Ryan And Ryan Construction Inc
- Based in
- South San Franciso
- On San Francisco permits
- Apr 2006 to May 2026
- Last 24 months
- 9 permits filed
99 permits since 2000: 57 completed, 9 in progress, 23 never finaled, 10 expired or cancelled.
Of the 23 never-finaled permits, 2 are 3 to 5 years old, 6 are 5 to 10 years old, 15 are over 10 years old.
This is the city’s permit record, not a license check. It does not show whether the state license is active, bonded or insured. How to read these records
Permits filed each year
How long permits take
Each point is the quarter the permits were filed, for all building permits across San Francisco. A median counts only permits that have finished, so the shaded recent quarters look faster than they will end up: their slow permits have not finished yet. Hover a point for the slowest 10%. Gaps mean fewer than 5 permits. A rise in the issue line is the city’s review backlog, not the contractor.
Most recent permits
| Filed | Outcome | Address | Work described on the permit | Declared cost |
|---|---|---|---|---|
| May 4, 2026 | Completed final sign-off Sep 2026 | 4007 22nd St | level 3: bathroom and kitchen remodel, in kind. level 2: bedroom and ceiling - insulation and partial dry wall on ceiling. living room replace plaster wall.Details
level 3: bathroom and kitchen remodel, in kind. level 2: bedroom and ceiling - insulation and partial dry wall on ceiling. living room replace plaster wall. | $35,000 |
| May 4, 2026 | In progress issued May 2026 | 332 Wilde Av | replace ceiling with new drywall to rewire electrical in lower level, replacing electrical panel and gas line in garage, rewire upper and lower area. upper level, remove and replace up to 2' of drywall to rewire. to comply nov# 202653957; replace the fire damage studs and joists at electrical panel.Details
replace ceiling with new drywall to rewire electrical in lower level, replacing electrical panel and gas line in garage, rewire upper and lower area. upper level, remove and replace up to 2' of drywall to rewire. to comply nov# 202653957; replace the fire damage studs and joists at electrical panel. | $58,000 |
| Dec 10, 2025 | Completed final sign-off Apr 2026 | 2311 15th Av | to obtain final inspection for work approved under pa 202404301060. all work is complete.Details
to obtain final inspection for work approved under pa 202404301060. all work is complete. | |
| Nov 19, 2025 | Completed final sign-off Jan 2026 | 83 Gladstone Dr | to comply with nov 2025545438. repair framing and stucco, 32 sq ft at front and left side of the building.Details
to comply with nov 2025545438. repair framing and stucco, 32 sq ft at front and left side of the building. | $6,500 |
| Feb 13, 2025 | In progress issued Feb 2025 | 573 Naples St | recommencement and completion of work under 202108116242, 202108116243Details
recommencement and completion of work under 202108116242, 202108116243 | $4,500 |
| Feb 12, 2025 | Completed final sign-off Feb 2025 | 475 Vienna St | revision to pa 201809180581 to plans from t1-11 to stucco (recommencement of 201809180581 under pa 202405011132)Details
revision to pa 201809180581 to plans from t1-11 to stucco (recommencement of 201809180581 under pa 202405011132) | |
| Feb 11, 2025 | In progress issued Apr 2025 | 151 Alice B Toklas Pl | demolition and remodel of kitchen an two bathroomsDetails
demolition and remodel of kitchen an two bathrooms | $150,000 |
| Dec 9, 2024 | Completed final sign-off Mar 2025 | 699 Pennsylvania Av | bathroom repair due to water damage: shower tile, water proof, drywall patch, re-install vanity toilet, reconnect vanity sink, new shower door, everything will be like to like.unit 9Details
bathroom repair due to water damage: shower tile, water proof, drywall patch, re-install vanity toilet, reconnect vanity sink, new shower door, everything will be like to like.unit 9 | $9,000 |
| Dec 6, 2024 | In progress issued Dec 2024 | 699 Pennsylvania Av | bathroom repair due to water damage: shower tile, water proof, drywall patch, re-install vanity toilet, reconnect vanity sink, new shower door, everything will be like to like.Details
bathroom repair due to water damage: shower tile, water proof, drywall patch, re-install vanity toilet, reconnect vanity sink, new shower door, everything will be like to like. | $9,000 |
| Oct 1, 2024 | Completed final sign-off Oct 2024 | 220 Corona St | to obtain final inspection for work approved under pa#2020-0220-4960 al work is completeDetails
to obtain final inspection for work approved under pa#2020-0220-4960 al work is complete | |
| Jul 8, 2024 | In progress issued Jul 2024 | 2115 San Jose Av | rev 202407025678- to include replacing drywall, and insulation for bedroom 1&2, foyer, breakfast nook and hallways.Details
