Silverado Contractors Inc
- Based in
- Oakland
- On San Francisco permits
- Feb 2001 to Aug 2026
- Last 24 months
- 3 permits filed
105 permits since 2000: 91 completed, 2 in progress, 7 never finaled, 5 expired or cancelled.
Of the 7 never-finaled permits, 1 is 5 to 10 years old, 6 are over 10 years old.
This is the city’s permit record, not a license check. It does not show whether the state license is active, bonded or insured. How to read these records
Permits filed each year
How long permits take
Each point is the quarter the permits were filed, for all building permits across San Francisco. A median counts only permits that have finished, so the shaded recent quarters look faster than they will end up: their slow permits have not finished yet. Hover a point for the slowest 10%. Gaps mean fewer than 5 permits. A rise in the issue line is the city’s review backlog, not the contractor.
Most recent permits
Showing the 100 most recent of 105.
| Filed | Outcome | Address | Work described on the permit | Declared cost |
|---|---|---|---|---|
| Aug 6, 2026 | In progress issued Aug 2026 | 301 Clay St | 29th floor: selective demo of non load baearing partitions, removal of power+ data outlets,lighting, switches, associated devices. removal of suspended ceiling tiles, grid +related ceiling mounted devices. removal of (e) floor covering down to the substrate. all work is interior, non structural.Details
29th floor: selective demo of non load baearing partitions, removal of power+ data outlets,lighting, switches, associated devices. removal of suspended ceiling tiles, grid +related ceiling mounted devices. removal of (e) floor covering down to the substrate. all work is interior, non structural. | $300,000 |
| Mar 11, 2026 | In progress issued Aug 2026 | 2 Embarcadero Center | 11/f: selective demolition of non-load-bearing partitions. removal of power and data outlets, lighting, switches, and associated electrical devices including removal of suspended ceiling tiles, grid, and related ceiling mounted devices, except smoke control devices as well as removal of (e)Details
11/f: selective demolition of non-load-bearing partitions. removal of power and data outlets, lighting, switches, and associated electrical devices including removal of suspended ceiling tiles, grid, and related ceiling mounted devices, except smoke control devices as well as removal of (e) | $300,000 |
| Feb 10, 2026 | Completed final sign-off Jun 2026 | 1 Clay St | remove portions of the existing embarcadero fountain located in embarcadero plaza, including the precast concrete tube elements ("arms").Details
remove portions of the existing embarcadero fountain located in embarcadero plaza, including the precast concrete tube elements ("arms"). | $1,000,000 |
| Nov 18, 2022 | Completed final sign-off May 2024 | 121 Blythdale Av | bldg 82f: demolition of 2-story, type v, residential bldg.Details
bldg 82f: demolition of 2-story, type v, residential bldg. | $226,654 |
| Nov 18, 2022 | Completed final sign-off May 2024 | 1724 Sunnydale Av | bldg 10f: demolition of 2-story, type v, residential bldg.Details
bldg 10f: demolition of 2-story, type v, residential bldg. | $228,702 |
| Nov 18, 2022 | Completed final sign-off May 2024 | 120 Blythdale Av | bldg 67e: demolition of 2-story, type v, residential bldg.Details
bldg 67e: demolition of 2-story, type v, residential bldg. | $161,935 |
| Nov 18, 2022 | Completed final sign-off May 2024 | 144 Brookdale Av | bldg 55a: demolition of 2-story, type v, residential bldg.Details
bldg 55a: demolition of 2-story, type v, residential bldg. | $141,728 |
| Nov 18, 2022 | Completed final sign-off May 2024 | 115 Santos St | bldg 84a: demolition of 2-story, type v, residential bldg.Details
bldg 84a: demolition of 2-story, type v, residential bldg. | $135,646 |
