1,003 permits since 2000: 654 completed, 2 in progress, 170 never finaled, 177 expired or cancelled.
Of the 170 never-finaled permits, 3 are 3 to 5 years old, 18 are 5 to 10 years old, 149 are over 10 years old. 1 was filed but never issued.
This is the city’s permit record, not a license check. It does not show whether the state license is active, bonded or insured. How to read these records
Permits filed each year
How long permits take
Each point is the quarter the permits were filed, for all building permits across San Francisco. A median counts only permits that have finished, so the shaded recent quarters look faster than they will end up: their slow permits have not finished yet. Hover a point for the slowest 10%. Gaps mean fewer than 5 permits. A rise in the issue line is the city’s review backlog, not the contractor.
Most recent permits
Showing the 100 most recent of 1,003.
| Filed | Outcome | Address | Work described on the permit | Declared cost |
|---|---|---|---|---|
| Oct 20, 2025 | Completed final sign-off Dec 2025 | 255 West Portal Av | re roofing: no hot works.carlsle scremold tpo 60m. (3 year .70, ; theral e (.86) sri 85Details
re roofing: no hot works.carlsle scremold tpo 60m. (3 year .70, ; theral e (.86) sri 85 | $90,000 |
| Oct 9, 2025 | Completed final sign-off Oct 2025 | 52 El Sereno Ct | re-roofing: low slope portion/gravel surface. remove sheet metal flashing with hot works. asphalt shingle roof.Details
re-roofing: low slope portion/gravel surface. remove sheet metal flashing with hot works. asphalt shingle roof. | $19,750 |
| Oct 1, 2025 | Completed final sign-off Oct 2025 | 153 Avila St | re roofing no hot workDetails
re roofing no hot work | $47,655 |
| Sep 9, 2025 | Completed final sign-off Oct 2025 | 6000 California St | re roofing: hot works.Details
re roofing: hot works. | $80,234 |
| Aug 29, 2025 | Completed final sign-off Apr 2026 | 1750 Taylor St | reroofing for penthouse unit 102 south deck/balcony. clean e) concrete roof, furrish & install new sikalastic roof deck sytem, re-roofing concrete roof. no torch work.Details
reroofing for penthouse unit 102 south deck/balcony. clean e) concrete roof, furrish & install new sikalastic roof deck sytem, re-roofing concrete roof. no torch work. | $132,041 |
| Jun 10, 2025 | Completed final sign-off Nov 2025 | 220 Montgomery St | 10 story bldg: re roofing remove existing roofing on floor roof down to concrete deck. install 2 ply sbs modified bitumen roofing system with title 24 complaint cap sheet. (torch down, hot work).Details
10 story bldg: re roofing remove existing roofing on floor roof down to concrete deck. install 2 ply sbs modified bitumen roofing system with title 24 complaint cap sheet. (torch down, hot work). | $756,000 |
| May 13, 2025 | Completed final sign-off Jun 2025 | 601 Eucalyptus Dr | re-roofing no torch downDetails
re-roofing no torch down | $80,000 |
| Mar 25, 2025 | Completed final sign-off Mar 2026 | 150 Lombard St | reroofing (no hotworks) cenc exception 2 to section 140.3(a)1aia.Details
reroofing (no hotworks) cenc exception 2 to section 140.3(a)1aia. | $2,841,765 |
| Mar 24, 2025 | Completed final sign-off Apr 2025 | 995 Pine St | re-roofing with torch down.Details
re-roofing with torch down. | $200,000 |
| Oct 28, 2024 | Completed final sign-off Dec 2024 | 2698 Filbert St | re-roofing, shingles, about 2500 sq. ft.Details
re-roofing, shingles, about 2500 sq. ft. | $123,333 |
| Oct 9, 2024 | Completed final sign-off Nov 2024 | 88 West Clay St | re-roofing: remove and replace roofing material / existing roofing material (in-kind)Details
re-roofing: remove and replace roofing material / existing roofing material (in-kind) | $59,962 |
| Oct 2, 2024 | Completed final sign-off Oct 2024 | 2011 Clement St | roof and haul away deris. furnish and install (n) certained sa roof systemDetails
roof and haul away deris. furnish and install (n) certained sa roof system | $62,305 |
| Jul 25, 2024 | Completed final sign-off Oct 2024 | 2786 Vallejo St | reroofDetails
reroof | $184,600 |
| Jul 18, 2024 | Completed final sign-off Oct 2024 | 2786 Vallejo St | reroofDetails
reroof | $58,070 |
