- 0 permits filed
18 permits since 2000: 14 completed, 2 never finaled, 2 expired or cancelled.
Of the 2 never-finaled permits, 1 is 3 to 5 years old, 1 is 5 to 10 years old.
This is the city’s permit record, not a license check. It does not show whether the state license is active, bonded or insured. How to read these records
Permits filed each year
How long permits take
Each point is the quarter the permits were filed, for all building permits across San Francisco. A median counts only permits that have finished, so the shaded recent quarters look faster than they will end up: their slow permits have not finished yet. Hover a point for the slowest 10%. Gaps mean fewer than 5 permits. A rise in the issue line is the city’s review backlog, not the contractor.
Most recent permits
| Filed | Outcome | Address | Work described on the permit | Declared cost |
|---|---|---|---|---|
| Jul 22, 2024 | Completed final sign-off Apr 2025 | 528 Bryant St | revision to pa# 2023-0428-6756 pony wall detail with simpson rckw3 @ 24" o.c and storefront entry section concrete detail for new slab with #5 rebar @ 12" o.c each wayDetails
revision to pa# 2023-0428-6756 pony wall detail with simpson rckw3 @ 24" o.c and storefront entry section concrete detail for new slab with #5 rebar @ 12" o.c each way | $2,500 |
| Feb 12, 2024 | Completed final sign-off Mar 2024 | 815 Burnett Av | replace header above fire exit door at second floor and repair framing around fire exit door leading to laundry room. repairs to be performed in-kind.Details
replace header above fire exit door at second floor and repair framing around fire exit door leading to laundry room. repairs to be performed in-kind. | $10,000 |
| Apr 28, 2023 | Completed final sign-off Apr 2025 | 528 Bryant St | change of land use from sales & service, nonretail - wholesale to office. building renovation for change of use including; alteration of facade for transparency by new glazing for lobby entry, (e) garage door to remain as loading area, interior demarkation of lobby from office space #1 with half ...Details
change of land use from sales & service, nonretail - wholesale to office. building renovation for change of use including; alteration of facade for transparency by new glazing for lobby entry, (e) garage door to remain as loading area, interior demarkation of lobby from office space #1 with half ... | |
| Nov 2, 2021 | Completed final sign-off Jan 2023 | 283 Bright St | one kitchen remodel in kind. led light fixtures in kitchen area. install 3 retrofit windows: 1 street facing and 2 in the back of building. upgrade electrical panel to 200a. replace furnace in garage with new one. install condensed tankless water heater in garage. milgard aluminum casements at frontDetails
one kitchen remodel in kind. led light fixtures in kitchen area. install 3 retrofit windows: 1 street facing and 2 in the back of building. upgrade electrical panel to 200a. replace furnace in garage with new one. install condensed tankless water heater in garage. milgard aluminum casements at front | $40,000 |
| Apr 28, 2021 | Expired or cancelled cancelled Jan 2026 | 130 Excelsior Av | re-stucco only the front elevation of residence second level only. approx 180 sqft.Details
re-stucco only the front elevation of residence second level only. approx 180 sqft. | $4,500 |
| Mar 9, 2021 | Never finaled issued Nov 2021, no final | 917 Cayuga Av | erect (1) car detached private parking garage.Details
erect (1) car detached private parking garage. | $60,000 |
| Jan 28, 2021 | Completed final sign-off Jul 2021 | 405 Lisbon St | replace windows visible from street with fiberglass woodclad windows. provide landscaping and permiable surface at front set back.Details
replace windows visible from street with fiberglass woodclad windows. provide landscaping and permiable surface at front set back. | $13,000 |
| Nov 3, 2020 | Completed final sign-off Feb 2021 | 1024 Alabama St | revision to pa# 202010146470. demo wall on 2nd fl.Details
revision to pa# 202010146470. demo wall on 2nd fl. | $7,500 |
| Oct 14, 2020 | Completed final sign-off Feb 2021 | 1024 Alabama St | remodel bathroom - install bath tub, new flooring, led lights, gfci outlets, new 110 cfm fan w/ occupancy sensor, new toilet, fixtures, tile, upgrade electrical panel, ceramic floor in kitchen, hardwood floor at 2nd flr throughout, upgrade plumbing, install electric heatersDetails