| Nov 18, 2022 | Completed final sign-off May 2024 | 1 Santos St | bldg 38e: demolition of 2-story, type v, residential bldg.Details
bldg 38e: demolition of 2-story, type v, residential bldg. | $148,679 |
| Nov 18, 2022 | Completed final sign-off May 2024 | 101 Blythdale Av | bldg 83b: demolition of 2-story, type v, residential bldg.Details
bldg 83b: demolition of 2-story, type v, residential bldg. | $214,465 |
| Nov 18, 2022 | Completed final sign-off May 2024 | 21 Santos St | bldg 37f: demolition of 2-story, type v, residential bldg.Details
bldg 37f: demolition of 2-story, type v, residential bldg. | $222,032 |
| Nov 18, 2022 | Completed final sign-off May 2024 | 50 Santos St | bldg 66e: demolition of 2-story, type v, residential bldg.Details
bldg 66e: demolition of 2-story, type v, residential bldg. | $152,770 |
| Nov 18, 2022 | Completed final sign-off May 2024 | 51 Santos St | bldg 36e: demolition of 2-story, type v, residential bldg.Details
bldg 36e: demolition of 2-story, type v, residential bldg. | $174,174 |
| Nov 18, 2022 | Completed final sign-off May 2024 | 1748 Sunnydale Av | bldg 9f: demolition of 2-story, type v, residential bldg.Details
bldg 9f: demolition of 2-story, type v, residential bldg. | $225,887 |
| Nov 18, 2022 | Completed final sign-off May 2024 | 1651 Sunnydale Av | bldg 21df: demolition of 2-story, type v, residential bldg.Details
bldg 21df: demolition of 2-story, type v, residential bldg. | $93,472 |
| Nov 18, 2022 | Completed final sign-off May 2024 | 51 Santos St | common area: demolition of 1-story, type v, storage bldg.Details
common area: demolition of 1-story, type v, storage bldg. | $137,000 |
| Nov 18, 2022 | Completed final sign-off May 2024 | 1949 Sunnydale Av | bldg 48f: demolition of 2-story, type v, residential bldg.Details
bldg 48f: demolition of 2-story, type v, residential bldg. | $240,676 |
| Nov 18, 2022 | Completed final sign-off May 2024 | 1700 Sunnydale Av | bldg 11f: demolition of 2-story, type v, residential bldg.Details
bldg 11f: demolition of 2-story, type v, residential bldg. | $221,357 |
| Apr 21, 2022 | Completed final sign-off Jun 2023 | 585 Bryant St | demolish a two story auto shop type 3.(marina auto body)Details
demolish a two story auto shop type 3.(marina auto body) | $85,000 |
| Apr 21, 2022 | Completed final sign-off Jun 2023 | 565 Bryant St | demolish a 1 story auto shop type 3.(auto body garage)Details
demolish a 1 story auto shop type 3.(auto body garage) | $43,000 |
| Apr 21, 2022 | Completed final sign-off Jun 2023 | 555 Bryant St | demolish a one story auto shop type 3.Details
demolish a one story auto shop type 3. | $85,000 |
| May 27, 2021 | Completed final sign-off Dec 2021 | 1 Avenue Of The Palms | bldg 34 - demolish a type v-b, 1-story bldgDetails
bldg 34 - demolish a type v-b, 1-story bldg | $15,000 |
| Mar 2, 2021 | Completed final sign-off Jun 2023 | 56 Welsh St | demolish a 1 story auto repair.Details
demolish a 1 story auto repair. | $10,000 |
| Dec 22, 2020 | Completed final sign-off Nov 2022 | 30 Van Ness Av | alteration to remove floors & walls per drawings. reference pa 201912139539.Details
alteration to remove floors & walls per drawings. reference pa 201912139539. | $750,000 |
| Oct 14, 2020 | Completed final sign-off Jan 2024 | 901 16th St | to demolish a type-v, 1-story office building - no basements.Details
to demolish a type-v, 1-story office building - no basements. | $15,000 |
| Sep 10, 2019 | Completed final sign-off Feb 2020 | 200 Cameron Wy | (builidng 21b): riority processing sfha project, (type b) demo two story type 5 construction 6 units apartment.Details
(builidng 21b): riority processing sfha project, (type b) demo two story type 5 construction 6 units apartment. | $15,000 |
| Sep 10, 2019 | Completed final sign-off Feb 2020 | 200 Cameron Wy | priority processing sfha project, (type e) demo two story type 5 construction 10 units apartment.Details