rev 202407025678- to include replacing drywall, and insulation for bedroom 1&2, foyer, breakfast nook and hallways. | |
| Jul 2, 2024 | In progress issued Jul 2024 | 2115 San Jose Av | living, dining, kitchen and bathroom install new insualtion and drywall. kitchen cabinets, baseboards. same for same. no mep work or wall or layout changes.Details
living, dining, kitchen and bathroom install new insualtion and drywall. kitchen cabinets, baseboards. same for same. no mep work or wall or layout changes. | $100,000 |
| May 1, 2024 | Completed final sign-off Feb 2025 | 475 Vienna St | recommencement and completion of work approved under pa# 202101132605 and 201809180581.Details
recommencement and completion of work approved under pa# 202101132605 and 201809180581. | $4,500 |
| Apr 30, 2024 | Completed final sign-off Apr 2026 | 2311 15th Av | rebuild front stairwell in-kind due to vechicle crashing inti it. rebuild & bring up to codeDetails
rebuild front stairwell in-kind due to vechicle crashing inti it. rebuild & bring up to code | $15,000 |
| Apr 18, 2024 | In progress issued Apr 2024 | 2838 24th St | to comply with nov# 202419671; repair corner of bldg due to car collision. damaged corner structurally sound, a new cripple wall underneath window opening will be rebuilt with double 2x6 top plates,Details
to comply with nov# 202419671; repair corner of bldg due to car collision. damaged corner structurally sound, a new cripple wall underneath window opening will be rebuilt with double 2x6 top plates, | $12,000 |
| Mar 1, 2024 | In progress issued Mar 2024 | 95 Red Rock Wy | unit: 210m; bathroom remodel, same for same. hardie board. tile up to date plumbing code if needed.Details
unit: 210m; bathroom remodel, same for same. hardie board. tile up to date plumbing code if needed. | $5,000 |
| Oct 2, 2023 | Never finaled issued Oct 2023, no final | 1399 Plymouth Av | demo permit. demo/remove plaster due to water damage. board up all exterior openings, broken windows if window works, garage door fully closed and securedDetails
demo permit. demo/remove plaster due to water damage. board up all exterior openings, broken windows if window works, garage door fully closed and secured | $1,500 |
| Sep 13, 2023 | Completed final sign-off Apr 2025 | 2 Maynard St | unit #4: fire/smoke damage repair. no structural repair. smoke damage work performed will be new insulation, drywall, electrcial, plumbing and flooring if needed. bring code upt to date, replacement if needed & to comply with violation #202306911. same for same nothing will be added or changed.Details
unit #4: fire/smoke damage repair. no structural repair. smoke damage work performed will be new insulation, drywall, electrcial, plumbing and flooring if needed. bring code upt to date, replacement if needed & to comply with violation #202306911. same for same nothing will be added or changed. | $85,000 |
| Apr 14, 2023 | Expired or cancelled cancelled Apr 2024 | 820 Mcallister St | unit# 835: smoke damage repair, insulation, drywall repair. bedroom and master ceiling. replace carpet.Details
unit# 835: smoke damage repair, insulation, drywall repair. bedroom and master ceiling. replace carpet. | $6,400 |
| Jun 24, 2022 | In progress issued Oct 2025 | 575 Naples St | to comply w/ nov# 202173574. legalize unit. repairs due to fire & water damage. removal of unpermitted rear portion on thirdDetails
to comply w/ nov# 202173574. legalize unit. repairs due to fire & water damage. removal of unpermitted rear portion on third | $45,000 |
| Mar 29, 2022 | Never finaled issued Mar 2022, no final | 573 Naples St | re-roofingDetails
re-roofing | $6,000 |
| Aug 11, 2021 | Never finaled issued Aug 2021, no final | 575 Naples St | fire damage, electrical, drywall, framing, plumbing - ktichen and bath repairs. remove and replace in kind.Details
fire damage, electrical, drywall, framing, plumbing - ktichen and bath repairs. remove and replace in kind. | $175,000 |
| Aug 11, 2021 | Never finaled issued Aug 2021, no final | 573 Naples St | smoke damage, electrical, drywall, plumbing - ktichen and bath repairs. remove and replace in kind.Details
smoke damage, electrical, drywall, plumbing - ktichen and bath repairs. remove and replace in kind. | $175,000 |
| Jul 21, 2021 | Never finaled issued Jul 2021, no final | 474 Orizaba Av | bathroom: new drywalls on walls only, new shower drain, shower faucet, toilet, sink faucet, new shower membrane, tile walls, enclosure and floor. kitchen new lower cabinet, sink and sink faucet.Details
bathroom: new drywalls on walls only, new shower drain, shower faucet, toilet, sink faucet, new shower membrane, tile walls, enclosure and floor. kitchen new lower cabinet, sink and sink faucet. | $8,500 |
