- 0 permits filed
12 permits since 2000: 6 completed, 1 in progress, 5 never finaled.
Of the 5 never-finaled permits, 5 are 3 to 5 years old.
This is the city’s permit record, not a license check. It does not show whether the state license is active, bonded or insured. How to read these records
Permits filed each year
How long permits take
Each point is the quarter the permits were filed, for all building permits across San Francisco. A median counts only permits that have finished, so the shaded recent quarters look faster than they will end up: their slow permits have not finished yet. Hover a point for the slowest 10%. Gaps mean fewer than 5 permits. A rise in the issue line is the city’s review backlog, not the contractor.
Most recent permits
| Filed | Outcome | Address | Work described on the permit | Declared cost |
|---|---|---|---|---|
| Oct 19, 2023 | In progress filed Oct 2023, not yet issued | 30 Onondaga Av | dish wireless proposing to install (3) panel antennas (3) antenna mounts (1) radome, (6) rru's (1) metal platform and frame and associated equipment. site modification based on 6409.Details
dish wireless proposing to install (3) panel antennas (3) antenna mounts (1) radome, (6) rru's (1) metal platform and frame and associated equipment. site modification based on 6409. | $38,000 |
| Jun 5, 2023 | Completed final sign-off Sep 2024 | 5000 Geary Bl | removal of (e) sprint equipment due to merger w/ t-mobile: removing spriny antennas, radio cabinets, & associcated equipmentsDetails
removal of (e) sprint equipment due to merger w/ t-mobile: removing spriny antennas, radio cabinets, & associcated equipments | $8,300 |
| May 30, 2023 | Completed final sign-off Feb 2024 | 1881 Post St | removal of existing sprint equipment due to merge of sprint with tmobile. scope includes removal of antennas, radio cabinets, and associated telecom equipments. sprint project: sf82xc055.Details
removal of existing sprint equipment due to merge of sprint with tmobile. scope includes removal of antennas, radio cabinets, and associated telecom equipments. sprint project: sf82xc055. | $8,300 |
| May 30, 2023 | Completed final sign-off Feb 2024 | 1881 Post St | removal of existing sprint equipment due to merge of sprint with tmobile. scope includes removal of all telecom equipment. sprint project: fs04xc007.Details
removal of existing sprint equipment due to merge of sprint with tmobile. scope includes removal of all telecom equipment. sprint project: fs04xc007. | $8,300 |
| May 30, 2023 | Completed final sign-off Jan 2024 | 4131 Geary Bl | removal of existing sprint equipment due to merge of sprint with tmobile. scope includes removal of antennas, radio cabinets, and associated telecom equipments. sprint project: sf36xc067.Details
removal of existing sprint equipment due to merge of sprint with tmobile. scope includes removal of antennas, radio cabinets, and associated telecom equipments. sprint project: sf36xc067. | $8,300 |
| May 30, 2023 | Never finaled issued Jun 2023, no final | 380 Clementina St | removal of existing sprint equipment due to merge of sprint with tmobile. scope includes removal of antennas and radio cabinets. sprint project: sf52xc490.Details
removal of existing sprint equipment due to merge of sprint with tmobile. scope includes removal of antennas and radio cabinets. sprint project: sf52xc490. | $8,300 |
| May 30, 2023 | Never finaled issued Jun 2023, no final | 300 02nd Av | removal of existing t-mobile telecom equipment due to merger w/sprint/t-mobile. scope includes removal of all t-mobile equipment (antenna, radio, cabinets, etc.) t-mobile id # sf131.Details
removal of existing t-mobile telecom equipment due to merger w/sprint/t-mobile. scope includes removal of all t-mobile equipment (antenna, radio, cabinets, etc.) t-mobile id # sf131. | $8,300 |
| May 30, 2023 | Completed final sign-off Feb 2024 | 1740 Sloat Bl | removal of existing sprint equipment due to merge of sprint with tmobile. scope includes removal of antennas, radio cabinets, and associated telecom equipments. sprint project: fs04xc020.Details
removal of existing sprint equipment due to merge of sprint with tmobile. scope includes removal of antennas, radio cabinets, and associated telecom equipments. sprint project: fs04xc020. | $8,300 |
| Aug 23, 2022 | Never finaled issued Nov 2022, no final | 1650 Owens St | dish wireless proposing to install 3 antennas 6 rrus,2 frp screenwalls, 1 equp cabinet on rooftop. antennas will be 2 sectors of rooftop, concealed with frp wall. power and fiber lines placed in new cable tray on roof, to run from equip cab to ea location. all installs to be painted to matchDetails
dish wireless proposing to install 3 antennas 6 rrus,2 frp screenwalls, 1 equp cabinet on rooftop. antennas will be 2 sectors of rooftop, concealed with frp wall. power and fiber lines placed in new cable tray on roof, to run from equip cab to ea location. all installs to be painted to match | $68,000 |
| Jul 26, 2022 | Completed final sign-off Feb 2023 | 2145 19th Av | dish to remove e radomes and all e equip, install 1 proposed ramdome, remove 3 e antenna rplace with e new antenna, remove and rplace 6 radios,replace equip cabinetsDetails
dish to remove e radomes and all e equip, install 1 proposed ramdome, remove 3 e antenna rplace with e new antenna, remove and rplace 6 radios,replace equip cabinets | $68,000 |
| Jul 26, 2022 | Never finaled issued Nov 2022, no final | 1344 Ocean Av | dish wireless llc to install 3 antennas, 6 rrus and wquip cabinet on rooftop. propsed to install 1 per sector at 3 locations on roof. antennas will be concealed within frp screen wall. both power and fiber lines will be placed in new cable tray on roof top. cable tray will run from equip cabinet toDetails
dish wireless llc to install 3 antennas, 6 rrus and wquip cabinet on rooftop. propsed to install 1 per sector at 3 locations on roof. antennas will be concealed within frp screen wall. both power and fiber lines will be placed in new cable tray on roof top. cable tray will run from equip cabinet to | $68,000 |
| Jun 15, 2022 | Never finaled issued Nov 2022, no final | 2696 Geary Bl | install 6 antennas (2/sect), 12 rru's (4/sect) & equip cabinets on roof. 3 sects at 3 locations on roof, antennas concealed w/in frp radomes.power lines & fiber lines will be placed in new cable tray on roof and run from equipment cabinet to ea antenna.all proposed screening/concealment/paint match.Details
install 6 antennas (2/sect), 12 rru's (4/sect) & equip cabinets on roof. 3 sects at 3 locations on roof, antennas concealed w/in frp radomes.power lines & fiber lines will be placed in new cable tray on roof and run from equipment cabinet to ea antenna.all proposed screening/concealment/paint match. | $68,000 |