- 0 permits filed
5 permits since 2000: 4 completed, 1 expired or cancelled.
This is the city’s permit record, not a license check. It does not show whether the state license is active, bonded or insured. How to read these records
Permits filed each year
How long permits take
Each point is the quarter the permits were filed, for all building permits across San Francisco. A median counts only permits that have finished, so the shaded recent quarters look faster than they will end up: their slow permits have not finished yet. Hover a point for the slowest 10%. Gaps mean fewer than 5 permits. A rise in the issue line is the city’s review backlog, not the contractor. Too few of this contractor’s permits have finished to plot them.
Most recent permits
| Filed | Outcome | Address | Work described on the permit | Declared cost |
|---|---|---|---|---|
| Oct 19, 2015 | Completed final sign-off May 2016 | 527 Oak Park Dr | install 2 windos, install grade beam with steel column, strengthen send floor wall, install simpson strong walls, install hold-downds 1st floorDetails
install 2 windos, install grade beam with steel column, strengthen send floor wall, install simpson strong walls, install hold-downds 1st floor | $64,000 |
| Aug 20, 2015 | Completed final sign-off May 2016 | 527 Oak Park Dr | voluntary siesmic retrofit, special cantilever moment column, foundation bolts, hold downs.Details
voluntary siesmic retrofit, special cantilever moment column, foundation bolts, hold downs. | $12,600 |
| Jun 14, 2010 | Completed final sign-off Jul 2010 | 40 Brompton Av | install plywood & framing angle/clips/hardware for voluntary sub-flr. strenghtening. 1/2" plywd. struc-1 approx. 54' installed @ ground level as access allows. nailing 10d @ 6"o.c. @ edge, 12"o.c. @ field. 5/8" dia.exp.anchors @ 4'-0" w/ 3" sq.galv. plate washer 7" emb.Details
install plywood & framing angle/clips/hardware for voluntary sub-flr. strenghtening. 1/2" plywd. struc-1 approx. 54' installed @ ground level as access allows. nailing 10d @ 6"o.c. @ edge, 12"o.c. @ field. 5/8" dia.exp.anchors @ 4'-0" w/ 3" sq.galv. plate washer 7" emb. | $7,000 |
| Jun 14, 2010 | Completed final sign-off Jul 2010 | 2079 43rd Av | install plywd. & framing clips/angles/hardware for voluntary strengthening. 1/2" plywd. struc-1 nailing w/ 10d @ 6"o.c. edge & 12"o.c. field. plywood quantity approx. 60' installed @ ground level as access allows. 5/8" dia. exp. anchor @ 4'-0" max w/ 3" sq.x1/4" galv. plate washer 7" emb.Details
install plywd. & framing clips/angles/hardware for voluntary strengthening. 1/2" plywd. struc-1 nailing w/ 10d @ 6"o.c. edge & 12"o.c. field. plywood quantity approx. 60' installed @ ground level as access allows. 5/8" dia. exp. anchor @ 4'-0" max w/ 3" sq.x1/4" galv. plate washer 7" emb. | $6,000 |
| May 18, 2007 | Expired or cancelled expired Dec 2007 | 231 Marietta Dr | install metal beam in garage to reinforce (e) girder.Details