Permit GraphShortlistSan Francisco building permits since 2000

Tutor Perini Corporation

Contractor license
92072
State license record
Based in
Sylmar
On San Francisco permits
Apr 2012 to Jun 2022
Last 24 months
0 permits filed

19 permits since 2000: 11 completed, 7 never finaled, 1 expired or cancelled.

Of the 7 never-finaled permits, 1 is 3 to 5 years old, 4 are 5 to 10 years old, 2 are over 10 years old.

CompletedIn progressNever finaledExpired or cancelled

This is the city’s permit record, not a license check. It does not show whether the state license is active, bonded or insured. How to read these records

Permits filed each year

How long permits take

Median days to final inspection, citywideMedian days to permit issued, citywideThis contractor’s finished permits

Each point is the quarter the permits were filed, for all building permits across San Francisco. A median counts only permits that have finished, so the shaded recent quarters look faster than they will end up: their slow permits have not finished yet. Hover a point for the slowest 10%. Gaps mean fewer than 5 permits. A rise in the issue line is the city’s review backlog, not the contractor.

Most recent permits

All
FiledOutcomeAddressWork described on the permitDeclared cost
Jun 10, 2022Completed
final sign-off Jul 2022
220 Geary Stto obtain final inspection for work approved under pa# 201905301968. all work is complete.
Details
Permit
202206106100
Status
complete
Filed
Jun 10, 2022
Permit issued
Jun 14, 2022
Final sign-off
Jul 13, 2022
Address
220 Geary St

to obtain final inspection for work approved under pa# 201905301968. all work is complete.

Open the permit page

Jan 27, 2022Never finaled
issued Apr 2022, no final
266 04th Stmodify permit for central subway yerba buena moscone station to accommodate anchor bolts in foundation for future public art sculpture. foundation for sculpture added as an extension to stuctural beams under pa# 202106102139
Details
Permit
202201276841
Status
issued
Filed
Jan 27, 2022
Permit issued
Apr 29, 2022
Declared cost
$25,000
Address
266 04th St

modify permit for central subway yerba buena moscone station to accommodate anchor bolts in foundation for future public art sculpture. foundation for sculpture added as an extension to stuctural beams under pa# 202106102139

Open the permit page

$25,000
Jun 10, 2021Never finaled
issued Jun 2021, no final
266 04th Stmodify permit for central subway yerba buena moscone station to accommodate future public art sculpture. foundation for sculpture added as an extension to structural beams. waterproofing amended to be located unerneath concrete topping slab. ref pa 201209190112.
Details
Permit
202106102139
Status
issued
Filed
Jun 10, 2021
Permit issued
Jun 28, 2021
Declared cost
$125,000
Address
266 04th St

modify permit for central subway yerba buena moscone station to accommodate future public art sculpture. foundation for sculpture added as an extension to structural beams. waterproofing amended to be located unerneath concrete topping slab. ref pa 201209190112.

Open the permit page

$125,000
Dec 7, 2020Never finaled
issued Jan 2021, no final
933 Stockton St6" di cement lined underground fire line (9.3 feet), muni china town station
Details
Permit
202012070410
Status
issued
Filed
Dec 7, 2020
Permit issued
Jan 29, 2021
Declared cost
$2,000
Address
933 Stockton St

6" di cement lined underground fire line (9.3 feet), muni china town station

Open the permit page

$2,000
Nov 12, 2020Never finaled
issued Apr 2021, no final
266 04th Stinstall new fire department connection that connects to (e) central subway 6" standpipe system. location of street level fdc is near 460 04th st. sffd phone system under f/a permit.
Details
Permit
202011128766
Status
issued
Filed
Nov 12, 2020
Permit issued
Apr 6, 2021
Address
266 04th St

install new fire department connection that connects to (e) central subway 6" standpipe system. location of street level fdc is near 460 04th st. sffd phone system under f/a permit.

Open the permit page

May 30, 2019Completed
final sign-off Jul 2022
220 Geary Stunderground dedicated fire water line to be 8" ductile iron cement lined pipe for ums station approx 1 length. ref pa 2017-0413-3879 (sprinklers) and 2012-0510-0184 (arch)
Details
Permit
201905301968
Status
complete
Filed
May 30, 2019
Permit issued
May 30, 2019
Final sign-off
Jul 13, 2022
Declared cost
$2,000
Address
220 Geary St

underground dedicated fire water line to be 8" ductile iron cement lined pipe for ums station approx 1 length. ref pa 2017-0413-3879 (sprinklers) and 2012-0510-0184 (arch)

Open the permit page

$2,000
Nov 30, 2018Completed
final sign-off Feb 2022
266 04th Stfire line service (underground) from street to building
Details
Permit
201811307186
Status
complete
Filed
Nov 30, 2018
Permit issued
Dec 3, 2018
Final sign-off
Feb 3, 2022
Declared cost
$1,000
Address
266 04th St

fire line service (underground) from street to building

Open the permit page

$1,000
Sep 29, 2016Completed
final sign-off Sep 2022
333 Post Strevision to 2012-0510-0184 due to field issues & unforseen conditions - construct garage ramp; demolition of (e) garage columns (partial) to accommodate new garage. the submitted plans are revisions to the approved; n/a maher ord
Details
Permit
201609299207
Status
complete
Filed
Sep 29, 2016
Permit issued
Nov 22, 2016
Final sign-off
Sep 15, 2022
Declared cost
$50,000
Address
333 Post St

revision to 2012-0510-0184 due to field issues & unforseen conditions - construct garage ramp; demolition of (e) garage columns (partial) to accommodate new garage. the submitted plans are revisions to the approved; n/a maher ord

Open the permit page

$50,000
Aug 8, 2016Expired or cancelled
cancelled Jan 2026
220 Geary Strevision to pa #201205100184 - revised plumbing drawing - addition of piping for water proofing system within union square plaza.
Details
Permit
201608084439
Status
cancelled
Filed
Aug 8, 2016
Declared cost
$10,000
Address
220 Geary St

revision to pa #201205100184 - revised plumbing drawing - addition of piping for water proofing system within union square plaza.

