587 permits since 2000: 398 completed, 56 in progress, 111 never finaled, 22 expired or cancelled.
Of the 111 never-finaled permits, 71 are 3 to 5 years old, 40 are 5 to 10 years old.
This is the city’s permit record, not a license check. It does not show whether the state license is active, bonded or insured. How to read these records
Permits filed each year
How long permits take
Each point is the quarter the permits were filed, for all building permits across San Francisco. A median counts only permits that have finished, so the shaded recent quarters look faster than they will end up: their slow permits have not finished yet. Hover a point for the slowest 10%. Gaps mean fewer than 5 permits. A rise in the issue line is the city’s review backlog, not the contractor.
Most recent permits
Showing the 100 most recent of 587.
| Filed | Outcome | Address | Work described on the permit | Declared cost |
|---|---|---|---|---|
| Jun 1, 2026 | In progress issued Jun 2026 | 2336 Cecilia Av | re-roofing: remove and replace roofing material / existing roofing material (in-kind)Details
re-roofing: remove and replace roofing material / existing roofing material (in-kind) | $18,000 |
| Jun 1, 2026 | Completed final sign-off Jun 2026 | 69 Aztec St | re-roofing: remove and replace roofing material / existing roofing material (in-kind)Details
re-roofing: remove and replace roofing material / existing roofing material (in-kind) | $17,000 |
| May 27, 2026 | In progress issued May 2026 | 2614 39th Av | re-roofing: remove and replace roofing material / existing roofing material (in-kind)Details
re-roofing: remove and replace roofing material / existing roofing material (in-kind) | $17,000 |
| May 26, 2026 | Completed final sign-off Jul 2026 | 2275 35th Av | re-roofing: remove and replace roofing material / existing roofing material (in-kind)Details
re-roofing: remove and replace roofing material / existing roofing material (in-kind) | $18,800 |
| May 15, 2026 | In progress issued May 2026 | 1850 10th Av | reroofing. no hot works.Details
reroofing. no hot works. | $20,000 |
| May 15, 2026 | In progress issued May 2026 | 163 Colby St | reroofing. no hot works.Details
reroofing. no hot works. | $12,500 |
| Apr 27, 2026 | Completed final sign-off May 2026 | 9 Lydia Av | re-roofing: remove and replace roofing material / existing roofing material (in-kind)Details
re-roofing: remove and replace roofing material / existing roofing material (in-kind) | $8,800 |
| Apr 16, 2026 | In progress issued Apr 2026 | 68 Pixley St | reroofing. no hot works. no work to (e) roof structural sheathing.Details
reroofing. no hot works. no work to (e) roof structural sheathing. | $16,000 |
| Apr 13, 2026 | Completed final sign-off May 2026 | 618 Sanchez St | reroofing with in kind materials 5a plybase & 5a moddified bitumen, no hot works.Details
reroofing with in kind materials 5a plybase & 5a moddified bitumen, no hot works. | $32,000 |
| Apr 13, 2026 | In progress issued Apr 2026 | 297 30th Av | reroofing with in kind materials 5a plybase & 5a moddified bitumen, no hot works.Details
reroofing with in kind materials 5a plybase & 5a moddified bitumen, no hot works. | $29,000 |
| Mar 16, 2026 | Completed final sign-off Apr 2026 | 2763 Bush St | reroofing. no hot works.Details
reroofing. no hot works. | $8,900 |
| Mar 9, 2026 | In progress issued Mar 2026 | 155 Winfield St | re-roofing: remove and replace roofing material / existing roofing material (in-kind)Details
re-roofing: remove and replace roofing material / existing roofing material (in-kind) | $25,000 |
| Feb 6, 2026 | In progress issued Feb 2026 | 715 Duboce Av | re-roofing: remove and replace roofing material / existing roofing material (in-kind)Details
re-roofing: remove and replace roofing material / existing roofing material (in-kind) | $35,000 |
| Feb 6, 2026 | In progress issued Feb 2026 | 291 30th Av | re-roofing: remove and replace roofing material / existing roofing material (in-kind)Details