priority processing sfha project, (type e) demo two story type 5 construction 10 units apartment. | $15,000 |
| Sep 10, 2019 | Completed final sign-off Feb 2020 | 200 Cameron Wy | (building 20b): priority processing sfha project, (type b) demo two story type 5 construction 6 units apartment.Details
(building 20b): priority processing sfha project, (type b) demo two story type 5 construction 6 units apartment. | $15,000 |
| Sep 10, 2019 | Completed final sign-off Feb 2020 | 200 Cameron Wy | priority processing sfha project, (type a) demo two story type 5 construction 6 units apartment.Details
priority processing sfha project, (type a) demo two story type 5 construction 6 units apartment. | $15,000 |
| Sep 10, 2019 | Completed final sign-off Feb 2020 | 200 Cameron Wy | priority processing sfha project, (type c) demo two story type 5 construction 10 units apartment.Details
priority processing sfha project, (type c) demo two story type 5 construction 10 units apartment. | $15,000 |
| Sep 10, 2019 | Completed final sign-off Feb 2020 | 200 Cameron Wy | (building 26b): priority processing sfha project, (type b) demo two story type 5 construction 6 units apartment.Details
(building 26b): priority processing sfha project, (type b) demo two story type 5 construction 6 units apartment. | $15,000 |
| Sep 10, 2019 | Completed final sign-off Feb 2020 | 200 Cameron Wy | (building 14b): priority processing sfha project, (type b) demo two story type 5 construction 6 units apartment.Details
(building 14b): priority processing sfha project, (type b) demo two story type 5 construction 6 units apartment. | $15,000 |
| Sep 10, 2019 | Completed final sign-off Feb 2020 | 200 Cameron Wy | (building 18b): priority processing sfha project, (type b) demo two story type 5 construction 6 units apartment.Details
(building 18b): priority processing sfha project, (type b) demo two story type 5 construction 6 units apartment. | $15,000 |
| Sep 10, 2019 | Completed final sign-off Feb 2020 | 200 Cameron Wy | priority processing sfha project, (type a) demo two story type 5 construction 6 units apartment.Details
priority processing sfha project, (type a) demo two story type 5 construction 6 units apartment. | $15,000 |
| Sep 10, 2019 | Completed final sign-off Feb 2020 | 200 Cameron Wy | (building 34d): priority processing sfha project, (type d) demo two story type 5 construction 7 units apartment.Details
(building 34d): priority processing sfha project, (type d) demo two story type 5 construction 7 units apartment. | $15,000 |
| Sep 10, 2019 | Completed final sign-off Feb 2020 | 200 Cameron Wy | priority processing sfha project, (type a) demo two story type 5 construction 6 units apartment.Details
priority processing sfha project, (type a) demo two story type 5 construction 6 units apartment. | $15,000 |
| Sep 10, 2019 | Completed final sign-off Feb 2020 | 200 Cameron Wy | priority processing sfha project, (type e) demo two story type 5 construction 10 units apartment.Details
priority processing sfha project, (type e) demo two story type 5 construction 10 units apartment. | $15,000 |
| Sep 10, 2019 | Completed final sign-off Feb 2020 | 200 Cameron Wy | priority processing sfha project, (type c) demo two story type 5 construction 10 units apartment.Details
priority processing sfha project, (type c) demo two story type 5 construction 10 units apartment. | $15,000 |
| Sep 10, 2019 | Completed final sign-off Feb 2020 | 200 Cameron Wy | (building 29d); priority processing sfha project, (type d) demo two story type 5 construction 7 units apartment.Details
(building 29d); priority processing sfha project, (type d) demo two story type 5 construction 7 units apartment. | $15,000 |
| Sep 10, 2019 | Completed final sign-off Feb 2020 | 200 Cameron Wy | priority processing sfha project, (type e) demo two story type 5 construction 10 units apartment.Details