Open the permit page

$10,000
May 25, 2016Never finaled
issued Jan 2017, no final
933 Stockton Strevision to pa #201204037405, addition of plaza level on top of existing (currently under construction) transit station. ref pa 201204037405
Details
Permit
201605258285
Status
issued
Filed
May 25, 2016
Permit issued
Jan 23, 2017
Declared cost
$3,500,000
Address
933 Stockton St

revision to pa #201204037405, addition of plaza level on top of existing (currently under construction) transit station. ref pa 201204037405

Open the permit page

$3,500,000
Sep 26, 2013Completed
final sign-off Oct 2013
1200 Carroll Avprovide a temporary commercial office trailer. install foundation system for commercial coach trailer. install ada parking space (van) w/access area & ramp leading into structure.
Details
Permit
201309267843
Status
complete
Filed
Sep 26, 2013
Permit issued
Sep 27, 2013
Final sign-off
Oct 4, 2013
Declared cost
$7,000
Address
1200 Carroll Av

provide a temporary commercial office trailer. install foundation system for commercial coach trailer. install ada parking space (van) w/access area & ramp leading into structure.

Open the permit page

$7,000
Aug 8, 2013Never finaled
issued Aug 2013, no final
530 Bush St3rd/4th floors-revision to pa# 2013-0708-1340-construction of new non bearing walls, ceiling to remain exposed (e). new dropped ceiling where indicated on plans. 1 hour rated wall at 4th floor it room
Details
Permit
201308083784
Status
issued
Filed
Aug 8, 2013
Permit issued
Aug 28, 2013
Address
530 Bush St

3rd/4th floors-revision to pa# 2013-0708-1340-construction of new non bearing walls, ceiling to remain exposed (e). new dropped ceiling where indicated on plans. 1 hour rated wall at 4th floor it room

Open the permit page

Jul 10, 2013Completed
final sign-off Feb 2014
530 Bush St1st/3rd & 4th floors-barrier removal improvement at restrooms; (both men & women's room)
Details
Permit
201307101466
Status
complete
Filed
Jul 10, 2013
Permit issued
Jul 11, 2013
Final sign-off
Feb 10, 2014
Declared cost
$50,000
Address
530 Bush St

1st/3rd & 4th floors-barrier removal improvement at restrooms; (both men & women's room)

Open the permit page

$50,000
Jul 8, 2013Completed
final sign-off Feb 2014
530 Bush St1st/3rd/4th floors-cosntruction of new non bearing partition walls, new dropped ceiling, doors, casework, finishes. mep separate permit
Details
Permit
201307081340
Status
complete
Filed
Jul 8, 2013
Permit issued
Jul 11, 2013
Final sign-off
Feb 10, 2014
Declared cost
$480,000
Address
530 Bush St

1st/3rd/4th floors-cosntruction of new non bearing partition walls, new dropped ceiling, doors, casework, finishes. mep separate permit

Open the permit page

$480,000
Oct 4, 2012Completed
final sign-off Oct 2025
933 Stockton Stdemolition of one commercial building for central sub-way.
Details
Permit
201210041288
Status
complete
Filed
Oct 4, 2012
Permit issued
Aug 23, 2013
Final sign-off
Oct 9, 2025
Declared cost
$238,091
Address
933 Stockton St

demolition of one commercial building for central sub-way.

Open the permit page

$238,091
Sep 19, 2012Completed
final sign-off May 2023
266 04th Stdemolish 1 story, type 5 gas station.
Details
Permit
201209190145
Status
complete
Filed
Sep 19, 2012
Permit issued
Aug 23, 2013
Final sign-off
May 8, 2023
Declared cost
$200,000
Address
266 04th St

demolish 1 story, type 5 gas station.

Open the permit page

$200,000
Sep 19, 2012Completed
final sign-off Jun 2025
266 04th Sterect central transit subway station.
Details
Permit
201209190112
Status
complete
Filed
Sep 19, 2012
Permit issued
Jul 19, 2013
Final sign-off
Jun 13, 2025
Declared cost
$38,314,494
Address
266 04th St

erect central transit subway station.

Open the permit page

$38,314,494
May 10, 2012Completed
final sign-off Jul 2025
220 Geary Stpartial demolition of union square plaza and garage, construction of new central subway union square/market street station entrance.
Details
Permit
201205100184
Status
complete
Filed
May 10, 2012
Permit issued
Jul 19, 2013
Final sign-off
Jul 1, 2025
Declared cost
$16,126,562
Address
220 Geary St

partial demolition of union square plaza and garage, construction of new central subway union square/market street station entrance.

Open the permit page

$16,126,562
Apr 3, 2012Never finaled
issued Jul 2013, no final
933 Stockton Sterect central t subway chinatown station. address: 933, 935, 937, 939, 941, 943, 945, 947, 949 stockton street
Details
Permit
201204037405
Status
issued
Filed
Apr 3, 2012
Permit issued
Jul 19, 2013
Declared cost
$69,970,683
Address
933 Stockton St

erect central t subway chinatown station. address: 933, 935, 937, 939, 941, 943, 945, 947, 949 stockton street

Open the permit page

$69,970,683