fixtures and finishes to be replaced in kind. | $128,545 |
| Jun 26, 2026 | In progress issued Jul 2026 | 55 New Montgomery St | floors 3,5,6,7 & 8: m.e.p permit for bpa 202601214251 and 202603026767.Details
floors 3,5,6,7 & 8: m.e.p permit for bpa 202601214251 and 202603026767. | $48,500 |
| May 22, 2026 | In progress issued Jun 2026 | 61 New Montgomery St | ground floor/mezzanine improvements, add restrooms/kitchenette, non-bearing partions, to ground floor, add kitchenette/snack counters and non-bearing partitions to mezzanine (no catering service)Details
ground floor/mezzanine improvements, add restrooms/kitchenette, non-bearing partions, to ground floor, add kitchenette/snack counters and non-bearing partitions to mezzanine (no catering service) | $85,000 |
| Mar 2, 2026 | In progress issued Mar 2026 | 55 New Montgomery St | remove non-compliant convenience stair 3 add non-bearing office partition @ floors 3,5,6,7 & 8. no change of use on office floorsDetails
remove non-compliant convenience stair 3 add non-bearing office partition @ floors 3,5,6,7 & 8. no change of use on office floors | $210,500 |
| Jan 21, 2026 | In progress issued Jan 2026 | 55 New Montgomery St | floors 3,5,6,7 & 8 revision to pa #2025-1223-2562: modified restroom layoutDetails
floors 3,5,6,7 & 8 revision to pa #2025-1223-2562: modified restroom layout | |
| Dec 23, 2025 | In progress issued Jan 2026 | 55 New Montgomery St | 3,5,6,7,8th/f: identical t.i. new men's/women's restrooms, kitchenette/snack for office use only. interior work onlyDetails
3,5,6,7,8th/f: identical t.i. new men's/women's restrooms, kitchenette/snack for office use only. interior work only | $210,000 |
| Jan 10, 2025 | Completed final sign-off Feb 2025 | 550 03rd St | interior work offices 1st and 2nd floor. mechanical and electrical. mep deferred portion for ref app # 202412136809.Details
interior work offices 1st and 2nd floor. mechanical and electrical. mep deferred portion for ref app # 202412136809. | $10,000 |
| Dec 13, 2024 | Completed final sign-off Feb 2025 | 550 03rd St | interior work only, new non-bearing storefront system for office at 1st & 2nd floor. mep deferred.Details
interior work only, new non-bearing storefront system for office at 1st & 2nd floor. mep deferred. | $38,000 |
| Nov 12, 2024 | Completed final sign-off Feb 2025 | 550 03rd St | electrical lighting title - 24. ref pa#202302061449Details
electrical lighting title - 24. ref pa#202302061449 | $60,000 |
| Apr 25, 2024 | In progress issued Jul 2024 | 156 02nd St | new observation deck at extg roof level.Details
new observation deck at extg roof level. | $63,000 |
| Apr 10, 2024 | In progress issued Apr 2024 | 185 Clara St | obtain final inspection for work approved under 200708311568. all work is complete.Details
obtain final inspection for work approved under 200708311568. all work is complete. | |
| Nov 7, 2023 | Completed final sign-off Nov 2023 | 880 Harrison St | revision to permit 202202158047. clarification of metal screen shape.Details
revision to permit 202202158047. clarification of metal screen shape. | |
| Jun 14, 2023 | Completed final sign-off Feb 2025 | 550 03rd St | replace (e) tiered platform, (4) new interior walkable skylight at (e) 2nd fl (interior work only)Details
replace (e) tiered platform, (4) new interior walkable skylight at (e) 2nd fl (interior work only) | $87,000 |
| Mar 24, 2023 | Completed final sign-off Feb 2025 | 550 03rd St | replace (e) stair at lobby, new interior partitions & new floor infill @ 2nd fl, at (e) double height spacesDetails
replace (e) stair at lobby, new interior partitions & new floor infill @ 2nd fl, at (e) double height spaces | $133,000 |
| Feb 6, 2023 | Completed final sign-off Feb 2025 | 550 03rd St | new elevator and stairs to the roof with a new roof deck and penthouse. reinstate the windows and garage doors on the rear facade, adding fixed property line windows.Details
new elevator and stairs to the roof with a new roof deck and penthouse. reinstate the windows and garage doors on the rear facade, adding fixed property line windows. | $177,000 |
| Nov 3, 2021 | Completed final sign-off Aug 2022 | 95 Minna St | revision to pa#2015-0525-9973, remove the 1st floor restroom work for this vacant space in order for pa#2015-0525-9973 to be finalled. accessible restrooms will be installed under the next tenants future tenant improvement. per ab-107Details
revision to pa#2015-0525-9973, remove the 1st floor restroom work for this vacant space in order for pa#2015-0525-9973 to be finalled. accessible restrooms will be installed under the next tenants future tenant improvement. per ab-107 | |
| Dec 15, 2016 | Completed final sign-off Nov 2018 | 898 Pennsylvania Av | to comply with nov 201525463: remove trailers. upgrade van accessible parking stall. maher naDetails
to comply with nov 201525463: remove trailers. upgrade van accessible parking stall. maher na | $5,000 |