priority processing sfha project, (type e) demo two story type 5 construction 10 units apartment. | $15,000 |
| Sep 10, 2019 | Completed final sign-off Feb 2020 | 200 Cameron Wy | (building 25d): priority processing sfha project, (type d) demo two story type 5 construction 7 units apartment.Details
(building 25d): priority processing sfha project, (type d) demo two story type 5 construction 7 units apartment. | $15,000 |
| Sep 10, 2019 | Completed final sign-off Feb 2020 | 200 Cameron Wy | (building 31b): priority processing sfha project, (type b) demo two story type 5 construction 6 units apartment.Details
(building 31b): priority processing sfha project, (type b) demo two story type 5 construction 6 units apartment. | $15,000 |
| Sep 10, 2019 | Completed final sign-off Feb 2020 | 200 Cameron Wy | (building 24d): priority processing sfha project, (type d) demo two story type 5 construction 7 units apartment.Details
(building 24d): priority processing sfha project, (type d) demo two story type 5 construction 7 units apartment. | $15,000 |
| Sep 10, 2019 | Completed final sign-off Feb 2020 | 200 Cameron Wy | priority processing sfha project, (type e) demo two story type 5 construction 10 units apartment.Details
priority processing sfha project, (type e) demo two story type 5 construction 10 units apartment. | $15,000 |
| Sep 10, 2019 | Completed final sign-off Feb 2020 | 200 Cameron Wy | (building 39d): priority processing sfha project, (type d) demo two story type 5 construction 7 units apartment.Details
(building 39d): priority processing sfha project, (type d) demo two story type 5 construction 7 units apartment. | $15,000 |
| Sep 10, 2019 | Completed final sign-off Feb 2020 | 200 Cameron Wy | priority processing sfha project, (type a) demo two story type 5 construction 6 units apartment.Details
priority processing sfha project, (type a) demo two story type 5 construction 6 units apartment. | $15,000 |
| Sep 10, 2019 | Completed final sign-off Feb 2020 | 200 Cameron Wy | priority processing sfha project, (type e) demo two story type 5 construction 10 units apartment.Details
priority processing sfha project, (type e) demo two story type 5 construction 10 units apartment. | $15,000 |
| Sep 10, 2019 | Completed final sign-off Feb 2020 | 200 Cameron Wy | (building 3b): priority processing sfha project, (type b) demo two story type 5 construction 6 units apartment.Details
(building 3b): priority processing sfha project, (type b) demo two story type 5 construction 6 units apartment. | $15,000 |
| Sep 10, 2019 | Completed final sign-off Feb 2020 | 200 Cameron Wy | (building 17d): priority processing sfha project, (type d) demo two story type 5 construction 7 units apartment.Details
(building 17d): priority processing sfha project, (type d) demo two story type 5 construction 7 units apartment. | $15,000 |
| Sep 10, 2019 | Completed final sign-off Feb 2020 | 200 Cameron Wy | priority processing sfha project, (type a) demo two story type 5 construction 6 units apartment.Details
priority processing sfha project, (type a) demo two story type 5 construction 6 units apartment. | $15,000 |
| Sep 10, 2019 | Completed final sign-off Feb 2020 | 200 Cameron Wy | (building 27d): priority processing sfha project, (type d) demo two story type 5 construction 7 units apartment.Details
(building 27d): priority processing sfha project, (type d) demo two story type 5 construction 7 units apartment. | $15,000 |
| Sep 10, 2019 | Completed final sign-off Feb 2020 | 200 Cameron Wy | priority processing sfha project, (type c) demo two story type 5 construction 10 units apartment.Details
priority processing sfha project, (type c) demo two story type 5 construction 10 units apartment. | $15,000 |
| Sep 10, 2019 | Completed final sign-off Feb 2020 | 200 Cameron Wy | priority processing sfha project, demo one story type 5 construction sewage pump station.Details