| Dec 24, 2020 | Completed final sign-off Nov 2025 | 64 Golden Gate Av | fire rebuild: new roof, roof trusses, electrical, plumbing, drywall. to comply with nov 202025050.Details
fire rebuild: new roof, roof trusses, electrical, plumbing, drywall. to comply with nov 202025050. | $675,000 |
| Aug 5, 2020 | Completed final sign-off Jan 2021 | 295 Brookdale Av | comply with nov# 201981541. replace 4 vertical 2x4x8 at right side of garage door. replace 32 sq ft siding, detach & reset exterior main panel detached, reset solar panel transformer.car damage to buildingDetails
comply with nov# 201981541. replace 4 vertical 2x4x8 at right side of garage door. replace 32 sq ft siding, detach & reset exterior main panel detached, reset solar panel transformer.car damage to building | $7,500 |
| Feb 24, 2020 | Completed final sign-off Nov 2020 | 1016 Lake St | water damange reair: replace drywall on ceiling of bathroom, new shower / tub diverter, new tub, tile surround. reinstall (e) vanity new toilet.Details
water damange reair: replace drywall on ceiling of bathroom, new shower / tub diverter, new tub, tile surround. reinstall (e) vanity new toilet. | $6,800 |
| Jan 7, 2019 | Completed final sign-off Apr 2019 | 1419 31st Av | comply with nov number 20183301. repair stucco where car hit front of property.Details
comply with nov number 20183301. repair stucco where car hit front of property. | $3,200 |
| Jun 13, 2018 | Completed final sign-off Nov 2018 | 130 Landers St | remove and replace kitchen cabinets. no electrical. plumbing: p-trap, install sink, and hook up dishwasher. no change of (e) floor planDetails
remove and replace kitchen cabinets. no electrical. plumbing: p-trap, install sink, and hook up dishwasher. no change of (e) floor plan | $15,000 |
| Mar 21, 2018 | Never finaled issued Mar 2018, no final | 183 Inverness Dr | replacement of four front windows (two on lower level, two on upper level) - aluminum sliders to aluminum clad wood windows - casement or fixed. other work includes interior drywall and finishes due to fire damage. no other work.Details
replacement of four front windows (two on lower level, two on upper level) - aluminum sliders to aluminum clad wood windows - casement or fixed. other work includes interior drywall and finishes due to fire damage. no other work. | $60,000 |
| Sep 28, 2017 | Completed final sign-off Dec 2017 | 649 Darien Wy | bathroom remodel, new insulation wall ceiling, new tub shower/tub faucet, 20 amp circuit, exhaust with light, 3 led recessed light, toilet vanity with faucet shower tile floor, tile 1/2 dry wall & add to comply with 200232363Details
bathroom remodel, new insulation wall ceiling, new tub shower/tub faucet, 20 amp circuit, exhaust with light, 3 led recessed light, toilet vanity with faucet shower tile floor, tile 1/2 dry wall & add to comply with 200232363 | $14,500 |
| May 3, 2017 | Never finaled issued May 2017, no final | 1 Lobos St | remodel:bath: new insul r13-r30. new drywall, new shower faucet vanity, sink, faucet, toilet, 2 exhaust fan. 2.4 led light outlet switches, new shower tile enclosed. kitchen:new 120amp circuit, new cabinet, sink faucet, garbage disp, new appliances. new elec circuits for appliances. drywall patches.Details
remodel:bath: new insul r13-r30. new drywall, new shower faucet vanity, sink, faucet, toilet, 2 exhaust fan. 2.4 led light outlet switches, new shower tile enclosed. kitchen:new 120amp circuit, new cabinet, sink faucet, garbage disp, new appliances. new elec circuits for appliances. drywall patches. | $34,000 |
| Apr 4, 2017 | Completed final sign-off Jun 2017 | 2044 14th Av | 2nd level shower new waterproof and tile, new vanity new counter, faucet. 1st level 1/2 bathroom new insulation drywall. re-install (e) toilet and vanityDetails
2nd level shower new waterproof and tile, new vanity new counter, faucet. 1st level 1/2 bathroom new insulation drywall. re-install (e) toilet and vanity | $13,000 |
| Dec 19, 2016 | Completed final sign-off May 2017 | 71 Rossmoor Dr | bathroom remodel: new tile new electric, new plumbing,new drywall,new retrofit window,no change on walls.Details
bathroom remodel: new tile new electric, new plumbing,new drywall,new retrofit window,no change on walls. | $12,500 |
| Nov 10, 2016 | Completed final sign-off Jun 2017 | 100 Melrose Av | one bathroom remodel, like for like. replace toilet, sink, faucet, shower valve, tile, & drywall(on walls only), 3 plugs & 5 switches, 4 cam lights, 1 20amp circuit.Details
one bathroom remodel, like for like. replace toilet, sink, faucet, shower valve, tile, & drywall(on walls only), 3 plugs & 5 switches, 4 cam lights, 1 20amp circuit. | $15,000 |
| Nov 10, 2016 | Never finaled issued Nov 2016, no final | 2327 38th Av | to obtain final inspection for work approved under pa#2014-1229-4616. all work is complete.Details
