62 permits since 2000: 55 completed, 4 never finaled, 3 expired or cancelled.
Of the 4 never-finaled permits, 2 are 5 to 10 years old, 2 are over 10 years old.
This is the city’s permit record, not a license check. It does not show whether the state license is active, bonded or insured. How to read these records
Permits filed each year
How long permits take
Each point is the quarter the permits were filed, for all building permits across San Francisco. A median counts only permits that have finished, so the shaded recent quarters look faster than they will end up: their slow permits have not finished yet. Hover a point for the slowest 10%. Gaps mean fewer than 5 permits. A rise in the issue line is the city’s review backlog, not the contractor.
Most recent permits
| Filed | Outcome | Address | Work described on the permit | Declared cost |
|---|---|---|---|---|
| Aug 22, 2022 | Completed final sign-off Feb 2023 | 930 Pine St | kitchen and bathroom remodeling: like for like: no relocation involved. replace cabinets, relsce countertop, replace appliances replace tile on floor in kitchen area updated. replace toilet, replace vanity. replace shower pan replace fan updated dedicated circuits per code. no walls or layout changeDetails
kitchen and bathroom remodeling: like for like: no relocation involved. replace cabinets, relsce countertop, replace appliances replace tile on floor in kitchen area updated. replace toilet, replace vanity. replace shower pan replace fan updated dedicated circuits per code. no walls or layout change | $50,000 |
| Aug 22, 2022 | Completed final sign-off Oct 2022 | 80 Richland Av | shower pan replacement like for like: noo relocation involved: repace rescessed lights in bath area. replace shower valve. no walls or layout changes.Details
shower pan replacement like for like: noo relocation involved: repace rescessed lights in bath area. replace shower valve. no walls or layout changes. | $15,000 |
| Apr 11, 2022 | Completed final sign-off Dec 2022 | 223 Upper Tr | new interior guardrail at interior stairsDetails
new interior guardrail at interior stairs | $9,000 |
| Dec 14, 2021 | Completed final sign-off Dec 2022 | 223 Upper Tr | interior: new flooors, add closet, new kichen casework and appliances, new remodel 2 bathrooms with like fixtures in simiir locations, replace doors and lighting.Details
interior: new flooors, add closet, new kichen casework and appliances, new remodel 2 bathrooms with like fixtures in simiir locations, replace doors and lighting. | $60,000 |
| Aug 25, 2021 | Completed final sign-off Nov 2021 | 650 Steiner St | unit 4: reframe door within load baearing wall. shift non-load bearing walls to enlarge closet.Details
unit 4: reframe door within load baearing wall. shift non-load bearing walls to enlarge closet. | $1,000 |
| Aug 11, 2021 | Completed final sign-off Nov 2021 | 650 Steiner St | unit 4: bathroom remodeling like for like, replace tub with shower, 2 recessed lights, replace fan, 2bfi. replace all plumbing fixtures. update mep up to code.Details
unit 4: bathroom remodeling like for like, replace tub with shower, 2 recessed lights, replace fan, 2bfi. replace all plumbing fixtures. update mep up to code. | $18,000 |
| Jul 9, 2021 | Completed final sign-off Dec 2022 | 2123 28th Av | convert 1/2 bath to full bath 2nd fl. new shower pan and shower head. toilet, vanity, recessed lights,fan.new walls with 2x4 sht 16" on centerDetails
convert 1/2 bath to full bath 2nd fl. new shower pan and shower head. toilet, vanity, recessed lights,fan.new walls with 2x4 sht 16" on center | $30,000 |
| Jun 11, 2021 | Completed final sign-off Jul 2021 | 76 Rossi Av | rear deck repair surface less then 50% in kind read deck reapir lessthan 50% in kind, not visible from streetDetails
rear deck repair surface less then 50% in kind read deck reapir lessthan 50% in kind, not visible from street | $3,000 |