| Jul 8, 2024 | Completed final sign-off Oct 2024 | 2645 Gough St | reroofDetails
reroof | $71,100 |
| Jun 17, 2024 | Completed final sign-off Feb 2025 | 1200 Page St | reroofingDetails
reroofing | $330,000 |
| Jun 17, 2024 | In progress issued Jun 2024 | 535 Pacific Av | reroofingDetails
reroofing | $529,589 |
| May 15, 2024 | Completed final sign-off Apr 2025 | 36 Hoff St | reroofingDetails
reroofing | $600,000 |
| Apr 10, 2024 | Completed final sign-off Apr 2024 | 567 Prentiss St | re-roofing: remove and replace roofing material / existing roofing material (in-kind)Details
re-roofing: remove and replace roofing material / existing roofing material (in-kind) | $22,741 |
| Feb 23, 2024 | Completed final sign-off Mar 2024 | 758 38th Av | re-roofing: remove and replace roofing material / existing roofing material (in-kind)Details
re-roofing: remove and replace roofing material / existing roofing material (in-kind) | $44,925 |
| Dec 14, 2023 | In progress issued Dec 2023 | 2390 Bush St | reroofingDetails
reroofing | $2,873,443 |
| Oct 30, 2023 | Completed final sign-off Nov 2023 | 3637 Clay St | reroofingDetails
reroofing | $45,823 |
| Oct 19, 2023 | Completed final sign-off Feb 2024 | 70 San Pablo Av | reroofingDetails
reroofing | $129,489 |
| Oct 3, 2023 | Completed final sign-off Nov 2023 | 209 Walnut St | reroofingDetails
reroofing | $128,491 |
| Aug 24, 2023 | Completed final sign-off Sep 2023 | 3655 Clay St | reroofingDetails
reroofing | $49,845 |
| Aug 10, 2023 | Completed final sign-off Sep 2023 | 3061 16th St | reroofingDetails
reroofing | $120,000 |
| Jul 18, 2023 | Completed final sign-off Feb 2025 | 1230 Kearny St | re-roofing: remove and replace roofing material / existing roofing material (in-kind)Details
re-roofing: remove and replace roofing material / existing roofing material (in-kind) | $58,070 |
| Jun 2, 2023 | Never finaled issued Jun 2023, no final | 441 Flood Av | re-roofing: remove and replace roofing material / existing roofing material (in-kind)Details
re-roofing: remove and replace roofing material / existing roofing material (in-kind) | $30,874 |
| Jun 1, 2023 | Completed final sign-off Jun 2023 | 1 Post St | reroofingDetails
reroofing | $81,575 |
| May 31, 2023 | Completed final sign-off Aug 2023 | 2750 Jackson St | reroofing; per sec 141.0(b)2bi exception 2.Details
reroofing; per sec 141.0(b)2bi exception 2. | $300,000 |
| May 25, 2023 | Completed final sign-off Jun 2023 | 234 28th Av | re-roofing: remove and replace roofing material / existing roofing material (in-kind)Details
re-roofing: remove and replace roofing material / existing roofing material (in-kind) | $67,894 |
| May 19, 2023 | Completed final sign-off Jun 2023 | 2226 22nd Av | re-roofing: remove and replace roofing material / existing roofing material (in-kind)Details
re-roofing: remove and replace roofing material / existing roofing material (in-kind) | $35,102 |
| May 3, 2023 | Completed final sign-off Aug 2023 | 2300 Harrison St | remove (e) tar and gravel. existing roof membrane to remain. install one layer of 2" iso insulation and siplast modified bitumen roof system. existing roof has r-19 insulation - add minimum r-10 insulation above roof deck. cool roof ceec id 0742-0018 - siplast paradiene 30 rg tg bw (sri 92).Details
remove (e) tar and gravel. existing roof membrane to remain. install one layer of 2" iso insulation and siplast modified bitumen roof system. existing roof has r-19 insulation - add minimum r-10 insulation above roof deck. cool roof ceec id 0742-0018 - siplast paradiene 30 rg tg bw (sri 92). | $698,926 |
| Apr 25, 2023 | Never finaled issued Apr 2023, no final | 338 Felton St | re-roofing: remove and replace roofing material / existing roofing material (in-kind)Details
re-roofing: remove and replace roofing material / existing roofing material (in-kind) | $29,831 |
| Feb 17, 2023 | Completed final sign-off Mar 2023 | 18 Rossi Av | re-roofing: remove and replace roofing material / existing roofing material (in-kind)Details
re-roofing: remove and replace roofing material / existing roofing material (in-kind) | $28,984 |