to obtain final inspection for work approved under pa#2014-1229-4616. all work is complete. | |
| Jun 8, 2016 | Completed final sign-off Sep 2016 | 2327 38th Av | remodel bathroom: upgrade electrical, plumbing and exhaust. no structural changes.Details
remodel bathroom: upgrade electrical, plumbing and exhaust. no structural changes. | $8,700 |
| Feb 17, 2016 | Expired or cancelled expired Nov 2017 | 190 Dartmouth St | to obtain final inspection for work appoved under app#200310177816 and 200410207366. all work is complete.Details
to obtain final inspection for work appoved under app#200310177816 and 200410207366. all work is complete. | |
| Feb 17, 2016 | Expired or cancelled expired Nov 2017 | 190 Dartmouth St | to obtain final inspection for work appoved under app#9714945 and 200202199440. all work is complete.Details
to obtain final inspection for work appoved under app#9714945 and 200202199440. all work is complete. | |
| Apr 28, 2015 | Completed final sign-off Nov 2015 | 101 Lombard St | unit 11: fix water damange; no walls moved, retile shower, new diverter, retile bathroom floor, drywall & installation on back side of bathroom from water damage, hot mop / water proofing.Details
unit 11: fix water damange; no walls moved, retile shower, new diverter, retile bathroom floor, drywall & installation on back side of bathroom from water damage, hot mop / water proofing. | $15,000 |
| Feb 26, 2015 | Expired or cancelled expired Aug 2016 | 3191 Pacific Av | revision to pa 2015-0209-7760. add one existing window to be replaced due to dry-rot repair at the facade.Details
revision to pa 2015-0209-7760. add one existing window to be replaced due to dry-rot repair at the facade. | $500 |
| Feb 9, 2015 | Expired or cancelled expired Aug 2016 | 3191 Pacific Av | replace 9e) n.w. corner dyyrot danaged wakk styds, "work in common" area. n/a maher ordinanceDetails
replace 9e) n.w. corner dyyrot danaged wakk styds, "work in common" area. n/a maher ordinance | $2,500 |
| Dec 29, 2014 | Completed final sign-off Apr 2015 | 116 Downey St | unit 2 - remodel existing bathroom - new tile on shower, new vanity, sink, new toilet, upgrade; electrical & plumbing to newest codeDetails
unit 2 - remodel existing bathroom - new tile on shower, new vanity, sink, new toilet, upgrade; electrical & plumbing to newest code | $12,000 |
| Dec 29, 2014 | Never finaled issued Dec 2014, no final | 2327 38th Av | remodel kitchen - new appliances, new tile, new cabinets, new sink, new installation, new counter tops, upgrade elelctrical & plumbing in kitchen to codeDetails
remodel kitchen - new appliances, new tile, new cabinets, new sink, new installation, new counter tops, upgrade elelctrical & plumbing in kitchen to code | $20,000 |
| Oct 27, 2014 | Never finaled issued Oct 2014, no final | 1654 Quesada Av | replace 2' high drywall around each room where removed for new electrical.Details
replace 2' high drywall around each room where removed for new electrical. | $4,000 |
| Oct 10, 2014 | Expired or cancelled expired Aug 2016 | 3193 Pacific Av | need to add a drain to roof top deck, it was supposed to be on the 1st permit pulled but was not added, revision to 201409226963. maher n/aDetails
need to add a drain to roof top deck, it was supposed to be on the 1st permit pulled but was not added, revision to 201409226963. maher n/a | |
| Oct 10, 2014 | Never finaled issued Oct 2014, no final | 556 Scott St | replace tile bathroom, toilet, vanity, sink faucet; add one gfic outlet, bathroom on 1st flrDetails
replace tile bathroom, toilet, vanity, sink faucet; add one gfic outlet, bathroom on 1st flr | $16,000 |
| Sep 22, 2014 | Completed final sign-off Dec 2014 | 780 14th St | bathroom remodel, remove tile, toilet, bath/shower, vanity sink, install drywall - tile - toilet, bath/shower, vanity.sink. no change on walls.Details
bathroom remodel, remove tile, toilet, bath/shower, vanity sink, install drywall - tile - toilet, bath/shower, vanity.sink. no change on walls. | $15,738 |
| Sep 22, 2014 | Expired or cancelled expired Aug 2016 | 3193 Pacific Av | ext deck, remove existing tile & water proof, re-install water proofing hot mop, 10" up two exterior walls, remove stucco - 10" up two walls, re-install stucco.Details
ext deck, remove existing tile & water proof, re-install water proofing hot mop, 10" up two exterior walls, remove stucco - 10" up two walls, re-install stucco. | $15,000 |
| Sep 22, 2014 | Never finaled issued Sep 2014, no final | 3045 Jackson St | #303: remove & reinstall toilet, tub/shower, pocket door, vanity/sink, drywall, tile flooring, no changes on walls.Details
#303: remove & reinstall toilet, tub/shower, pocket door, vanity/sink, drywall, tile flooring, no changes on walls. | $40,000 |