| Jun 11, 2021 | Completed final sign-off Jul 2021 | 76 Rossi Av | reroofingDetails
reroofing | $12,000 |
| Apr 15, 2021 | Completed final sign-off Sep 2021 | 3795 20th St | kitchen remodel in-kind. replace apliances. upgrade m/e/p. replace plumbing fixtures in kind. no layout/wall change.Details
kitchen remodel in-kind. replace apliances. upgrade m/e/p. replace plumbing fixtures in kind. no layout/wall change. | $22,000 |
| Mar 30, 2021 | Completed final sign-off Nov 2021 | 537 Grand View Av | remodel kitchen. new cabints, backsplashs, countertop, faucet. add kitchen island with no plumbing.Details
remodel kitchen. new cabints, backsplashs, countertop, faucet. add kitchen island with no plumbing. | $10,000 |
| Mar 29, 2021 | Completed final sign-off Apr 2023 | 17 Hoff St | per ordinance 162-16 -convert (e) garage and storage to two adus and two regular dwelling units. new units within existing building footprint. new units include bedroom, bathroom, and kitchen -soft-story retrofit under permit #201406027201Details
per ordinance 162-16 -convert (e) garage and storage to two adus and two regular dwelling units. new units within existing building footprint. new units include bedroom, bathroom, and kitchen -soft-story retrofit under permit #201406027201 | $150,000 |
| Jan 20, 2021 | Completed final sign-off Mar 2021 | 1595 Treat Av | bathroom remodeling, not completed like for like, replace tile in shower, take the floor heating off and install back, shower pan, vanity and sink as is.Details
bathroom remodeling, not completed like for like, replace tile in shower, take the floor heating off and install back, shower pan, vanity and sink as is. | $9,000 |
| Nov 20, 2020 | Completed final sign-off Mar 2022 | 645 Cole St | unit 645: remodel existing kitchen & bathroom. add 1 full bathroom. add new furnace, washer & dryer.Details
unit 645: remodel existing kitchen & bathroom. add 1 full bathroom. add new furnace, washer & dryer. | $90,000 |
| Jul 14, 2020 | Completed final sign-off Jul 2021 | 3724 Divisadero St | full seismic strengthening throughout. interior reconfiguration, relocate kitchen, add bath, lightwell infill at ground floor against blank wall of adjacent building.Details
full seismic strengthening throughout. interior reconfiguration, relocate kitchen, add bath, lightwell infill at ground floor against blank wall of adjacent building. | $174,000 |
| Jul 1, 2020 | Never finaled issued Jul 2020, no final | 1050 North Point St | kitchen & bath remodel inkindDetails
kitchen & bath remodel inkind | |
| Feb 18, 2020 | Completed final sign-off Feb 2021 | 1185 South Van Ness Av | remodeling a kichne, like for like. upgrade electrial subpanel 150a. wall not moved or modified.Details
remodeling a kichne, like for like. upgrade electrial subpanel 150a. wall not moved or modified. | $10,000 |
| Jan 13, 2020 | Completed final sign-off Oct 2021 | 401 26th Av | unit #6: remodel 2 bathrooms like for like - master bathroom , main bathroom; no removal of walls.Details
unit #6: remodel 2 bathrooms like for like - master bathroom , main bathroom; no removal of walls. | $20,000 |
| Dec 5, 2019 | Completed final sign-off Jun 2020 | 401 26th Av | #6: remodel kitchen by plan. electrical add 14 recess light and install pipeline for washer.Details
#6: remodel kitchen by plan. electrical add 14 recess light and install pipeline for washer. | $65,000 |
| Sep 10, 2019 | Completed final sign-off Jan 2020 | 455 Vallejo St | kitchen remodel - like for like, change cabinets, countertop, backsplash appliances. replace existing recessed lights with led can lights.Details
kitchen remodel - like for like, change cabinets, countertop, backsplash appliances. replace existing recessed lights with led can lights. | $25,000 |
| Aug 6, 2019 | Completed final sign-off Jan 2020 | 455 Vallejo St | door 212: bathroom remodel. like for like. change recessed lights, run a dedicated 20 amp electrical line to bathroom. no change on walls.Details