| Dec 12, 2022 | Completed final sign-off May 2023 | 727 Nelson Rising Ln | reroofingDetails
reroofing | $474,664 |
| Nov 28, 2022 | Completed final sign-off Dec 2022 | 790 25th Av | reroofingDetails
reroofing | $29,828 |
| Nov 16, 2022 | Completed final sign-off Dec 2022 | 381 Arlington St | re-roofing: remove and replace roofing material / existing roofing material (in-kind)Details
re-roofing: remove and replace roofing material / existing roofing material (in-kind) | $37,991 |
| Nov 16, 2022 | Completed final sign-off Nov 2023 | 335 Powell St | reroofingDetails
reroofing | $1,679,291 |
| Oct 31, 2022 | Completed final sign-off Nov 2022 | 24 Presidio Av | reroofing.Details
reroofing. | $17,789 |
| Sep 12, 2022 | Completed final sign-off Oct 2022 | 50 Ramona Av | reroofingDetails
reroofing | $42,821 |
| Aug 4, 2022 | Completed final sign-off Jul 2023 | 347 Liberty St | reroofingDetails
reroofing | $64,787 |
| Aug 4, 2022 | Completed final sign-off Sep 2022 | 3310 California St | reroofingDetails
reroofing | $101,819 |
| Jul 27, 2022 | Completed final sign-off Aug 2022 | 512 Bella Vista Wy | re-roofing: remove and replace roofing material / existing roofing material (in-kind)Details
re-roofing: remove and replace roofing material / existing roofing material (in-kind) | $26,040 |
| Jul 20, 2022 | Completed final sign-off Aug 2022 | 626 Diamond St | reroofingDetails
reroofing | $22,486 |
| Jun 29, 2022 | Completed final sign-off Jun 2022 | 2018 Keith St | to obtain final inspection for work approved under permit application no: 201809139977. all work is complete.Details
to obtain final inspection for work approved under permit application no: 201809139977. all work is complete. | $13,498 |
| Jun 15, 2022 | Completed final sign-off Jul 2022 | 77 Connecticut St | reroofing. min aged solar reflectance 0.63 & min thermal emittance 0.75Details
reroofing. min aged solar reflectance 0.63 & min thermal emittance 0.75 | $121,000 |
| May 23, 2022 | Completed final sign-off Jun 2022 | 1 Post St | reroofing.Details
reroofing. | $260,670 |
| May 13, 2022 | Completed final sign-off Jun 2022 | 3825 25th St | reroofingDetails
reroofing | $54,250 |
| May 10, 2022 | Completed final sign-off Feb 2023 | 1 Lombard St | reroofing. minimum sri of 75 (low-sloped, non-res)Details
reroofing. minimum sri of 75 (low-sloped, non-res) | $1,521,013 |
| Apr 26, 2022 | Completed final sign-off Aug 2022 | 1170 Sacramento St | reroofingDetails
reroofing | $600,000 |
| Apr 22, 2022 | Completed final sign-off May 2022 | 1754 Wawona St | re-roofing: remove and replace roofing material / existing roofing material (in-kind)Details
re-roofing: remove and replace roofing material / existing roofing material (in-kind) | $28,913 |
| Mar 23, 2022 | Completed final sign-off Apr 2022 | 818 Rivera St | re-roofing: remove and replace roofing material / existing roofing material (in-kind)Details
re-roofing: remove and replace roofing material / existing roofing material (in-kind) | $35,699 |
| Mar 10, 2022 | Completed final sign-off Mar 2022 | 2739 Larkin St | reroofingDetails
reroofing | $35,908 |
| Feb 25, 2022 | Never finaled issued Feb 2022, no final | 1127 Carolina St | re-roofing: remove and replace roofing material / existing roofing material (in-kind)Details
re-roofing: remove and replace roofing material / existing roofing material (in-kind) | $22,512 |
| Feb 18, 2022 | Completed final sign-off Feb 2022 | 225 Naylor St | re-roofing: remove and replace roofing material / existing roofing material (in-kind)Details
re-roofing: remove and replace roofing material / existing roofing material (in-kind) | $27,384 |
| Jan 31, 2022 | Completed final sign-off Feb 2022 | 2020 Great Hy | reroofingDetails
reroofing | $73,844 |
| Jan 6, 2022 | Completed final sign-off Mar 2022 | 100 Spruce St | reroofingDetails
reroofing | $17,180 |
| Jan 6, 2022 | Completed final sign-off Feb 2022 | 3820 22nd St | reroofingDetails
reroofing | $42,315 |
| Nov 4, 2021 | Completed final sign-off Dec 2021 | 2031 46th Av | re-roofing: remove and replace roofing material / existing roofing material (in-kind)Details
