- 0 permits filed
67 permits since 2000: 59 completed, 7 never finaled, 1 expired or cancelled.
Of the 7 never-finaled permits, 7 are over 10 years old.
This is the city’s permit record, not a license check. It does not show whether the state license is active, bonded or insured. How to read these records
Permits filed each year
How long permits take
Each point is the quarter the permits were filed, for all building permits across San Francisco. A median counts only permits that have finished, so the shaded recent quarters look faster than they will end up: their slow permits have not finished yet. Hover a point for the slowest 10%. Gaps mean fewer than 5 permits. A rise in the issue line is the city’s review backlog, not the contractor.
Most recent permits
| Filed | Outcome | Address | Work described on the permit | Declared cost |
|---|---|---|---|---|
| Jan 10, 2013 | Completed final sign-off Dec 2013 | 1680 Eddy St | to obtain final inspection for work approved under pa#200808152447. all work is complete.Details
to obtain final inspection for work approved under pa#200808152447. all work is complete. | |
| Jan 8, 2013 | Completed final sign-off Dec 2013 | 1680 Eddy St | to obtain final inspection for work approved under pa # 201106248892. all work is complete.Details
to obtain final inspection for work approved under pa # 201106248892. all work is complete. | |
| Dec 7, 2011 | Completed final sign-off Dec 2013 | 1680 Eddy St | remove 2 non conforming stairs and 1 non complying ramp and replace with 2 new exterior stairs and 1 ramp with handrailsDetails
remove 2 non conforming stairs and 1 non complying ramp and replace with 2 new exterior stairs and 1 ramp with handrails | $4,000 |
| Aug 17, 2011 | Completed final sign-off Sep 2011 | 1690 Eddy St | revision to pa# 2010.09.03.0223. revise accessible path of travel to show 48" walkway. replace existing 2 steps at sidewalk with 2 new steps and handrailDetails
revision to pa# 2010.09.03.0223. revise accessible path of travel to show 48" walkway. replace existing 2 steps at sidewalk with 2 new steps and handrail | $3,000 |
| Aug 15, 2011 | Completed final sign-off Sep 2011 | 1680 Eddy St | revision to appl #201010082636 - add accessible ramp & railing at (e) play area, re-construct (e) fence. not visible from the streetDetails
revision to appl #201010082636 - add accessible ramp & railing at (e) play area, re-construct (e) fence. not visible from the street | $4,000 |
| Jun 24, 2011 | Never finaled issued Jul 2011, no final | 1680 Eddy St | replacement of (e) non complying concrete ramp with new complying accessible ramp & railing in (e) location. (e) fencing to relocated, add entry controls to fenceDetails
replacement of (e) non complying concrete ramp with new complying accessible ramp & railing in (e) location. (e) fencing to relocated, add entry controls to fence | $8,000 |
| Apr 1, 2011 | Completed final sign-off May 2011 | 1150 Pierce St | relocate extg site fence at pierce st between turk and eddy to completely inside property line. re-install extg fence at new location. extg landscape area at sidewalk to remain.Details
relocate extg site fence at pierce st between turk and eddy to completely inside property line. re-install extg fence at new location. extg landscape area at sidewalk to remain. | $2,000 |
| Jan 20, 2011 | Never finaled issued Jan 2011, no final | 1690 Eddy St | approval of sffd fire access in lieu of required sprinklers (refer to p/a no. 201009030223. demo/relocate existing parking space and curb. all parking on site.Details
approval of sffd fire access in lieu of required sprinklers (refer to p/a no. 201009030223. demo/relocate existing parking space and curb. all parking on site. | $1,000 |
| Oct 21, 2010 | Never finaled issued Oct 2010, no final | 1225 Steiner St | installation of 3 free standing trash enclosures and entry trellis structure with accessible path of travel laundry bldg.Details
installation of 3 free standing trash enclosures and entry trellis structure with accessible path of travel laundry bldg. | $110,000 |
| Oct 8, 2010 | Completed final sign-off Sep 2011 | 1680 Eddy St | renovation of (e) community bldg bathrooms, offices, kitchen at 2nd floor, new windows to replace (e) at 2nd floor. new hvac, plumbing, electrical, new exterior stair to repair (e) stair. no work at ground fl, no work in public way. (n)accessible ramp to replace existing non-complying ramp.Details
renovation of (e) community bldg bathrooms, offices, kitchen at 2nd floor, new windows to replace (e) at 2nd floor. new hvac, plumbing, electrical, new exterior stair to repair (e) stair. no work at ground fl, no work in public way. (n)accessible ramp to replace existing non-complying ramp. | $600,000 |
| Oct 8, 2010 | Never finaled issued Feb 2011, no final | 1150 Pierce St | (e) accessory structure to 1150 pierce st. scope of permit: install new curb cut at (e) sidewalk.Details
(e) accessory structure to 1150 pierce st. scope of permit: install new curb cut at (e) sidewalk. | $5,000 |
| Sep 9, 2010 | Completed final sign-off Dec 2013 | 1303 Steiner St | rebuild free standing trash enclosures, pathe of accessible travel to accessible units (units accessiblity via sep permit) new accessible parking at ex parking lots (3 locations) rebuild e steps to n accessible ramp at same locaation, no work at public wayDetails