door 212: bathroom remodel. like for like. change recessed lights, run a dedicated 20 amp electrical line to bathroom. no change on walls. | $15,000 |
| May 1, 2019 | Completed final sign-off Dec 2019 | 2130 Harrison St | remodel 1st fl bathroom. remodel and increase size of mezzanine bathroom.Details
remodel 1st fl bathroom. remodel and increase size of mezzanine bathroom. | $35,000 |
| Mar 26, 2019 | Completed final sign-off Aug 2019 | 1111 Bay St | complete remodel for master bathroom and hall bathroom, electrical upgrade to code. master bathroom to remain same size 58 sqft hall bathroom to remain same size 45 sqftDetails
complete remodel for master bathroom and hall bathroom, electrical upgrade to code. master bathroom to remain same size 58 sqft hall bathroom to remain same size 45 sqft | $35,300 |
| Mar 18, 2019 | Completed final sign-off Jul 2020 | 228 Cotter St | replace kitchen cabinets, replace windows (same size) alum clad front, reframe o add sliding door, update electrica to current code, reframe to add skylights, upgrade/refigure fixtures.Details
replace kitchen cabinets, replace windows (same size) alum clad front, reframe o add sliding door, update electrica to current code, reframe to add skylights, upgrade/refigure fixtures. | $40,000 |
| Jan 30, 2019 | Completed final sign-off Apr 2019 | 930 Pine St | bathroom remodel like-for-like. upgrade electrical to code. no change of existing floor plan.Details
bathroom remodel like-for-like. upgrade electrical to code. no change of existing floor plan. | $15,000 |
| Dec 10, 2018 | Completed final sign-off Dec 2018 | 223 29th St | complete master bathroom remodeling, like for like. add bathroom fan, terminate duct from side wall to roof, 3 ft min from property line. run a new dedicated electrical to bathroom from main panel. no walls moved, removed, added or installed. all (e) layouts to remain unchanged.Details
complete master bathroom remodeling, like for like. add bathroom fan, terminate duct from side wall to roof, 3 ft min from property line. run a new dedicated electrical to bathroom from main panel. no walls moved, removed, added or installed. all (e) layouts to remain unchanged. | $20,000 |
| Jun 20, 2018 | Completed final sign-off Jul 2018 | 125 Clipper St | bathroom remodelDetails
bathroom remodel | $15,000 |
| Apr 25, 2018 | Completed final sign-off Jun 2018 | 1259 45th Av | kitchen remodel at 2nd floor: demo kitchen area, install new appliances, new sink, faucet, new counter top, new tiles on floor. no new wall and no existing wall relocation. lighting shall comply with cec 150.0(k)3.Details
kitchen remodel at 2nd floor: demo kitchen area, install new appliances, new sink, faucet, new counter top, new tiles on floor. no new wall and no existing wall relocation. lighting shall comply with cec 150.0(k)3. | $20,000 |
| Feb 6, 2018 | Completed final sign-off Apr 2018 | 771 38th Av | replace cabinets replace sink, replace appliances replace countertop. install new sink and facuet. cut out non bearing wall to be 4' ht from floor for bar areaDetails
replace cabinets replace sink, replace appliances replace countertop. install new sink and facuet. cut out non bearing wall to be 4' ht from floor for bar area | $30,000 |
| Oct 11, 2017 | Completed final sign-off Dec 2017 | 1792 Green St | remodel (e) bathroom, relocate fixtures (tub, toilet, vanity. convert (e) closet into a master bathroom; add shower, add toilet, add vanity. infill hallway door wall. remove master bedroom closet and non-load bearing partition wall. new recessed lighting and fan. add 10 recess lights 5 for each brDetails
remodel (e) bathroom, relocate fixtures (tub, toilet, vanity. convert (e) closet into a master bathroom; add shower, add toilet, add vanity. infill hallway door wall. remove master bedroom closet and non-load bearing partition wall. new recessed lighting and fan. add 10 recess lights 5 for each br | $74,720 |