priority processing sfha project, demo one story type 5 construction sewage pump station. | $15,000 |
| Sep 10, 2019 | Completed final sign-off Feb 2020 | 200 Cameron Wy | priority processing sfha project, (type a) demo two story type 5 construction 6 units apartment.Details
priority processing sfha project, (type a) demo two story type 5 construction 6 units apartment. | $15,000 |
| Sep 10, 2019 | Completed final sign-off Feb 2020 | 200 Cameron Wy | priority processing sfha project, (type e) demo two story type 5 construction 10 units apartment.Details
priority processing sfha project, (type e) demo two story type 5 construction 10 units apartment. | $15,000 |
| Sep 10, 2019 | Completed final sign-off Feb 2020 | 200 Cameron Wy | priority processing sfha project, (type c) demo two story type 5 construction 10 units apartment.Details
priority processing sfha project, (type c) demo two story type 5 construction 10 units apartment. | $15,000 |
| Sep 10, 2019 | Completed final sign-off Feb 2020 | 200 Cameron Wy | priority processing sfha project, (type e) demo two story type 5 construction 10 units apartment.Details
priority processing sfha project, (type e) demo two story type 5 construction 10 units apartment. | $15,000 |
| Sep 10, 2019 | Completed final sign-off Feb 2020 | 200 Cameron Wy | (building 41b): priority processing sfha project, (type b) demo two story type 5 construction 6 units apartment.Details
(building 41b): priority processing sfha project, (type b) demo two story type 5 construction 6 units apartment. | $15,000 |
| Sep 10, 2019 | Completed final sign-off Feb 2020 | 200 Cameron Wy | (building 15d): priority processing sfha project, (type d) demo two story type 5 construction 7 units apartment.Details
(building 15d): priority processing sfha project, (type d) demo two story type 5 construction 7 units apartment. | $15,000 |
| Mar 28, 2019 | Never finaled issued Apr 2019, no final | 1125 Market St | (3) potholing to uncover bottom of foundation.Details
(3) potholing to uncover bottom of foundation. | $18,000 |
| Sep 17, 2018 | Completed final sign-off Jul 2021 | 38 Otis St | demolish 1-story industrial/automotive glass repairDetails
demolish 1-story industrial/automotive glass repair | $85,000 |
| Sep 17, 2018 | Completed final sign-off Jul 2021 | 30 Otis St | demolish 2-story industrial/automotive glass repair & ballet schoolDetails
demolish 2-story industrial/automotive glass repair & ballet school | $85,000 |
| Sep 17, 2018 | Completed final sign-off Jul 2021 | 74 12th St | bldg# 2. demolish 1-story industrial/automotive glass repair.Details
bldg# 2. demolish 1-story industrial/automotive glass repair. | $11,666 |
| Sep 17, 2018 | Completed final sign-off Jul 2021 | 98 12th St | demolish 1-story & mezz retail carpet & flooring storeDetails
demolish 1-story & mezz retail carpet & flooring store | $75,000 |
| Sep 17, 2018 | Completed final sign-off Jul 2021 | 74 12th St | bldg# 1. demolish 1-story industrial/automotive glass repairDetails
bldg# 1. demolish 1-story industrial/automotive glass repair | $11,666 |
| Sep 17, 2018 | Completed final sign-off Jul 2021 | 74 12th St | bldg# 3. demolish 1-story industrial/automotive glass repairDetails
bldg# 3. demolish 1-story industrial/automotive glass repair | $11,666 |
| Sep 17, 2018 | Completed final sign-off Jul 2021 | 14 Otis St | demolish 3-story commercial/officeDetails
demolish 3-story commercial/office | $95,000 |
| Dec 5, 2017 | Completed final sign-off Oct 2018 | 75 Howard St | to demolish 7 stories, parking garage building. ** maher: n/a **Details
to demolish 7 stories, parking garage building. ** maher: n/a ** | $2,185,000 |
| Dec 5, 2017 | Completed final sign-off May 2019 | 385 Channel | demolish 1 story storage bldgDetails
demolish 1 story storage bldg | $179,000 |