| Aug 5, 2014 | Completed final sign-off Dec 2014 | 1305 Laguna St | kitchen - remove cabinets, sheetrock, add plugs and switches - replace same. bathroom - remove toilet, vanity, tub/shower, tile floor - replace same; electrical - new sub panel (same layout on both)Details
kitchen - remove cabinets, sheetrock, add plugs and switches - replace same. bathroom - remove toilet, vanity, tub/shower, tile floor - replace same; electrical - new sub panel (same layout on both) | $14,000 |
| Oct 31, 2013 | Completed final sign-off Jul 2014 | 1281 Filbert St | remodel kitchen, add toilet at extg bath, add sink at extg toilet room, relocate furnace to laundry room, reconfigure walls at entry closet, add 2 tube skylights. all work is at 4th floor. maher ordinance # 155-13 does not applyDetails
remodel kitchen, add toilet at extg bath, add sink at extg toilet room, relocate furnace to laundry room, reconfigure walls at entry closet, add 2 tube skylights. all work is at 4th floor. maher ordinance # 155-13 does not apply | $43,000 |
| Sep 13, 2013 | Completed final sign-off Jul 2014 | 2931 Fillmore St | unit a- remodel bathroom "as is" (no removal or moving walls); to comply with cec 150(k) 6Details
unit a- remodel bathroom "as is" (no removal or moving walls); to comply with cec 150(k) 6 | $12,500 |
| Sep 12, 2013 | Never finaled issued Sep 2013, no final | 500 Larkin St | rev. to pa# 201206072061 use wood to construct elevator machine room access stairs and platform.Details
rev. to pa# 201206072061 use wood to construct elevator machine room access stairs and platform. | |
| Jun 17, 2013 | Completed final sign-off Aug 2013 | 216 Ewing Tr | legalize bathroom in garage, existing waste lines, new dry wall electrical, sink toiletDetails
legalize bathroom in garage, existing waste lines, new dry wall electrical, sink toilet | $7,500 |
| May 29, 2013 | Never finaled issued Jun 2013, no final | 500 Larkin St | remove and replace 3 levels of west elevator wall. revision to 201206072061. remove existing terra cotta wall. replace with 2-hr. shaft liner wall.Details
remove and replace 3 levels of west elevator wall. revision to 201206072061. remove existing terra cotta wall. replace with 2-hr. shaft liner wall. | $10,000 |
| May 24, 2013 | Completed final sign-off Aug 2013 | 3230 Washington St | additional work for permit 2013/01/17/8193. drywall & painting on the 1st floor. "b" boad replace @ entry way.Details
additional work for permit 2013/01/17/8193. drywall & painting on the 1st floor. "b" boad replace @ entry way. | $14,000 |
| Mar 6, 2013 | Never finaled issued Mar 2013, no final | 54 Mcallister St | work in units 403, 404, 405: repair/replace drywall/dry rot in all units. remodel kitchens and bathrooms all units. rewire all units. no new walls. no new windows. in-kind repair.Details
work in units 403, 404, 405: repair/replace drywall/dry rot in all units. remodel kitchens and bathrooms all units. rewire all units. no new walls. no new windows. in-kind repair. | $90,000 |
| Feb 26, 2013 | Completed final sign-off Oct 2013 | 2015 Pine St | remodel one existing kitchen located on first floor. all fixtures to remain in the same location. no new wall and no wall relocation. lighting installed in kitchen shall comply with cec 150(k)8. provide smoke detectors and carbon monoxide alarms in hallway.Details
remodel one existing kitchen located on first floor. all fixtures to remain in the same location. no new wall and no wall relocation. lighting installed in kitchen shall comply with cec 150(k)8. provide smoke detectors and carbon monoxide alarms in hallway. | $26,000 |
| Feb 7, 2013 | Completed final sign-off May 2013 | 201 Granville Wy | remodel bath room, replace shower pan, toilet, lavatory. fixtures to reamin same. lighting shall be high efficiency or controlled by manuel on sensors. no change in walls and opening layout, bathroom is on upper level.Details
remodel bath room, replace shower pan, toilet, lavatory. fixtures to reamin same. lighting shall be high efficiency or controlled by manuel on sensors. no change in walls and opening layout, bathroom is on upper level. | $9,400 |
| Jan 17, 2013 | Completed final sign-off Aug 2013 | 3230 Washington St | contractor to replace existing drywall and install new 5/8 quiet rock in living room, hallway and 2 bedroom.Details
contractor to replace existing drywall and install new 5/8 quiet rock in living room, hallway and 2 bedroom. | $14,000 |
| Jan 10, 2013 | Completed final sign-off Aug 2013 | 216 Ewing Tr | remove & replace cabinets & drywall in kitchen. remodel upstairs bathroom only.Details
remove & replace cabinets & drywall in kitchen. remodel upstairs bathroom only. | $50,000 |