| Oct 2, 2017 | Completed final sign-off Dec 2017 | 601 Van Ness Av | kitchen remodeling - install new cabinet, new counter top, new appliances (fridge, oven, dw) install new back splash, apply new gfi every 2 ft. replace tile on floor. install 3 recess lights (led). all plumbing existing - in kind. n/a maherDetails
kitchen remodeling - install new cabinet, new counter top, new appliances (fridge, oven, dw) install new back splash, apply new gfi every 2 ft. replace tile on floor. install 3 recess lights (led). all plumbing existing - in kind. n/a maher | $22,500 |
| Sep 13, 2017 | Completed final sign-off Mar 2018 | 117 Scott St | 3rd floor: relocate interior bearing wall, add (n) bathroom, convert sitting room to (n) bedroom, convert sunroom to laundry, remodel kitchen.Details
3rd floor: relocate interior bearing wall, add (n) bathroom, convert sitting room to (n) bedroom, convert sunroom to laundry, remodel kitchen. | $34,000 |
| Sep 13, 2017 | Never finaled issued Sep 2017, no final | 176 Gold Mine Dr | repair framing for concrete landing, replace couple 2 by 10 joost & plywood. construciton to be built as is, pour concrete less than 50% repair kin kindDetails
repair framing for concrete landing, replace couple 2 by 10 joost & plywood. construciton to be built as is, pour concrete less than 50% repair kin kind | $9,500 |
| Sep 6, 2017 | Completed final sign-off Oct 2017 | 55 Red Rock Wy | unit 303: replace tub, fan; install new toilet, new floor/wall tile; replace plumbing, shower headDetails
unit 303: replace tub, fan; install new toilet, new floor/wall tile; replace plumbing, shower head | $11,284 |
| Sep 6, 2017 | Completed final sign-off Oct 2017 | 407 Miguel St | replace shower pan, install new floor/wall tile, new shower headDetails
replace shower pan, install new floor/wall tile, new shower head | $14,500 |
| Aug 9, 2017 | Completed final sign-off Oct 2017 | 2650 Ortega St | kitchen remodel, replace, cabinet, floor (install floor tile), countertop, backsplash, recessed lights, new sink, garbage disposal; bathroom remodel, replace tile on floor/wall, shower pan, fan, cabinet, toilet, install vanity, recessed lights.Details
kitchen remodel, replace, cabinet, floor (install floor tile), countertop, backsplash, recessed lights, new sink, garbage disposal; bathroom remodel, replace tile on floor/wall, shower pan, fan, cabinet, toilet, install vanity, recessed lights. | $65,000 |
| Jun 19, 2017 | Expired or cancelled cancelled Sep 2017 | 537 Moultrie St | replace electrical panel in same location, revision to pa#201706129088Details
replace electrical panel in same location, revision to pa#201706129088 | $2,000 |
| Jun 15, 2017 | Completed final sign-off Oct 2017 | 537 Moultrie St | replace 3 front windows with same windows wood replace 2 back windows vinyl. u factor is 0.32 or better.Details
replace 3 front windows with same windows wood replace 2 back windows vinyl. u factor is 0.32 or better. | $3,000 |
| Jun 12, 2017 | Completed final sign-off Oct 2017 | 537 Moultrie St | kitchen remodel: change cabients, sink, countertop, appliance, back splash, new gfci, 4 recess lights. bathroom remodel; change tub to shower, valve, install new tile, change toilet, vanity, add fan, install 2 new lights. change bathroom window. add 6 recess lights in living room.Details
kitchen remodel: change cabients, sink, countertop, appliance, back splash, new gfci, 4 recess lights. bathroom remodel; change tub to shower, valve, install new tile, change toilet, vanity, add fan, install 2 new lights. change bathroom window. add 6 recess lights in living room. | $40,000 |
| May 10, 2017 | Completed final sign-off Jun 2017 | 590 06th St | apt 305: change bathtub to shower pan in 2 bathrooms, install 2 shower heads with two different valves in each bathroom. install tile on walls surrouding shower.Details
apt 305: change bathtub to shower pan in 2 bathrooms, install 2 shower heads with two different valves in each bathroom. install tile on walls surrouding shower. | $15,000 |
