Signature Homes Inc
- Based in
- Pleasanton
- On San Francisco permits
- Jul 2012 to Jul 2013
- Last 24 months
- 0 permits filed
11 permits since 2000: 10 completed, 1 never finaled.
Of the 1 never-finaled permit, 1 is over 10 years old.
This is the city’s permit record, not a license check. It does not show whether the state license is active, bonded or insured. How to read these records
Permits filed each year
How long permits take
Each point is the quarter the permits were filed, for all building permits across San Francisco. A median counts only permits that have finished, so the shaded recent quarters look faster than they will end up: their slow permits have not finished yet. Hover a point for the slowest 10%. Gaps mean fewer than 5 permits. A rise in the issue line is the city’s review backlog, not the contractor.
Most recent permits
| Filed | Outcome | Address | Work described on the permit | Declared cost |
|---|---|---|---|---|
| Jul 11, 2013 | Completed final sign-off Oct 2013 | 108 Seal Cove Tr | bldg # 1:floor and roof truss design. ref app#200512281117Details
bldg # 1:floor and roof truss design. ref app#200512281117 | |
| Jul 11, 2013 | Completed final sign-off Oct 2013 | 200 Diamond Cove Tr | bldg # 20:floor and roof truss design. ref app#200512281122Details
bldg # 20:floor and roof truss design. ref app#200512281122 | |
| Jul 11, 2013 | Completed final sign-off Oct 2013 | 120 Diamond Cove Tr | bldg # 18:floor and roof truss design. ref app#200512281128Details
bldg # 18:floor and roof truss design. ref app#200512281128 | |
| May 14, 2013 | Completed final sign-off Jun 2013 | 101 Otter Cove Tr | bldg 10: floor and roof truss submittal. this is a deffered submittal item under ref. pa#2005-1228-1130.Details
bldg 10: floor and roof truss submittal. this is a deffered submittal item under ref. pa#2005-1228-1130. | |
| May 14, 2013 | Completed final sign-off Aug 2013 | 115 Otter Cove Tr | bldg 9 - floor & roof truss designs, ref pa #2005.12.28.1136Details
bldg 9 - floor & roof truss designs, ref pa #2005.12.28.1136 | |
| Mar 4, 2013 | Completed final sign-off Apr 2013 | 109 Seal Cove Tr | bldg 2- floor & roof truss designs. ref pa# 200512281124Details
bldg 2- floor & roof truss designs. ref pa# 200512281124 | |
| Jan 31, 2013 | Never finaled issued Apr 2013, no final | 115 Otter Cove Tr | thorpe design to install a new overhead 13r fire sprinkler system for eight residential units (115-129). plans include a 2-inch dedicated fire service with 2-inch underground copper 'k' piping. 200 heads total.Details
thorpe design to install a new overhead 13r fire sprinkler system for eight residential units (115-129). plans include a 2-inch dedicated fire service with 2-inch underground copper 'k' piping. 200 heads total. | $20,000 |
| Jan 25, 2013 | Completed final sign-off Feb 2013 | 112 Diamond Cove Tr | bldg 16 floor & roof truss designs reference pa#2005-1228-1121Details
bldg 16 floor & roof truss designs reference pa#2005-1228-1121 | |
| Nov 29, 2012 | Completed final sign-off Feb 2013 | 213 Diamond Cove Tr | bldg 21 - floor & roof truss plans, ref pa #205.1228.1141Details
bldg 21 - floor & roof truss plans, ref pa #205.1228.1141 | |
| Sep 4, 2012 | Completed final sign-off Oct 2012 | 201 Diamond Cove Tr | floor and roof truss designs and calculationsDetails
floor and roof truss designs and calculations | |
| Jul 19, 2012 | Completed final sign-off Sep 2012 | 100 Diamond Cove Tr | floor and roof truss designs and calculations. ref 200512281127Details
floor and roof truss designs and calculations. ref 200512281127 |