Permit GraphShortlistSan Francisco building permits since 2000

Sunrun Installation Services Inc

Contractor license
750184
State license record
Based in
San Luis Obispo
On San Francisco permits
Jul 2016 to Oct 2025
Last 24 months
3 permits filed

15 permits since 2000: 4 completed, 3 in progress, 7 never finaled, 1 expired or cancelled.

Of the 7 never-finaled permits, 5 are 3 to 5 years old, 1 is 5 to 10 years old, 1 is over 10 years old. 1 was filed but never issued.

CompletedIn progressNever finaledExpired or cancelled

This is the city’s permit record, not a license check. It does not show whether the state license is active, bonded or insured. How to read these records

Permits filed each year

How long permits take

Median days to final inspection, citywideMedian days to permit issued, citywide

Each point is the quarter the permits were filed, for all building permits across San Francisco. A median counts only permits that have finished, so the shaded recent quarters look faster than they will end up: their slow permits have not finished yet. Hover a point for the slowest 10%. Gaps mean fewer than 5 permits. A rise in the issue line is the city’s review backlog, not the contractor. Too few of this contractor’s permits have finished to plot them.

Most recent permits

All
FiledOutcomeAddressWork described on the permitDeclared cost
Oct 9, 2025In progress
filed Oct 2025, not yet issued
136 Santa Rosa Avsolar permit: ballasted: n, including 1 energy storage unit, with 13.5 kwh each in capacity, ess units will not be closer than 3 feet | revision to permit e202501099242 updated interconnection
Details
Permit
S20251009174
Status
triage
Filed
Oct 9, 2025
Address
136 Santa Rosa Av

solar permit: ballasted: n, including 1 energy storage unit, with 13.5 kwh each in capacity, ess units will not be closer than 3 feet | revision to permit e202501099242 updated interconnection

Open the permit page

Oct 9, 2025In progress
filed Oct 2025, not yet issued
136 Santa Rosa Avsolar permit: ballasted: n, including 1 energy storage unit, with 13.5 kwh each in capacity, ess units will not be closer than 3 feet | revision to permit e202501099242 updated interconnection
Details
Permit
S20251009173
Status
triage
Filed
Oct 9, 2025
Address
136 Santa Rosa Av

solar permit: ballasted: n, including 1 energy storage unit, with 13.5 kwh each in capacity, ess units will not be closer than 3 feet | revision to permit e202501099242 updated interconnection

Open the permit page

Oct 9, 2025In progress
filed Oct 2025, not yet issued
136 Santa Rosa Avsolar permit: ballasted: n, including 1 energy storage unit, with 13.5 kwh each in capacity, ess units will not be closer than 3 feet | revision to permit e202501099242 updated interconnection
Details
Permit
S20251009175
Status
triage
Filed
Oct 9, 2025
Address
136 Santa Rosa Av

solar permit: ballasted: n, including 1 energy storage unit, with 13.5 kwh each in capacity, ess units will not be closer than 3 feet | revision to permit e202501099242 updated interconnection

Open the permit page

Jul 7, 2023Completed
final sign-off Aug 2023
789 Castro Streroofing
Details
Permit
202307071622
Status
complete
Filed
Jul 7, 2023
Permit issued
Jul 7, 2023
Final sign-off
Aug 11, 2023
Declared cost
$12,700
Address
789 Castro St

reroofing

Open the permit page

$12,700
Apr 26, 2022Never finaled
issued Apr 2022, no final
350 Raymond Avre-roofing: remove and replace roofing material / existing roofing material (in-kind)
Details
Permit
202204263036
Status
issued
Filed
Apr 26, 2022
Permit issued
Apr 26, 2022
Declared cost
$7,698
Address
350 Raymond Av

re-roofing: remove and replace roofing material / existing roofing material (in-kind)

Open the permit page

$7,698
Mar 31, 2022Completed
final sign-off Aug 2022
549 Somerset Stre-roofing: remove and replace roofing material / existing roofing material (in-kind)
Details
Permit
202203311343
Status
complete
Filed
Mar 31, 2022
Permit issued
Mar 31, 2022
Final sign-off
Aug 16, 2022
Declared cost
$5,821
Address
549 Somerset St

re-roofing: remove and replace roofing material / existing roofing material (in-kind)