re-roofing: remove and replace roofing material / existing roofing material (in-kind) | $18,486 |
| Nov 4, 2021 | Completed final sign-off Nov 2021 | 434 Molimo Dr | re-roofing: remove and replace roofing material / existing roofing material (in-kind)Details
re-roofing: remove and replace roofing material / existing roofing material (in-kind) | $42,413 |
| Sep 8, 2021 | Completed final sign-off Oct 2021 | 5 Buena Vista East Av | reroofingDetails
reroofing | $61,329 |
| Sep 2, 2021 | Completed final sign-off Oct 2021 | 145 Laurel St | reroofing. overlay (e) built-up roofing. install dens-dck + 2-ply modified bitumen siplast roofing over (e) cap sheet foor membrane, install new copper flashing over top of parapet wall.Details
reroofing. overlay (e) built-up roofing. install dens-dck + 2-ply modified bitumen siplast roofing over (e) cap sheet foor membrane, install new copper flashing over top of parapet wall. | $347,501 |
| Aug 25, 2021 | Completed final sign-off Sep 2021 | 3430 Baker St | reroofingDetails
reroofing | $14,510 |
| Aug 25, 2021 | Completed final sign-off Sep 2021 | 447 40th Av | re-roofing: remove and replace roofing material / existing roofing material (in-kind)Details
re-roofing: remove and replace roofing material / existing roofing material (in-kind) | $21,764 |
| Aug 25, 2021 | Completed final sign-off Sep 2021 | 662 Sanchez St | reroofingDetails
reroofing | $31,509 |
| Aug 9, 2021 | Completed final sign-off Dec 2021 | 950 Howard St | reroofingDetails
reroofing | $72,504 |
| Jul 27, 2021 | Completed final sign-off Aug 2021 | 114 Ney St | re-roofing: remove and replace roofing material / existing roofing material (in-kind)Details
re-roofing: remove and replace roofing material / existing roofing material (in-kind) | $25,530 |
| Jul 15, 2021 | Completed final sign-off Jun 2022 | 302 Silver Av | reroofingDetails
reroofing | $752,898 |
| Jun 24, 2021 | Completed final sign-off Mar 2022 | 2799 Pacific Av | remove existing shingles and low slope roofing to roof substrate/ imnstall 2-ply sbs roofing modified bitumen on slopes roofd. install davinci slate on steep roofing portion of building.Details
remove existing shingles and low slope roofing to roof substrate/ imnstall 2-ply sbs roofing modified bitumen on slopes roofd. install davinci slate on steep roofing portion of building. | $300,000 |
| May 20, 2021 | Completed final sign-off May 2021 | 211 Romain St | reroofingDetails
reroofing | $38,215 |
| Apr 13, 2021 | Completed final sign-off Jun 2021 | 1097 Green St | sweep clean loose gravel and haul away to three dumps. install new ridgio insulation board and carlisle pvc single-ply roofing membrane over existing roof membrane. flat roof. approx 4000 sfDetails
sweep clean loose gravel and haul away to three dumps. install new ridgio insulation board and carlisle pvc single-ply roofing membrane over existing roof membrane. flat roof. approx 4000 sf | $139,021 |
| Mar 15, 2021 | Completed final sign-off May 2021 | 1201 Golden Gate Av | reroofingDetails
reroofing | $265,146 |
| Mar 9, 2021 | Completed final sign-off Mar 2021 | 563 36th Av | re-roofingDetails
re-roofing | $25,000 |
| Mar 9, 2021 | Completed final sign-off Apr 2021 | 485 Jersey St | re-roofingDetails
re-roofing | $19,517 |
| Feb 2, 2021 | Completed final sign-off Mar 2021 | 162 Day St | re-roofing - remove (e) roofing down to original dec, furnish and install a four ply tar system with capsheet finish, install new galvanized flashingsDetails
re-roofing - remove (e) roofing down to original dec, furnish and install a four ply tar system with capsheet finish, install new galvanized flashings | $3,537 |
| Feb 2, 2021 | Completed final sign-off Feb 2021 | 540 Urbano Dr | re-roofing - remove (e) comp shingles down to wood deck and install new comp shingles and new flashingsDetails
re-roofing - remove (e) comp shingles down to wood deck and install new comp shingles and new flashings | $21,569 |
| Dec 21, 2020 | Completed final sign-off Mar 2022 | 100 Spruce St | reroofingDetails
reroofing | $97,952 |
| Dec 10, 2020 | Completed final sign-off Feb 2021 | 181 Collins St | reroofingDetails
reroofing | $31,098 |