| Nov 21, 2012 | Expired or cancelled expired Jul 2014 | 54 Macondray Ln | replace plaster, shower pan bath fan lightDetails
replace plaster, shower pan bath fan light | $5,000 |
| Nov 13, 2012 | Never finaled issued Nov 2012, no final | 500 Larkin St | revision to 201206072061. remove deteriorated concrete wall at top of elevator shaft. (approx 21sf)and replace with 2 steel columns and metal stud walls. comply with nov 200929941,201043578Details
revision to 201206072061. remove deteriorated concrete wall at top of elevator shaft. (approx 21sf)and replace with 2 steel columns and metal stud walls. comply with nov 200929941,201043578 | $10,000 |
| Sep 24, 2012 | Completed final sign-off May 2013 | 2600 Ortega St | rev. pa#201208076744 to remove dry rotted framing and re-install in like kind on the two street sides of building.Details
rev. pa#201208076744 to remove dry rotted framing and re-install in like kind on the two street sides of building. | $30,000 |
| Aug 7, 2012 | Completed final sign-off May 2013 | 2600 Ortega St | remove & replace windows & stucco. windows visible from the street, total of 20 windowsDetails
remove & replace windows & stucco. windows visible from the street, total of 20 windows | $21,000 |
| Jun 7, 2012 | Never finaled issued Sep 2012, no final | 500 Larkin St | comply with nov# 200929941-replace (e) elevator cab, elevator machine room penthouse & elevator doors st all levels. reinforce supports & replace 2 hr. rated shaft. patch spalling concrete in shaft & basement. fire alarm and sprinklers separate permit.Details
comply with nov# 200929941-replace (e) elevator cab, elevator machine room penthouse & elevator doors st all levels. reinforce supports & replace 2 hr. rated shaft. patch spalling concrete in shaft & basement. fire alarm and sprinklers separate permit. | $250,000 |
| Nov 16, 2011 | Completed final sign-off Jan 2012 | 1522 Fulton St | replace entry porch tile and replace dry rot at garage door header and wall replace trim and handrail. replace with a 4x8 header that matches extg header size.Details
replace entry porch tile and replace dry rot at garage door header and wall replace trim and handrail. replace with a 4x8 header that matches extg header size. | $6,400 |
| Oct 5, 2011 | Completed final sign-off Nov 2011 | 1475 08th Av | remove and replace garage ceiling support beam and concrete foundationsDetails
remove and replace garage ceiling support beam and concrete foundations | $9,000 |
| Aug 9, 2011 | Completed final sign-off Dec 2011 | 2674 17th Av | bathroom remodel hallway. insulation drywall toilet, sink shower valve, hot mop.Details
bathroom remodel hallway. insulation drywall toilet, sink shower valve, hot mop. | $21,000 |
| Apr 21, 2011 | Completed final sign-off May 2011 | 1751 Geneva Av | updating electrical, drywall in (e) storage room in garage (110 sq.ft.) 5/8" gyp. bd. type x. replace drywall upstairs, 1' high for a total of 110 l.f. due to water damage.Details
updating electrical, drywall in (e) storage room in garage (110 sq.ft.) 5/8" gyp. bd. type x. replace drywall upstairs, 1' high for a total of 110 l.f. due to water damage. | $8,337 |
| Apr 21, 2011 | Completed final sign-off Feb 2012 | 300 Nevada St | new plumbing/new electrical, windows, insulation, drywood and carpet repairs/toilet, sink, cabinets. to comply with nov #201111902.Details
new plumbing/new electrical, windows, insulation, drywood and carpet repairs/toilet, sink, cabinets. to comply with nov #201111902. | $41,526 |
| Apr 6, 2011 | Never finaled issued Apr 2011, no final | 1665 19th Av | replace insulation r13-304 sq.ft. replace drywall 384 sq.ft. no structural work, with 5/8 gyp. bd. in kind.Details
replace insulation r13-304 sq.ft. replace drywall 384 sq.ft. no structural work, with 5/8 gyp. bd. in kind. | $3,400 |
| Mar 21, 2011 | Expired or cancelled cancelled Aug 2011 | 1942 Alemany Bl | kitchen: insulation, drywall re-install cabinets, sink, faucets, flooring. no dish washer. bathroom: insulation, drywall, shower unit. bedroom: insulation, drywall, floor coverigs. no framing, no plumbing or elecrical, non structure work under this permit.Details
kitchen: insulation, drywall re-install cabinets, sink, faucets, flooring. no dish washer. bathroom: insulation, drywall, shower unit. bedroom: insulation, drywall, floor coverigs. no framing, no plumbing or elecrical, non structure work under this permit. | $12,500 |
| Mar 21, 2011 | Completed final sign-off Apr 2011 | 513 Bush St | repair wall framing on light well, 1 hour exterior wall @2nd story r-13 insulation, replace 2 windows in light well, same size 24"x60" replace in kind @ 2nd tory u factor =0.47 max., installl flooring covering @ bottom of lightwell, class "a" or "b" roofing, 519 bush replace 48 sq.ft. 1 t bar ceilinDetails