re-roofing: remove and replace roofing material / existing roofing material (in-kind) | $35,000 |
| Jan 27, 2026 | In progress issued Jan 2026 | 1934 35th Av | re-roofing: remove and replace roofing material / existing roofing material (in-kind)Details
re-roofing: remove and replace roofing material / existing roofing material (in-kind) | $25,000 |
| Jan 9, 2026 | In progress issued Jan 2026 | 1410 Jefferson St | reroof no hot works.Details
reroof no hot works. | $42,000 |
| Dec 7, 2025 | In progress issued Dec 2025 | 790 Funston Av | re-roofing: remove and replace roofing material / existing roofing material (in-kind)Details
re-roofing: remove and replace roofing material / existing roofing material (in-kind) | $25,000 |
| Dec 1, 2025 | Completed final sign-off Dec 2025 | 726 Lake St | re-roofingDetails
re-roofing | $25,000 |
| Nov 26, 2025 | Completed final sign-off Apr 2026 | 263 Carl St | re-roofingDetails
re-roofing | $23,000 |
| Nov 26, 2025 | Completed final sign-off Dec 2025 | 24 Retiro Wy | re-roofingDetails
re-roofing | $21,000 |
| Nov 5, 2025 | In progress issued Nov 2025 | 1406 Rhode Island St | re-roofing w/ in kind materials, sa ply base. no hot workDetails
re-roofing w/ in kind materials, sa ply base. no hot work | $19,000 |
| Oct 29, 2025 | In progress issued Oct 2025 | 1631 Beach St | reroofing. no hot works.Details
reroofing. no hot works. | $28,000 |
| Oct 26, 2025 | In progress issued Oct 2025 | 2871 24th St | re-roofing: remove and replace roofing material / existing roofing material (in-kind)Details
re-roofing: remove and replace roofing material / existing roofing material (in-kind) | $20,000 |
| Oct 8, 2025 | Completed final sign-off Nov 2025 | 309 Molimo Dr | re-roofing: remove and replace roofing material / existing roofing material (in-kind)Details
re-roofing: remove and replace roofing material / existing roofing material (in-kind) | $13,000 |
| Oct 6, 2025 | In progress issued Oct 2025 | 44 Langton St | reroofing: flat roof, r/r self-adhesive ply base, no hot works.Details
reroofing: flat roof, r/r self-adhesive ply base, no hot works. | $24,000 |
| Sep 26, 2025 | In progress issued Sep 2025 | 558 23rd Av | re-roofing: remove and replace roofing material / existing roofing material (in-kind)Details
re-roofing: remove and replace roofing material / existing roofing material (in-kind) | $33,000 |
| Sep 21, 2025 | In progress issued Sep 2025 | 127 Saint Charles Av | re-roofing: remove and replace roofing material / existing roofing material (in-kind)Details
re-roofing: remove and replace roofing material / existing roofing material (in-kind) | $16,000 |
| Sep 16, 2025 | In progress issued Sep 2025 | 278 Liberty St | re-roofing no hot workDetails
re-roofing no hot work | $20,000 |
| Aug 29, 2025 | In progress issued Aug 2025 | 672 Prentiss St | re-roofing: remove and replace roofing material / existing roofing material (in-kind)Details
re-roofing: remove and replace roofing material / existing roofing material (in-kind) | $13,000 |
| Aug 19, 2025 | In progress issued Aug 2025 | 4087 17th St | reroof. no hot works.Details
reroof. no hot works. | $9,000 |
| Aug 18, 2025 | In progress issued Aug 2025 | 1249 Diamond St | re-roofing: remove and replace roofing material / existing roofing material (in-kind)Details
re-roofing: remove and replace roofing material / existing roofing material (in-kind) | $14,000 |
| Aug 14, 2025 | In progress issued Aug 2025 | 929 Clay St | reroofing. no hot works.Details
reroofing. no hot works. | $100,000 |
| Aug 11, 2025 | In progress issued Aug 2025 | 3232 Mission St | reroofing inkind, no hot worksDetails
reroofing inkind, no hot works | $26,000 |
| Aug 8, 2025 | In progress issued Aug 2025 | 36 Romain St | re-roofing: remove and replace roofing material / existing roofing material (in-kind)Details
re-roofing: remove and replace roofing material / existing roofing material (in-kind) | $45,000 |