| Oct 8, 2020 | Completed final sign-off Oct 2020 | 159 Commonwealth Av | reroofing at detached garageDetails
reroofing at detached garage | $5,324 |
| Sep 1, 2020 | Completed final sign-off Nov 2020 | 1 Sutter St | reroofing. must comply with cool roof requirements 2019 cec 141.0(b)2b.Details
reroofing. must comply with cool roof requirements 2019 cec 141.0(b)2b. | $208,838 |
| Aug 11, 2020 | Completed final sign-off Sep 2020 | 641 Connecticut St | reroofing - remove exiting tar and gravel roofing. install new four ply tar and gravel roofing with gravel surface and new sheet metal flashing.Details
reroofing - remove exiting tar and gravel roofing. install new four ply tar and gravel roofing with gravel surface and new sheet metal flashing. | $18,953 |
| Aug 11, 2020 | Completed final sign-off Sep 2020 | 637 Connecticut St | reroofing - remove existing tar and gravel roofing. install new four ply tar and gravel roofing and new sheet metal flashing. to comply with cool roof requirements per 2019 california energy code 141.0(b)2b for all non-residential building.Details
reroofing - remove existing tar and gravel roofing. install new four ply tar and gravel roofing and new sheet metal flashing. to comply with cool roof requirements per 2019 california energy code 141.0(b)2b for all non-residential building. | $21,479 |
| Jul 14, 2020 | Never finaled issued Jul 2020, no final | 3575 Washington St | reroofing. remove existing roofing down to original deck surface. furnish and install new composition shingles. (permit excluding rough carpentry work)Details
reroofing. remove existing roofing down to original deck surface. furnish and install new composition shingles. (permit excluding rough carpentry work) | $107,871 |
| Jul 10, 2020 | Completed final sign-off Oct 2020 | 2650 Green St | reroofing - remove existing roofing, furnish and install new composition shingle roofing over existing roof deck surface. new compositing roofing to match existing shingle roofing and kind.Details
reroofing - remove existing roofing, furnish and install new composition shingle roofing over existing roof deck surface. new compositing roofing to match existing shingle roofing and kind. | $65,653 |
| Jun 30, 2020 | Completed final sign-off Jul 2020 | 2308 Buchanan St | reroofing - remove existing shingle roof and install new shinglesDetails
reroofing - remove existing shingle roof and install new shingles | $36,091 |
| Jun 10, 2020 | Completed final sign-off May 2021 | 50 Green St | reroofingDetails
reroofing | $2,493,031 |
| May 28, 2020 | Completed final sign-off Jun 2020 | 7070 California St | reroofingDetails
reroofing | $27,789 |
| May 27, 2020 | Completed final sign-off Jun 2020 | 1882 18th Av | reroofing. remove existing roofing down to original wood deck, install new tar and gravel roofDetails
reroofing. remove existing roofing down to original wood deck, install new tar and gravel roof | $20,984 |
| May 11, 2020 | Never finaled issued May 2020, no final | 747 Front St | street space / 202002134360Details
street space / 202002134360 | |
| Mar 10, 2020 | Completed final sign-off Jul 2020 | 3645 17th St | reroofingDetails
reroofing | $87,521 |
| Feb 13, 2020 | Completed final sign-off Jun 2020 | 747 Front St | reroofingDetails
reroofing | $401,350 |
| Jan 17, 2020 | Completed final sign-off Jan 2020 | 120 Locksley Av | reroofing.Details
reroofing. | $40,230 |
| Oct 21, 2019 | Completed final sign-off Nov 2019 | 2967 21st Av | reroofing.Details
reroofing. | $16,525 |
| Oct 21, 2019 | Completed final sign-off Mar 2020 | 157 Commonwealth Av | reroofing.Details
reroofing. | $36,959 |
| Oct 15, 2019 | Completed final sign-off Nov 2019 | 297 Baltimore Wy | reroofing.Details
reroofing. | $15,771 |
| Oct 15, 2019 | Completed final sign-off Dec 2019 | 46 Admiral Av | reroofing.Details
reroofing. | $20,854 |
| Oct 4, 2019 | Completed final sign-off Oct 2019 | 711 Marina Bl | reroofingDetails
reroofing | $45,000 |
| Sep 23, 2019 | Completed final sign-off Jan 2020 | 781 Rockdale Dr | reroofing.Details
reroofing. | $14,993 |
| Sep 23, 2019 | Completed final sign-off Dec 2019 | 25 Pomona St | reroofing.Details
reroofing. | $16,716 |