repair wall framing on light well, 1 hour exterior wall @2nd story r-13 insulation, replace 2 windows in light well, same size 24"x60" replace in kind @ 2nd tory u factor =0.47 max., installl flooring covering @ bottom of lightwell, class "a" or "b" roofing, 519 bush replace 48 sq.ft. 1 t bar ceilin | $12,000 |
| Nov 17, 2010 | Completed final sign-off Mar 2011 | 1755 Filbert St | patch repair where fire dept cut a hole in the roof type of roof 2 ply modified build up. size 64 sq ft of plywood & roof material repair size 460 sq ft.Details
patch repair where fire dept cut a hole in the roof type of roof 2 ply modified build up. size 64 sq ft of plywood & roof material repair size 460 sq ft. | $8,000 |
| Oct 19, 2010 | Completed final sign-off Nov 2010 | 1200 Treat Av | replace 48sf of siding reference left side of window w/ new 2x4's @ 16" on center.Details
replace 48sf of siding reference left side of window w/ new 2x4's @ 16" on center. | $4,600 |
| Oct 18, 2010 | Completed final sign-off Mar 2011 | 1755 Filbert St | cosmetic - paint, drywall, insulation, carpet, tile. all new drywall will be 5/8 x rated. master bedroom ceiling, wall. master bathroom ceiling & wall. additional plans and permit may be required at discretion of building inspector.Details
cosmetic - paint, drywall, insulation, carpet, tile. all new drywall will be 5/8 x rated. master bedroom ceiling, wall. master bathroom ceiling & wall. additional plans and permit may be required at discretion of building inspector. | $4,100 |
| Oct 18, 2010 | Never finaled issued Oct 2010, no final | 1755 Filbert St | cosmetic - paint, drywall, insulation, carpet. all new drywall will be 5/8 x rated. bedroom ceiling, kitchen ceiling. additional plans and permit may be required at discretion of building inspector.Details
cosmetic - paint, drywall, insulation, carpet. all new drywall will be 5/8 x rated. bedroom ceiling, kitchen ceiling. additional plans and permit may be required at discretion of building inspector. | $8,875 |
| Oct 18, 2010 | Completed final sign-off Mar 2011 | 1755 Filbert St | cosmetic - paint, drywall, insulation, carpet, electrical. all new drywall will be 5/8 x rated. master bedroom ceiling and wall, 2nd bedroom ceiling & wall. 2 ceiling can lights rewire. additional plans and permit may be required at discretion of building inspector.Details
cosmetic - paint, drywall, insulation, carpet, electrical. all new drywall will be 5/8 x rated. master bedroom ceiling and wall, 2nd bedroom ceiling & wall. 2 ceiling can lights rewire. additional plans and permit may be required at discretion of building inspector. | $12,200 |
| Oct 18, 2010 | Completed final sign-off Mar 2011 | 1755 Filbert St | cosmetic - drywall/insulation/carpet/hardwood/tile. paint, all new drywall to be 5/8 x rated: master bedroom ceiling and walls, kitchen ceiling. additional plans and permit may be required at discretion of building inspector.Details
cosmetic - drywall/insulation/carpet/hardwood/tile. paint, all new drywall to be 5/8 x rated: master bedroom ceiling and walls, kitchen ceiling. additional plans and permit may be required at discretion of building inspector. | $24,000 |
| Oct 18, 2010 | Completed final sign-off Jun 2011 | 1755 Filbert St | cosmetic - drywall/insulation/carpet/hardwood/tile. paint, all new drywall to be rated 5/8 in the entry, hallway, closet, bedroom ceiling. additional plans and permit may be required at discretion of building inspector.Details
cosmetic - drywall/insulation/carpet/hardwood/tile. paint, all new drywall to be rated 5/8 in the entry, hallway, closet, bedroom ceiling. additional plans and permit may be required at discretion of building inspector. | $9,500 |
| Oct 18, 2010 | Never finaled issued Oct 2010, no final | 1755 Filbert St | cosmetic - paint, drywall, insulation. all new drywall to be 5/8 x rated. bedroom #1 ceiling, kitchen ceiling. additional plans and permit may be required at discretion of building inspector.Details
cosmetic - paint, drywall, insulation. all new drywall to be 5/8 x rated. bedroom #1 ceiling, kitchen ceiling. additional plans and permit may be required at discretion of building inspector. | $150 |
| Oct 8, 2010 | Never finaled issued Oct 2010, no final | 1755 Filbert St | to comply with correction notice 9/20/10 fire damage repair in like kind. replace damaged gypsum board in bedroooms #2 & #3. install insuation, repair electrical under separate permit.Details
to comply with correction notice 9/20/10 fire damage repair in like kind. replace damaged gypsum board in bedroooms #2 & #3. install insuation, repair electrical under separate permit. | $15,000 |
| Oct 8, 2010 | Completed final sign-off Mar 2011 | 1755 Filbert St | unit #25 -to comply with correction notice 9/20/10 fire damage repair in like kind repair 8 ft x 8 ft of roof framing, replace roof deck rail/fence.Details