| Jul 30, 2025 | In progress issued Jul 2025 | 28 Harrington St | re-roofing: remove and replace roofing material / existing roofing material (in-kind)Details
re-roofing: remove and replace roofing material / existing roofing material (in-kind) | $20,000 |
| Jul 24, 2025 | In progress issued Jul 2025 | 51 Delmar St | reroofing with in-kind materials. no hot works.Details
reroofing with in-kind materials. no hot works. | $24,000 |
| Jul 16, 2025 | In progress issued Jul 2025 | 4441 18th St | reroofing w/o hot works. self-adhesive.Details
reroofing w/o hot works. self-adhesive. | $10,000 |
| Jul 7, 2025 | In progress issued Jul 2025 | 488 12th Av | re-roofing: remove and replace roofing material / existing roofing material (in-kind)Details
re-roofing: remove and replace roofing material / existing roofing material (in-kind) | $22,000 |
| Jun 17, 2025 | In progress issued Jun 2025 | 2155 Turk Bl | re-roofing: remove and replace roofing material / existing roofing material (in-kind)Details
re-roofing: remove and replace roofing material / existing roofing material (in-kind) | $29,000 |
| Jun 16, 2025 | In progress issued Jun 2025 | 67 Madrone Av | reroof no hot worksDetails
reroof no hot works | $20,000 |
| Jun 8, 2025 | In progress issued Jun 2025 | 1393 Noe St | re-roofing: remove and replace roofing material / existing roofing material (in-kind)Details
re-roofing: remove and replace roofing material / existing roofing material (in-kind) | $30,000 |
| Jun 2, 2025 | In progress issued Jun 2025 | 1351 26th Av | re-roofing: remove and replace roofing material / existing roofing material (in-kind)Details
re-roofing: remove and replace roofing material / existing roofing material (in-kind) | $22,000 |
| May 27, 2025 | Completed final sign-off Jun 2025 | 1390 Utah St | reroofing. no hot works.Details
reroofing. no hot works. | $50,000 |
| May 19, 2025 | In progress issued May 2025 | 3174 Turk Bl | reroofing with in/kind material. no hot works.Details
reroofing with in/kind material. no hot works. | $29,000 |
| May 19, 2025 | In progress issued May 2025 | 214 Clayton St | 214-216 clayton st: reroofing. no hot works.Details
214-216 clayton st: reroofing. no hot works. | $26,000 |
| May 13, 2025 | Completed final sign-off Jun 2025 | 213 Gold Mine Dr | re-roofing: remove and replace roofing material / existing roofing material (in-kind)Details
re-roofing: remove and replace roofing material / existing roofing material (in-kind) | $26,000 |
| May 9, 2025 | Completed final sign-off Jun 2025 | 494 Flood Av | re-roofing: remove and replace roofing material / existing roofing material (in-kind)Details
re-roofing: remove and replace roofing material / existing roofing material (in-kind) | $14,000 |
| May 5, 2025 | Completed final sign-off Jun 2025 | 4151 Ulloa St | re-roofing: remove and replace roofing material / existing roofing material (in-kind)Details
re-roofing: remove and replace roofing material / existing roofing material (in-kind) | $22,000 |
| Apr 28, 2025 | Completed final sign-off Apr 2026 | 2075 Greenwich St | reroofing. no hot works.Details
reroofing. no hot works. | $22,800 |
| Apr 23, 2025 | Completed final sign-off Jun 2025 | 130 Denslowe Dr | re-roofing: remove and replace roofing material / existing roofing material (in-kind)Details
re-roofing: remove and replace roofing material / existing roofing material (in-kind) | $26,000 |
| Apr 22, 2025 | Completed final sign-off Jun 2025 | 181 Jersey St | re-roofing: remove and replace roofing material / existing roofing material (in-kind)Details
re-roofing: remove and replace roofing material / existing roofing material (in-kind) | $19,000 |
| Apr 8, 2025 | In progress issued Apr 2025 | 3585 18th St | re-roofing no hot worksDetails
re-roofing no hot works | $38,000 |
| Mar 20, 2025 | Completed final sign-off Oct 2025 | 47 Delmar St | reroof no torch downDetails
reroof no torch down | $42,000 |
