6 permits since 2000: 2 completed, 4 in progress.
This is the city’s permit record, not a license check. It does not show whether the state license is active, bonded or insured. How to read these records
Permits filed each year
How long permits take
Each point is the quarter the permits were filed, for all building permits across San Francisco. A median counts only permits that have finished, so the shaded recent quarters look faster than they will end up: their slow permits have not finished yet. Hover a point for the slowest 10%. Gaps mean fewer than 5 permits. A rise in the issue line is the city’s review backlog, not the contractor. Too few of this contractor’s permits have finished to plot them.
Most recent permits
| Filed | Outcome | Address | Work described on the permit | Declared cost |
|---|---|---|---|---|
| Dec 12, 2025 | In progress issued Dec 2025 | 610 Shotwell St | revision to pa #2025-1031-8655. install new nfpa 13, wet pipe automatic fire sprinkler system on the 4th fl level to a 455 sqft in a 4 story building. install a new a 4" dedicated underground service.Details
revision to pa #2025-1031-8655. install new nfpa 13, wet pipe automatic fire sprinkler system on the 4th fl level to a 455 sqft in a 4 story building. install a new a 4" dedicated underground service. | $10,000 |
| Oct 31, 2025 | In progress issued Nov 2025 | 610 Shotwell St | install a new nfpa 13, wet pipe, automatic fire sprinkler system on the ground level to convert 550 into adu ona 4 story building. install a new 2' dedicated underground fire serviceDetails
install a new nfpa 13, wet pipe, automatic fire sprinkler system on the ground level to convert 550 into adu ona 4 story building. install a new 2' dedicated underground fire service | $20,000 |
| Oct 23, 2025 | Completed final sign-off Mar 2026 | 866 38th Av | reference to fire sprinkler permit 202507030139. revised calculations to avoid installing underground.Details
reference to fire sprinkler permit 202507030139. revised calculations to avoid installing underground. | |
| Jul 3, 2025 | Completed final sign-off Mar 2026 | 866 38th Av | install a new nfpa 13r-wet pipe, automatic fire sprinkler system on the ground level to convert 583 into adu on a 3 story building. installation of new 2" dedicated underground fire service. dedicated underground will be done on separate permit. ref pa 202308315739Details
install a new nfpa 13r-wet pipe, automatic fire sprinkler system on the ground level to convert 583 into adu on a 3 story building. installation of new 2" dedicated underground fire service. dedicated underground will be done on separate permit. ref pa 202308315739 | $10,000 |
| Nov 20, 2023 | In progress issued Jan 2024 | 2782 Folsom St | installation of a addition new f/s systemDetails
installation of a addition new f/s system | $10,000 |
| Nov 15, 2023 | In progress issued May 2024 | 1750 Sacramento St | installation of new fire sprinkler system. nfpa 13 standard only on ground floor due to addition of adu. underground included. ref arch #2019-0710-5566Details
installation of new fire sprinkler system. nfpa 13 standard only on ground floor due to addition of adu. underground included. ref arch #2019-0710-5566 | $10,000 |