Thyssenkrupp Elevator Corp.
- Based in
- San Francisco
- On San Francisco permits
- Dec 2008 to Dec 2020
- Last 24 months
- 0 permits filed
5 permits since 2000: 1 completed, 4 never finaled.
Of the 4 never-finaled permits, 1 is 5 to 10 years old, 3 are over 10 years old. 1 was filed but never issued.
This is the city’s permit record, not a license check. It does not show whether the state license is active, bonded or insured. How to read these records
Permits filed each year
How long permits take
Each point is the quarter the permits were filed, for all building permits across San Francisco. A median counts only permits that have finished, so the shaded recent quarters look faster than they will end up: their slow permits have not finished yet. Hover a point for the slowest 10%. Gaps mean fewer than 5 permits. A rise in the issue line is the city’s review backlog, not the contractor. Too few of this contractor’s permits have finished to plot them.
Most recent permits
| Filed | Outcome | Address | Work described on the permit | Declared cost |
|---|---|---|---|---|
| Dec 11, 2020 | Never finaled filed Dec 2020, never issued | 1550 Bryant St | removal of fire sprinklers at top of elevator hoistway and elevator machine room. due to elevator modernization. in compliance with addendum f submittal.Details
removal of fire sprinklers at top of elevator hoistway and elevator machine room. due to elevator modernization. in compliance with addendum f submittal. | $5,000 |
| Apr 27, 2015 | Never finaled issued Jun 2015, no final | 505 Montgomery St | floors 1, 3 thru 12 : upgrade three elevators w/ destination dispatch low rise 1-12 elevators. n/a maher ordinanceDetails
floors 1, 3 thru 12 : upgrade three elevators w/ destination dispatch low rise 1-12 elevators. n/a maher ordinance | $50,000 |
| Jun 9, 2014 | Never finaled issued Jun 2014, no final | 60 Spear St | upgrade of elevator system to destination based elevator dispatching. all work & operation complies with sf administrative bulletin 090. all public signage for elevators complies with s.f. ab-090. n/a ordinance #155-13.Details
upgrade of elevator system to destination based elevator dispatching. all work & operation complies with sf administrative bulletin 090. all public signage for elevators complies with s.f. ab-090. n/a ordinance #155-13. | $35,000 |
| Oct 20, 2010 | Completed final sign-off Apr 2012 | 505 Montgomery St | upgrade from conventional elevator all technology to destination dispatch per ab-090; floors 1,4,12 though 24, only.Details
upgrade from conventional elevator all technology to destination dispatch per ab-090; floors 1,4,12 though 24, only. | $90,640 |
| Dec 15, 2008 | Never finaled issued Sep 2011, no final | 211 Main St | install destination based elevator controlDetails
install destination based elevator control | $25,000 |