| Apr 24, 2017 | Completed final sign-off Jun 2017 | 608 Haight St | unit #c: bathroom remodel. relocate the tub, vanity, and toilet. remove pony wall, replace fan, led lights.Details
unit #c: bathroom remodel. relocate the tub, vanity, and toilet. remove pony wall, replace fan, led lights. | $11,000 |
| Feb 24, 2017 | Completed final sign-off Mar 2017 | 185 Ney St | remodel (e) bathroom on 2nd story. no structural changes. no change on walls.Details
remodel (e) bathroom on 2nd story. no structural changes. no change on walls. | $14,500 |
| Feb 6, 2017 | Completed final sign-off Aug 2017 | 127 30th St | convert laundry room to full bathroom on 2nd flrDetails
convert laundry room to full bathroom on 2nd flr | $25,000 |
| Nov 22, 2016 | Expired or cancelled cancelled Oct 2018 | 1771 20th Av | replace windows and repair dry rot at front of house, revision to 201608185423Details
replace windows and repair dry rot at front of house, revision to 201608185423 | $5,000 |
| Aug 18, 2016 | Completed final sign-off May 2023 | 1771 20th Av | revisions to permit 201511062007; change roof type and add footings due to unforeseeen conditions.Details
revisions to permit 201511062007; change roof type and add footings due to unforeseeen conditions. | |
| Jun 16, 2016 | Completed final sign-off Nov 2016 | 498 Natoma St | revision not to build storage room in corner of 6th street and natoma st (ref. 201512155211)Details
revision not to build storage room in corner of 6th street and natoma st (ref. 201512155211) | |
| May 25, 2016 | Completed final sign-off Aug 2016 | 2023 22nd St | bathroom remodel, change tub to standing/walk-in shower, install recess light, install switch & tile bathroom.Details
bathroom remodel, change tub to standing/walk-in shower, install recess light, install switch & tile bathroom. | $9,000 |
| Feb 22, 2016 | Completed final sign-off May 2016 | 2435 Francisco St | bathrom remodel, change tub & shower, vanity, toilet. in half bath change only countertop/vanity.Details
bathrom remodel, change tub & shower, vanity, toilet. in half bath change only countertop/vanity. | $15,000 |
| Feb 11, 2016 | Completed final sign-off Mar 2019 | 715 22nd Av | second story remodel of kitchen, dining, living room, and bathroom.Details
second story remodel of kitchen, dining, living room, and bathroom. | $50,000 |
| Dec 15, 2015 | Never finaled issued May 2016, no final | 498 Natoma St | refurbish (e) commerical space, upgrade entry & bathrooms for full ada compliance. no structural work, no exterior alteration.Details
refurbish (e) commerical space, upgrade entry & bathrooms for full ada compliance. no structural work, no exterior alteration. | $50,000 |
| Nov 30, 2015 | Completed final sign-off Dec 2015 | 871 32nd Av | reroofing - remove gravel roof, install torch down roofDetails
reroofing - remove gravel roof, install torch down roof | $5,000 |
| Nov 19, 2015 | Completed final sign-off May 2016 | 920 Harrison St | unit 7: bathroom remodel-replace (e) exhaust fan in kind, change tub into shower. replace shower head, install tile in floor and walls. all new lights shall be led.Details
unit 7: bathroom remodel-replace (e) exhaust fan in kind, change tub into shower. replace shower head, install tile in floor and walls. all new lights shall be led. | $9,000 |
| Oct 23, 2015 | Never finaled issued Oct 2015, no final | 496 Natoma St | interior dry wall demo, bathrooms. remain vacancy under ab-017. space shall remain vacant per sfbc ab-017.Details
interior dry wall demo, bathrooms. remain vacancy under ab-017. space shall remain vacant per sfbc ab-017. | $3,000 |
| Oct 21, 2015 | Completed final sign-off Apr 2018 | 715 22nd Av | build new closet at entry at landing. remove window frame and trim. remove section of exterior wall. framing and header to remain. 2x4 stud wall finish exterior to match. 24" wide x 80" high door complete w/hardware. on interior move (e) window forward.Details