Open the permit page

$5,821
Mar 3, 2022Never finaled
issued Mar 2022, no final
342 Holyoke Stre-roofing: remove and replace roofing material / existing roofing material (in-kind)
Details
Permit
202203039196
Status
issued
Filed
Mar 3, 2022
Permit issued
Mar 3, 2022
Declared cost
$2,425
Address
342 Holyoke St

re-roofing: remove and replace roofing material / existing roofing material (in-kind)

Open the permit page

$2,425
Feb 23, 2022Never finaled
issued Oct 2022, no final
345 Granada Avinstall 1 tesla 13.5kwh powerwall energy storage system. existing solar with ess system installed.
Details
Permit
202202238515
Status
issued
Filed
Feb 23, 2022
Permit issued
Oct 19, 2022
Declared cost
$6,000
Address
345 Granada Av

install 1 tesla 13.5kwh powerwall energy storage system. existing solar with ess system installed.

Open the permit page

$6,000
Feb 23, 2022Never finaled
filed Feb 2022, never issued
429 Colon Avinstall 1 tesla 13.5kwh powerwall energy storage system. existing solar with ess system installed.
Details
Permit
202202238513
Status
filed
Filed
Feb 23, 2022
Declared cost
$6,000
Address
429 Colon Av

install 1 tesla 13.5kwh powerwall energy storage system. existing solar with ess system installed.

Open the permit page

$6,000
Nov 29, 2021Completed
final sign-off Jan 2022
250 San Benito Wyreroofing
Details
Permit
202111293189
Status
complete
Filed
Nov 29, 2021
Permit issued
Nov 29, 2021
Final sign-off
Jan 31, 2022
Declared cost
$10,388
Address
250 San Benito Wy

reroofing

Open the permit page

$10,388
Oct 22, 2021Never finaled
issued Oct 2021, no final
99 Rotteck Stre-roofing: remove and replace roofing material / existing roofing material (in-kind)
Details
Permit
202110220985
Status
issued
Filed
Oct 22, 2021
Permit issued
Oct 22, 2021
Declared cost
$5,591
Address
99 Rotteck St

re-roofing: remove and replace roofing material / existing roofing material (in-kind)

Open the permit page

$5,591
Sep 30, 2021Never finaled
issued Sep 2021, no final
224 Pope Stre-roofing: remove and replace roofing material / existing roofing material (in-kind)
Details
Permit
202109309580
Status
issued
Filed
Sep 30, 2021
Permit issued
Sep 30, 2021
Declared cost
$7,224
Address
224 Pope St

re-roofing: remove and replace roofing material / existing roofing material (in-kind)

Open the permit page

$7,224
Sep 26, 2020Completed
final sign-off Jul 2022
2650 Green Stinstall 2 additional tesla 13.5kwh powerwall2 battery energy storge system in garage (42 kwh total) w/ (2) bollards & (4) interconnected heat alarms
Details
Permit
202009265101
Status
complete
Filed
Sep 26, 2020
Permit issued
May 13, 2022
Final sign-off
Jul 26, 2022
Declared cost
$12,000
Address
2650 Green St

install 2 additional tesla 13.5kwh powerwall2 battery energy storge system in garage (42 kwh total) w/ (2) bollards & (4) interconnected heat alarms

Open the permit page

$12,000
Jun 13, 2020Expired or cancelled
cancelled Jan 2026
165 Cerritos Avinstall(2)tesla powerwall 13.5kwh,5kw inverter output,lithium-ion batteries(weight:251.3lbs each)
Details
Permit
202006138685
Status
cancelled
Filed
Jun 13, 2020
Address
165 Cerritos Av

install(2)tesla powerwall 13.5kwh,5kw inverter output,lithium-ion batteries(weight:251.3lbs each)

Open the permit page

Jul 1, 2016Never finaled
issued Jul 2016, no final
722 Steiner St5.12 kw rooftop solar pv system (16) modules (16) power optimizers (for planning review only) ref e2016067314
Details
Permit
201607011368
Status
issued
Filed
Jul 1, 2016
Permit issued
Jul 29, 2016
Declared cost
$10,700
Address
722 Steiner St

5.12 kw rooftop solar pv system (16) modules (16) power optimizers (for planning review only) ref e2016067314

Open the permit page

$10,700