| Mar 20, 2025 | In progress issued Mar 2025 | 2391 12th Av | reroof no torch downDetails
reroof no torch down | $32,000 |
| Feb 27, 2025 | Completed final sign-off Jun 2025 | 2495 27th Av | re-roofing: remove and replace roofing material / existing roofing material (in-kind)Details
re-roofing: remove and replace roofing material / existing roofing material (in-kind) | $31,000 |
| Feb 27, 2025 | Completed final sign-off Mar 2025 | 345 Juanita Wy | re-roofing: remove and replace roofing material / existing roofing material (in-kind)Details
re-roofing: remove and replace roofing material / existing roofing material (in-kind) | $26,000 |
| Feb 25, 2025 | Completed final sign-off Oct 2025 | 1219 Arguello Bl | re-roofing: remove and replace roofing material / existing roofing material (in-kind)Details
re-roofing: remove and replace roofing material / existing roofing material (in-kind) | $30,000 |
| Feb 18, 2025 | Completed final sign-off Oct 2025 | 57 14th Av | re-roofing: remove and replace roofing material / existing roofing material (in-kind)Details
re-roofing: remove and replace roofing material / existing roofing material (in-kind) | $35,000 |
| Feb 5, 2025 | Completed final sign-off Oct 2025 | 865 Castro St | to obtain a final inspection for work approved under pa# 2021-0212-4600. all work is complete.Details
to obtain a final inspection for work approved under pa# 2021-0212-4600. all work is complete. | |
| Feb 5, 2025 | Completed final sign-off Oct 2025 | 125 Montalvo Av | to obtain a final inspection for work approved under pa# 2021-1105-1929. all work is complete.Details
to obtain a final inspection for work approved under pa# 2021-1105-1929. all work is complete. | |
| Feb 5, 2025 | Completed final sign-off Oct 2025 | 3520 17th St | to obtain a final inspection for work approved under pa# 2021-0902-7733. all work is complete.Details
to obtain a final inspection for work approved under pa# 2021-0902-7733. all work is complete. | |
| Feb 5, 2025 | Completed final sign-off Oct 2025 | 32 Hartford St | to obtain a final inspection for work approved under pa# 2021-0621-2824. all work is complete.Details
to obtain a final inspection for work approved under pa# 2021-0621-2824. all work is complete. | |
| Feb 5, 2025 | Completed final sign-off Oct 2025 | 869 Castro St | to obtain a final inspection for work approved under pa# 2021-0212-4601. all work is complete.Details
to obtain a final inspection for work approved under pa# 2021-0212-4601. all work is complete. | |
| Feb 5, 2025 | Completed final sign-off Oct 2025 | 173 Hartford St | to obtain a final inspection for work approved under pa# 2021-0209-4311. all work is complete.Details
to obtain a final inspection for work approved under pa# 2021-0209-4311. all work is complete. | |
| Feb 5, 2025 | Completed final sign-off Oct 2025 | 345 Vicksburg St | to obtain a final inspection for work approved under pa# 202202027188. all work is complete.Details
to obtain a final inspection for work approved under pa# 202202027188. all work is complete. | |
| Feb 5, 2025 | Completed final sign-off Oct 2025 | 1500 Taylor St | to obtain a final inspection for work approved under pa#2022-0107-5590. all work is complete.Details
to obtain a final inspection for work approved under pa#2022-0107-5590. all work is complete. | |
| Feb 5, 2025 | Completed final sign-off Oct 2025 | 333 Lombard St | to obtain a final inspection for work approved under pa# 2021-0728-5276. all work is complete.Details
to obtain a final inspection for work approved under pa# 2021-0728-5276. all work is complete. | |
| Feb 5, 2025 | Completed final sign-off Oct 2025 | 289 Douglass St | to obtain a final inspection for work approved under pa# 2021-0706-3831. all work is complete.Details
to obtain a final inspection for work approved under pa# 2021-0706-3831. all work is complete. | |
| Feb 3, 2025 | Completed final sign-off Jun 2025 | 3991 17th St | reroofing w/in-kind replacement material. gta bitumen cap. torchDetails