| May 24, 2017 | Completed final sign-off Aug 2017 | 82 01st St | to comply with 201772841 - for installation of platform susported on cantilever beams extending through property line wall of 78 1st st. 3708-007 for scaffold erectionDetails
to comply with 201772841 - for installation of platform susported on cantilever beams extending through property line wall of 78 1st st. 3708-007 for scaffold erection | $1,000 |
| May 24, 2017 | Completed final sign-off Aug 2017 | 78 01st St | to comply with nov 201772602 - install cantilever beams for support of platform at 82-84 1st street 3708/008 faciliting scaffold erection over 82-84 ast streetDetails
to comply with nov 201772602 - install cantilever beams for support of platform at 82-84 1st street 3708/008 faciliting scaffold erection over 82-84 ast street | $1,000 |
| Apr 27, 2017 | Completed final sign-off Sep 2017 | 78 01st St | administrative permit only, no work. for partial compliance to nov 201772602, revision to 2016097343 sheet d1, d2. remove ref to scaffolding on cantilever support over adjacent building at 82-84 1st, 25 jessie and 1 ecker stDetails
administrative permit only, no work. for partial compliance to nov 201772602, revision to 2016097343 sheet d1, d2. remove ref to scaffolding on cantilever support over adjacent building at 82-84 1st, 25 jessie and 1 ecker st | |
| Sep 9, 2016 | Completed final sign-off Apr 2018 | 78 01st St | demo alteration of building. work also includes temporary bracing.Details
demo alteration of building. work also includes temporary bracing. | $550,000 |
| Apr 21, 2016 | Completed final sign-off Jan 2018 | 40 01st St | to demolish 5 stories, office / retail building.Details
to demolish 5 stories, office / retail building. | $200,000 |
| Apr 21, 2016 | Completed final sign-off Oct 2017 | 50 01st St | to demolish 7 stories, office / retail building.Details
to demolish 7 stories, office / retail building. | $250,000 |
| Apr 21, 2016 | Completed final sign-off Oct 2017 | 62 01st St | to demolish 5 stories office / retail building.Details
to demolish 5 stories office / retail building. | $250,000 |
| Dec 3, 2015 | Expired or cancelled withdrawn Jun 2016 | 1000 Brannan St | removal of existing elevated wood framed water tank, the supporting steel tank supports, and unused existing steel boiler pipe, exhaust; maher n/aDetails
removal of existing elevated wood framed water tank, the supporting steel tank supports, and unused existing steel boiler pipe, exhaust; maher n/a | $50,000 |
| Nov 20, 2015 | Completed final sign-off Oct 2016 | 706 Mission St | no structural demolition or work - comply with ab-017. exploratory demolition on floors: 10, 9, 7, 6,5, 3, & 2. no work on floors 1,4, 8 and roof. interior work only.Details
no structural demolition or work - comply with ab-017. exploratory demolition on floors: 10, 9, 7, 6,5, 3, & 2. no work on floors 1,4, 8 and roof. interior work only. | $2,000 |
| Aug 6, 2015 | Completed final sign-off Apr 2016 | 150 Van Ness Av | administrative change to remove note: "must maintain existing fire life safety systems during construction" ref pa 2015 0317 1042Details
administrative change to remove note: "must maintain existing fire life safety systems during construction" ref pa 2015 0317 1042 | |
| Mar 17, 2015 | Completed final sign-off Apr 2016 | 150 Van Ness Av | demolish (e) office building.Details
demolish (e) office building. | $10,000 |
| Mar 2, 2015 | Completed final sign-off Dec 2015 | 155 Hayes St | demolish one story for pedestrian bridge.Details
demolish one story for pedestrian bridge. | $10,000 |
| Nov 25, 2014 | Completed final sign-off Apr 2016 | 490 Jamestown Av | removal of asbestos containing materials & other hazardous materials as identified in the hazardous material removal drawings prepared by van brunt associates, dated 9/14/14Details