unit #25 -to comply with correction notice 9/20/10 fire damage repair in like kind repair 8 ft x 8 ft of roof framing, replace roof deck rail/fence. | $10,000 |
| Aug 25, 2010 | Completed final sign-off Jun 2011 | 208 States St | replace e exterior stair in kind. same size and same envelopeDetails
replace e exterior stair in kind. same size and same envelope | $10,000 |
| Jul 13, 2010 | Never finaled issued Jul 2010, no final | 4096 17th St | bathroom: new shower tile, new shower diverton & finish trimDetails
bathroom: new shower tile, new shower diverton & finish trim | $3,500 |
| Feb 2, 2010 | Completed final sign-off Feb 2010 | 173 Girard St | reroofing.Details
reroofing. | $6,000 |
| Nov 17, 2009 | Completed final sign-off Oct 2010 | 59 Grand View Av | deck dry rot repair - less than 50%. replace sheetrock @ basement level walls.Details
deck dry rot repair - less than 50%. replace sheetrock @ basement level walls. | $15,000 |
| Oct 26, 2009 | Expired or cancelled expired May 2012 | 190 Curtis St | remove stucco on the east side wall, install new 151lbs tar paper, chicken wire & stucco finishDetails
remove stucco on the east side wall, install new 151lbs tar paper, chicken wire & stucco finish | $3,500 |
| Nov 3, 2008 | Completed final sign-off May 2009 | 439 Brussels St | renovate bathroom, new circuits, lights and recepatacle at lower level.new dedicated circuit for laundry. add new recess lighting, reframe wall on the interior . add new p/t mud sills, remove a seperation wall between 2 rooms, install exterior doorDetails
renovate bathroom, new circuits, lights and recepatacle at lower level.new dedicated circuit for laundry. add new recess lighting, reframe wall on the interior . add new p/t mud sills, remove a seperation wall between 2 rooms, install exterior door | $30,000 |
| Oct 1, 2008 | Never finaled issued Oct 2008, no final | 439 Brussels St | reroofing and replace 6" raise existing skylight in roof.Details
reroofing and replace 6" raise existing skylight in roof. | $4,000 |
| Aug 19, 2008 | Completed final sign-off Oct 2009 | 1256 08th Av | unit #3-kitchen remodel to include replace 2 windows, 1 ext. door, (n) gyp bd & insulation, (n) cabinets, expand into adjacent closet.Details
unit #3-kitchen remodel to include replace 2 windows, 1 ext. door, (n) gyp bd & insulation, (n) cabinets, expand into adjacent closet. | $30,000 |
| Sep 27, 2007 | Completed final sign-off Apr 2008 | 1256 08th Av | remodel unit#1/ kitchen remodel,replace existing window and door at rear,new refrigerator alcove, new appliances and cabinets, electrical and plumbing.Details
remodel unit#1/ kitchen remodel,replace existing window and door at rear,new refrigerator alcove, new appliances and cabinets, electrical and plumbing. | $30,000 |
| Aug 1, 2007 | Completed final sign-off Dec 2007 | 215 Red Rock Wy | demo kitchen cabinets, install new cabinets, new wood flooring, a new closet door, new counter tops, existing lighting to remain, new hood to conenct to existing ductwork.Details
demo kitchen cabinets, install new cabinets, new wood flooring, a new closet door, new counter tops, existing lighting to remain, new hood to conenct to existing ductwork. | $18,500 |
| Jul 23, 2007 | Completed final sign-off Aug 2007 | 2237 Fillmore St | store front change. install new doorDetails
store front change. install new door | $8,000 |
| Jul 9, 2007 | Completed final sign-off Aug 2007 | 2237 Fillmore St | revision to permit #200705080673, relocate door in wall to rear roomDetails
revision to permit #200705080673, relocate door in wall to rear room | |
| Jun 6, 2007 | Completed final sign-off Dec 2007 | 1746 Bay St | kitchen remodel and laundry room remodel. opening wall in breakfast area, add washer water and waste line. new sheetrock in the kitchen/laundry room,insulation in the ceiling of the laundry and kitchen ceiling and exterior wall. comply with title 24Details
kitchen remodel and laundry room remodel. opening wall in breakfast area, add washer water and waste line. new sheetrock in the kitchen/laundry room,insulation in the ceiling of the laundry and kitchen ceiling and exterior wall. comply with title 24 | $40,000 |
| Apr 12, 2006 | Completed final sign-off Jun 2006 | 101 Lansdale Av | add 3 gfi outlets, 1 new light, new shower fixtures, new tub and fixtures. add 1 more sink, water lines, waste line. framing 9 new landing. for the tub-new copper shower pan and drain. no structural work.Details
add 3 gfi outlets, 1 new light, new shower fixtures, new tub and fixtures. add 1 more sink, water lines, waste line. framing 9 new landing. for the tub-new copper shower pan and drain. no structural work. | $5,200 |