reroofing w/in-kind replacement material. gta bitumen cap. torch | $10,800 |
| Jan 23, 2025 | Completed final sign-off Feb 2025 | 156 08th Av | to obtain a final inspection for work approved under pa #202107275221. all work is complete.Details
to obtain a final inspection for work approved under pa #202107275221. all work is complete. | |
| Jan 23, 2025 | Completed final sign-off Feb 2025 | 2608 Green St | to obtain a final inspection for work approved under pa #202110120288. all work is complete.Details
to obtain a final inspection for work approved under pa #202110120288. all work is complete. | |
| Jan 23, 2025 | Completed final sign-off Feb 2025 | 70 Ina Ct | to obtain a final inspection for work approved under pa #202107275220. all work is complete.Details
to obtain a final inspection for work approved under pa #202107275220. all work is complete. | |
| Jan 23, 2025 | Completed final sign-off Feb 2025 | 588 42nd Av | to obtain a final inspection for work approved under pa #202111051927. all work is complete.Details
to obtain a final inspection for work approved under pa #202111051927. all work is complete. | |
| Jan 23, 2025 | Completed final sign-off Feb 2025 | 738 19th Av | to obtain a final inspection for work approved under pa #202105130314. all work is complete.Details
to obtain a final inspection for work approved under pa #202105130314. all work is complete. | |
| Jan 23, 2025 | Completed final sign-off Feb 2025 | 20 Pinehurst Wy | to obtain a final inspection for work approved under pa #202102265492. all work is complete.Details
to obtain a final inspection for work approved under pa #202102265492. all work is complete. | |
| Jan 23, 2025 | Completed final sign-off Feb 2025 | 2281 Green St | to obtain a final inspection for work approved under pa #202106253280. all work is complete.Details
to obtain a final inspection for work approved under pa #202106253280. all work is complete. | |
| Jan 23, 2025 | Completed final sign-off Feb 2025 | 4435 Anza St | to obtain a final inspection for work approved under pa #202105261119. all work is complete.Details
to obtain a final inspection for work approved under pa #202105261119. all work is complete. | |
| Jan 23, 2025 | Completed final sign-off Feb 2025 | 6412 California St | to obtain a final inspection for work approved under pa #202109239078. all work is complete.Details
to obtain a final inspection for work approved under pa #202109239078. all work is complete. | |
| Jan 23, 2025 | Completed final sign-off Feb 2025 | 2517 Octavia St | to obtain a final inspection for work approved under pa #202104198872. all work is complete.Details
to obtain a final inspection for work approved under pa #202104198872. all work is complete. | |
| Jan 23, 2025 | Completed final sign-off Feb 2025 | 2515 Filbert St | to obtain a final inspection for work approved under pa #202111092115. all work is complete.Details
to obtain a final inspection for work approved under pa #202111092115. all work is complete. | |
| Jan 23, 2025 | Completed final sign-off Feb 2025 | 3737 Broderick St | to obtain a final inspection for work approved under pa #202107214850. all work is complete.Details
to obtain a final inspection for work approved under pa #202107214850. all work is complete. | |
| Jan 23, 2025 | Completed final sign-off Feb 2025 | 2467 Jackson St | to obtain a final inspection for work approved under pa #202106112275. all work is complete.Details
to obtain a final inspection for work approved under pa #202106112275. all work is complete. | |
| Jan 23, 2025 | Completed final sign-off Feb 2025 | 585 Monterey Bl | to obtain a final inspection for work approved under pa #202109138284. all work is complete.Details
to obtain a final inspection for work approved under pa #202109138284. all work is complete. | |
| Jan 23, 2025 | Completed final sign-off Feb 2025 | 772 16th Av | to obtain a final inspection for work approved under pa #202102228417. all work is complete.Details