removal of asbestos containing materials & other hazardous materials as identified in the hazardous material removal drawings prepared by van brunt associates, dated 9/14/14 | $2,695,000 |
| Nov 24, 2014 | Expired or cancelled withdrawn Mar 2015 | 490 Jamestown Av | implosion demo: 4-story, sports and entertainment stadium - candlestick stadium.Details
implosion demo: 4-story, sports and entertainment stadium - candlestick stadium. | $500,000 |
| Nov 24, 2014 | Completed final sign-off Apr 2016 | 490 Jamestown Av | conventional demo: 4-story, sports and entertainment stadium - candlestick stadium.Details
conventional demo: 4-story, sports and entertainment stadium - candlestick stadium. | $5,500,000 |
| May 1, 2014 | Completed final sign-off Feb 2016 | 270 Brannan St | shoring cantilever soldier beams along brannan street frontage at site. accomodate for construction at 270 brannon app#201312174402. n/a for the maher ordinance #155-13Details
shoring cantilever soldier beams along brannan street frontage at site. accomodate for construction at 270 brannon app#201312174402. n/a for the maher ordinance #155-13 | $70,000 |
| Mar 4, 2014 | Never finaled issued May 2014, no final | 270 Brannan St | demolish 2 stories of office buildingDetails
demolish 2 stories of office building | $100,000 |
| Sep 6, 2012 | Completed final sign-off Jul 2013 | 1169 Market St | demolish 8 story residential and commercial building.Details
demolish 8 story residential and commercial building. | $1,500,000 |
| Jan 30, 2012 | Never finaled issued May 2012, no final | 260 05th St | demolition of two story office building.Details
demolition of two story office building. | $250,000 |
| Jun 21, 2010 | Completed final sign-off Dec 2011 | 1650 15th St | to demolish 1 story vacant / printing shop.Details
to demolish 1 story vacant / printing shop. | $30,000 |
| Jun 21, 2010 | Completed final sign-off Dec 2011 | 1886 Mission St | to demolish 2 stories vacant / printing shop.Details
to demolish 2 stories vacant / printing shop. | $80,000 |
| Nov 16, 2007 | Never finaled issued Nov 2007, no final | 127 Ellis St | exploritory demo in two rooms. 5th floor, rm 514,517. remove some wall coverings, mouldings & basetrim. no structural work.Details
exploritory demo in two rooms. 5th floor, rm 514,517. remove some wall coverings, mouldings & basetrim. no structural work. | $5,000 |
| Mar 23, 2007 | Never finaled issued Sep 2007, no final | 461 Baker St | to demolish a churchDetails
to demolish a church | |
| Mar 23, 2007 | Completed final sign-off Aug 2007 | 1390 Mission St | to demolish a restaurantDetails
to demolish a restaurant | |
| Feb 23, 2007 | Completed final sign-off Mar 2007 | 333 Fremont St | renew 200508170463 for final inspection. permit was originally issued for demolition of buildingDetails
renew 200508170463 for final inspection. permit was originally issued for demolition of building | |
| Apr 7, 2006 | Completed final sign-off Jun 2008 | 40 Jessie St | 3 story vertical addition to (e) office building.Details
3 story vertical addition to (e) office building. | $10,800,000 |
| Feb 17, 2006 | Completed final sign-off Feb 2007 | 230 Turk St | demolish 1, type 1, 5 story hotelDetails
demolish 1, type 1, 5 story hotel | |
| Aug 8, 2005 | Never finaled issued Aug 2005, no final | 445 Harrison St | to demolish 3 story parking garage.Details
to demolish 3 story parking garage. | |
| Apr 28, 2005 | Expired or cancelled expired Nov 2013 | 425 01st St | demolish 11 stories office/parking buildingDetails
demolish 11 stories office/parking building | |
| Sep 2, 2004 | Completed final sign-off Sep 2005 | 2201 Bay Shore Bl | demolish 1 story warehouse for lock parts.Details
demolish 1 story warehouse for lock parts. | |
| Jan 24, 2002 | Expired or cancelled expired May 2011 | 701 16th St | demolish a 1 story wholesale/ warehouseDetails
demolish a 1 story wholesale/ warehouse |