Stoer Construction Inc
- Based in
- San Jose
- On San Francisco permits
- Jul 2018 to Apr 2022
- Last 24 months
- 0 permits filed
7 permits since 2000: 6 completed, 1 expired or cancelled.
This is the city’s permit record, not a license check. It does not show whether the state license is active, bonded or insured. How to read these records
Permits filed each year
How long permits take
Each point is the quarter the permits were filed, for all building permits across San Francisco. A median counts only permits that have finished, so the shaded recent quarters look faster than they will end up: their slow permits have not finished yet. Hover a point for the slowest 10%. Gaps mean fewer than 5 permits. A rise in the issue line is the city’s review backlog, not the contractor.
Most recent permits
| Filed | Outcome | Address | Work described on the permit | Declared cost |
|---|---|---|---|---|
| Apr 1, 2022 | Completed final sign-off Apr 2023 | 345 04th St | revision to 201807194942. update fire pump from 75hp to 40hp, update full load amps, update fire pump controller. update fire pump meter fsb to show 400a breaker. add calculations for lra at 312a so. 400a is acceptable. updated feeders to fire pump controller with a conductor size calculations.Details
revision to 201807194942. update fire pump from 75hp to 40hp, update full load amps, update fire pump controller. update fire pump meter fsb to show 400a breaker. add calculations for lra at 312a so. 400a is acceptable. updated feeders to fire pump controller with a conductor size calculations. | |
| Sep 29, 2020 | Completed final sign-off Jan 2023 | 345 04th St | installation of new fire 6" service for commercial buildingDetails
installation of new fire 6" service for commercial building | $40,000 |
| Aug 28, 2020 | Completed final sign-off Nov 2022 | 345 04th St | stormwater plan review. ref new construction pa# 201807194942.Details
stormwater plan review. ref new construction pa# 201807194942. | |
| Mar 3, 2020 | Expired or cancelled withdrawn Apr 2023 | 345 04th St | revision to bpa #201807194942. structural conversion of the fixed head pile assembly. design has changed to utilize deeper pile embedment into the pile. **maher n/a**Details
revision to bpa #201807194942. structural conversion of the fixed head pile assembly. design has changed to utilize deeper pile embedment into the pile. **maher n/a** | |
| Nov 30, 2018 | Completed final sign-off Dec 2022 | 343 04th St | demolish 2-story, type 1, office building. maher n/a.Details
demolish 2-story, type 1, office building. maher n/a. | $432,700 |
| Nov 30, 2018 | Completed final sign-off Dec 2022 | 345 04th St | shoring for future work. maher n/a.Details
shoring for future work. maher n/a. | $143,000 |
| Jul 19, 2018 | Completed final sign-off Jun 2023 | 345 04th St | to erect 7 stories, no basement, type i-b, office building. ** disturbance of at least 50 cu.yd. of soil, route to dph **Details
to erect 7 stories, no basement, type i-b, office building. ** disturbance of at least 50 cu.yd. of soil, route to dph ** | $15,000,000 |