remodel bathroom - install bath tub, new flooring, led lights, gfci outlets, new 110 cfm fan w/ occupancy sensor, new toilet, fixtures, tile, upgrade electrical panel, ceramic floor in kitchen, hardwood floor at 2nd flr throughout, upgrade plumbing, install electric heaters | $65,000 |
| Jan 28, 2020 | Completed final sign-off Jun 2021 | 1234 Plymouth Av | renovate (e) kitchen to include; replace (e) cabinets & counter, build new pantry in the kitchen. replace the wall between the kitchen & dining room w/header beam. replace (e) kitchen window. upgrade kitchen electrical & plumbing as neededDetails
renovate (e) kitchen to include; replace (e) cabinets & counter, build new pantry in the kitchen. replace the wall between the kitchen & dining room w/header beam. replace (e) kitchen window. upgrade kitchen electrical & plumbing as needed | $25,000 |
| Dec 3, 2019 | Expired or cancelled cancelled Dec 2019 | 130 Excelsior Av | reroofingDetails
reroofing | $4,500 |
| Nov 15, 2019 | Completed final sign-off Nov 2019 | 400 38th Av | reroofingDetails
reroofing | $5,500 |
| Nov 14, 2019 | Never finaled issued Dec 2019, no final | 130 Excelsior Av | 1st floor: add family room, bathroom no shower, closet, laundry room, re-wire elec. upgrade, box 200amp, led recessed lights, fan, speakers, ww-replcae in kind dual pane epoxy. 2nd flr: kitchen remodel cabinets, appliances,island. guest bath upgrade in-kind. master bath remodel. install elec.Details
1st floor: add family room, bathroom no shower, closet, laundry room, re-wire elec. upgrade, box 200amp, led recessed lights, fan, speakers, ww-replcae in kind dual pane epoxy. 2nd flr: kitchen remodel cabinets, appliances,island. guest bath upgrade in-kind. master bath remodel. install elec. | $30,000 |
| Jun 21, 2019 | Completed final sign-off Aug 2019 | 269 Romain St | 2nd flr bath remodel. remove closet & extend shower area. relocate toilet. upgrade all fixtures, led lights, gfci outlets, occupancy sensor fan, install bathtub, build pony wall, install floors wall tile, new drain, faucet, spout, shower door, shower head.Details
2nd flr bath remodel. remove closet & extend shower area. relocate toilet. upgrade all fixtures, led lights, gfci outlets, occupancy sensor fan, install bathtub, build pony wall, install floors wall tile, new drain, faucet, spout, shower door, shower head. | $15,000 |
| Mar 15, 2019 | Completed final sign-off Jun 2019 | 125 Elmira St | converting bathtub to shower & remodeling bathroom on upper level redoing title increasing height at shower head installing new vanity and an electric toilet no change in wall layout and window and door openings.Details
converting bathtub to shower & remodeling bathroom on upper level redoing title increasing height at shower head installing new vanity and an electric toilet no change in wall layout and window and door openings. | $8,000 |
| Nov 28, 2018 | Completed final sign-off Jan 2020 | 1127 Wisconsin St | build a closet at 1st flr behind bathroom. install floor at closet, upgrade main electrical service of house to atleast 300a. install 2 (n) breakers in both (e) meter panels and 1 (n) house meter at garage. install recess lights, install 2 distribution subpanels at 2nd flr and 1 at 3rd flr.Details
build a closet at 1st flr behind bathroom. install floor at closet, upgrade main electrical service of house to atleast 300a. install 2 (n) breakers in both (e) meter panels and 1 (n) house meter at garage. install recess lights, install 2 distribution subpanels at 2nd flr and 1 at 3rd flr. | $10,500 |
| Nov 21, 2018 | Completed final sign-off Dec 2018 | 734 21st Av | reroofingDetails
reroofing | $4,000 |
| Jul 9, 2018 | Completed final sign-off Oct 2018 | 811 Shrader St | master bath upgrade like for like, replace tub, shower fixtures, vanity, sinks, flooring. hallway 1/2 bath upgrade toilet. kitchen/lavatory area; new washer/dryer install, new fridge, new convection oven, new flooring. building 2 walls in kitchenDetails
master bath upgrade like for like, replace tub, shower fixtures, vanity, sinks, flooring. hallway 1/2 bath upgrade toilet. kitchen/lavatory area; new washer/dryer install, new fridge, new convection oven, new flooring. building 2 walls in kitchen | $55,000 |