build new closet at entry at landing. remove window frame and trim. remove section of exterior wall. framing and header to remain. 2x4 stud wall finish exterior to match. 24" wide x 80" high door complete w/hardware. on interior move (e) window forward. | $2,000 |
| Sep 21, 2015 | Completed final sign-off Jun 2016 | 715 22nd Av | renovation and upgrades of existing ground floor living space. install wet bar.Details
renovation and upgrades of existing ground floor living space. install wet bar. | $40,000 |
| Jul 31, 2015 | Completed final sign-off Nov 2016 | 132 06th St | bakery with 8 seats, install hoods, electrical and plumbing. n/a for maher. u2300 hood and duct suppression syst. under separate application.Details
bakery with 8 seats, install hoods, electrical and plumbing. n/a for maher. u2300 hood and duct suppression syst. under separate application. | $210,000 |
| Jul 21, 2015 | Completed final sign-off Feb 2017 | 483 03rd St | rev.. to 201411050830- documentation purposes for 201411050830: resubmittal of mep sheets omitted from approved set at issuance and not included in microfilm set. mech review occurred on orig permit.Details
rev.. to 201411050830- documentation purposes for 201411050830: resubmittal of mep sheets omitted from approved set at issuance and not included in microfilm set. mech review occurred on orig permit. | |
| Apr 15, 2015 | Completed final sign-off Apr 2015 | 3355 21st St | to comply with notice of violation #201540791. repair in kind less than 50% and paint job for front house stairs. repair rotten railing pieces, with same material, same finish and same profile.Details
to comply with notice of violation #201540791. repair in kind less than 50% and paint job for front house stairs. repair rotten railing pieces, with same material, same finish and same profile. | $750 |
| Nov 5, 2014 | Expired or cancelled expired Mar 2026 | 483 03rd St | the scope of work under this application includes the necessary tenant improvements to accommodate a pizza restaurant, this work includes new non-bearing walls to create service rooms and accessible toilet, customer service area; and installation of equipment, mechanical, elec, plmbg fixtures; maherDetails
the scope of work under this application includes the necessary tenant improvements to accommodate a pizza restaurant, this work includes new non-bearing walls to create service rooms and accessible toilet, customer service area; and installation of equipment, mechanical, elec, plmbg fixtures; maher | $95,000 |
| Oct 23, 2014 | Completed final sign-off Mar 2015 | 2411 19th Av | existing store front to be modified and replace with stucco at buklhead. t.i. and change of use approved under appl. #2014.0711.0995 and 2013.1022.9943. correction of story count to 3 stories. n/aDetails
existing store front to be modified and replace with stucco at buklhead. t.i. and change of use approved under appl. #2014.0711.0995 and 2013.1022.9943. correction of story count to 3 stories. n/a | $8,000 |
| Jul 11, 2014 | Completed final sign-off Mar 2015 | 2411 19th Av | revision to app#201310229943. to change location of bathroom door and provde ceiling framing. n/a for the maher ordinance #155=13Details
revision to app#201310229943. to change location of bathroom door and provde ceiling framing. n/a for the maher ordinance #155=13 | $10,000 |
| Apr 3, 2014 | Completed final sign-off Apr 2014 | 151 Westmoorland Dr | stucco repairs- whre crack and rot, electrical add 3 lights, reroofing, remove 9e) asphalt shingles, install felt paper (eo p), sinishing and asphalt shingles (30p), deck framing repair and replacement portion of decking onlyDetails
stucco repairs- whre crack and rot, electrical add 3 lights, reroofing, remove 9e) asphalt shingles, install felt paper (eo p), sinishing and asphalt shingles (30p), deck framing repair and replacement portion of decking only | $7,500 |