to obtain a final inspection for work approved under pa #202102228417. all work is complete. | |
| Jan 21, 2025 | Completed final sign-off Mar 2025 | 74 Macondray Ln | reroofing. bituman self adhesive. no hot works.Details
reroofing. bituman self adhesive. no hot works. | $24,000 |
| Jan 10, 2025 | Completed final sign-off Feb 2025 | 651 43rd Av | to obtain final inspection for work approved under pa #202204041488. all work is complete.Details
to obtain final inspection for work approved under pa #202204041488. all work is complete. | |
| Dec 30, 2024 | Completed final sign-off Oct 2025 | 952 Vallejo St | reroofing (no hot works)Details
reroofing (no hot works) | $29,000 |
| Dec 9, 2024 | Completed final sign-off Oct 2025 | 2167 28th Av | re-roofing: remove and replace roofing material / existing roofing material (in-kind)Details
re-roofing: remove and replace roofing material / existing roofing material (in-kind) | $22,000 |
| Dec 4, 2024 | Completed final sign-off Oct 2025 | 63 Brewster St | re-roofing: remove and replace roofing material / existing roofing material (in-kind)Details
re-roofing: remove and replace roofing material / existing roofing material (in-kind) | $10,000 |
| Dec 2, 2024 | Completed final sign-off Jan 2025 | 1547 Alabama St | reroofing: with in kind material. (no hotworks). flat roof with slope less than 2:12 pitch.Details
reroofing: with in kind material. (no hotworks). flat roof with slope less than 2:12 pitch. | $27,000 |
| Nov 29, 2024 | Completed final sign-off Jan 2025 | 41 Beachmont Dr | re-roofing: remove and replace roofing material / existing roofing material (in-kind)Details
re-roofing: remove and replace roofing material / existing roofing material (in-kind) | $75,000 |
| Nov 8, 2024 | In progress issued Nov 2024 | 647 32nd Av | re-roofing: remove and replace roofing material / existing roofing material (in-kind)Details
re-roofing: remove and replace roofing material / existing roofing material (in-kind) | $32,000 |
| Nov 7, 2024 | Completed final sign-off Jan 2025 | 38 Ellington Av | re-roofing: remove and replace roofing material / existing roofing material (in-kind)Details
re-roofing: remove and replace roofing material / existing roofing material (in-kind) | $17,300 |
| Oct 30, 2024 | In progress issued Oct 2024 | 1941 Taylor St | re-roofing: remove and replace roofing material / existing roofing material (in-kind)Details
re-roofing: remove and replace roofing material / existing roofing material (in-kind) | $36,000 |
| Oct 23, 2024 | In progress issued Oct 2024 | 1910 12th Av | re-roofing: remove and replace roofing material / existing roofing material (in-kind)Details
re-roofing: remove and replace roofing material / existing roofing material (in-kind) | $25,000 |
| Oct 16, 2024 | In progress issued Oct 2024 | 3006 Laguna St | reroofingDetails
reroofing | $24,000 |
| Oct 16, 2024 | In progress issued Oct 2024 | 127 21st Av | re-roofing: remove and replace roofing material / existing roofing material (in-kind)Details
re-roofing: remove and replace roofing material / existing roofing material (in-kind) | $28,000 |
| Oct 14, 2024 | Completed final sign-off Jan 2025 | 46 Wilmot St | re-roofing: remove and replace roofing material / existing roofing material (in-kind)Details
re-roofing: remove and replace roofing material / existing roofing material (in-kind) | $20,000 |
| Oct 10, 2024 | In progress issued Oct 2024 | 152 Bonview St | re-roofing: remove and replace roofing material / existing roofing material (in-kind)Details
re-roofing: remove and replace roofing material / existing roofing material (in-kind) | $11,000 |
| Oct 8, 2024 | In progress issued Oct 2024 | 30 16th Av | re-roofing: remove and replace roofing material / existing roofing material (in-kind)Details
re-roofing: remove and replace roofing material / existing roofing material (in-kind) | $60,000 |