rebuild free standing trash enclosures, pathe of accessible travel to accessible units (units accessiblity via sep permit) new accessible parking at ex parking lots (3 locations) rebuild e steps to n accessible ramp at same locaation, no work at public way | $110,000 |
| Sep 3, 2010 | Completed final sign-off Sep 2011 | 1665 Eddy St | to erect 1 story laundry building. fire dept access review and fire protection analysis. no sprinklers required. access lane and lock box program sffd ab-5.09 required.Details
to erect 1 story laundry building. fire dept access review and fire protection analysis. no sprinklers required. access lane and lock box program sffd ab-5.09 required. | $400,000 |
| Sep 3, 2010 | Completed final sign-off Dec 2013 | 1690 Eddy St | to erect 1 story laundry building.Details
to erect 1 story laundry building. | $200,000 |
| Jul 26, 2010 | Completed final sign-off Feb 2011 | 1329 Steiner St | unit 02 and 82: convert 2 existing units to accessible. new kitchen, bath cabinets, raise elec, new bath layout, upgrade finishesDetails
unit 02 and 82: convert 2 existing units to accessible. new kitchen, bath cabinets, raise elec, new bath layout, upgrade finishes | $44,000 |
| Jul 26, 2010 | Completed final sign-off Mar 2011 | 1755 Ellis St | convert two existing units to accessible (1755 ellis unit 32 & 93), new kitchen & bath cabients, raise electrical, new bathroom layout, upgrade finishes.Details
convert two existing units to accessible (1755 ellis unit 32 & 93), new kitchen & bath cabients, raise electrical, new bathroom layout, upgrade finishes. | $44,000 |
| Jul 26, 2010 | Completed final sign-off Mar 2011 | 1797 Ellis St | unit 31: convert 1 existing unit to accessible. new kitchen, bath cabinets, raise elec, new bath layout, upgrade finishesDetails
unit 31: convert 1 existing unit to accessible. new kitchen, bath cabinets, raise elec, new bath layout, upgrade finishes | $22,000 |
| Jul 26, 2010 | Completed final sign-off Jan 2011 | 1303 Steiner St | unit 62: convert 1 existing unit to accessible. new kitchen, bath cabinets, raise elec, new bath layout, upgrade finishesDetails
unit 62: convert 1 existing unit to accessible. new kitchen, bath cabinets, raise elec, new bath layout, upgrade finishes | $22,000 |
| Jul 26, 2010 | Completed final sign-off Mar 2011 | 1349 Steiner St | unit 83: convert 1 existing unit to accessible. new kitchen, bath cabinets, raise elec, new bath layout, upgrade finishesDetails
unit 83: convert 1 existing unit to accessible. new kitchen, bath cabinets, raise elec, new bath layout, upgrade finishes | $22,000 |
| Jul 12, 2010 | Completed final sign-off Mar 2011 | 1355 Steiner St | convert 2 existing units to accessible (units 63 & 92). new kitchen, bath cabinets, raise elec, new bath layout, upgrade finishesDetails
convert 2 existing units to accessible (units 63 & 92). new kitchen, bath cabinets, raise elec, new bath layout, upgrade finishes | $44,000 |
| Jul 12, 2010 | Completed final sign-off Mar 2011 | 1624 Eddy St | unit o1: convert 1 existing unit to accessible. new kitchen and bath caints, raise elec, new bath layout, upgrade finishesDetails
unit o1: convert 1 existing unit to accessible. new kitchen and bath caints, raise elec, new bath layout, upgrade finishes | $22,000 |
| Jul 6, 2010 | Completed final sign-off Dec 2013 | 1769 Ellis St | 1775 ellis, unit 52: convert 1 existing unit to accessible. new kitchen and bath cabinets, raise electrical, new bathroom layout, upgrade finishesDetails
1775 ellis, unit 52: convert 1 existing unit to accessible. new kitchen and bath cabinets, raise electrical, new bathroom layout, upgrade finishes | $22,000 |
| Jul 6, 2010 | Completed final sign-off Dec 2013 | 1250 Pierce St | 1250 pierce, unit 53: convert 1 existing unit to accessible. new kitchen and bath cabinets. raise electrical, new bathroom layout, ugprade finishesDetails
1250 pierce, unit 53: convert 1 existing unit to accessible. new kitchen and bath cabinets. raise electrical, new bathroom layout, ugprade finishes | $22,000 |
| Mar 25, 2010 | Completed final sign-off Sep 2010 | 1769 Ellis St | bldg 3.1 - remove existing base & upper cabients, existing appliances, & existing plumbing fixtures & replace in kind, 9 total kitchens. at least 50% high electrical lighting (by wattage) cec 150 (k)8 no change to exhaust systemDetails
bldg 3.1 - remove existing base & upper cabients, existing appliances, & existing plumbing fixtures & replace in kind, 9 total kitchens. at least 50% high electrical lighting (by wattage) cec 150 (k)8 no change to exhaust system | $13,221 |
| Mar 25, 2010 | Completed final sign-off Feb 2011 | 1560 Turk St | bldg 1 - remove existing base & upper cabients, existing appliances, & exisitng plumbing fixtures & repalce in kind, 23 total kitchens.Details
bldg 1 - remove existing base & upper cabients, existing appliances, & exisitng plumbing fixtures & repalce in kind, 23 total kitchens. | $195,500 |
| Mar 25, 2010 | Completed final sign-off Mar 2011 | 1355 Steiner St | bldg 2.3 -to comply w/his nov #200866799 dated 8/1/2008: remove existing base & upper cabients, existing appliances, & exisitng plumbing fixtures & repalce in kind, 10 total kitchens.Details
bldg 2.3 -to comply w/his nov #200866799 dated 8/1/2008: remove existing base & upper cabients, existing appliances, & exisitng plumbing fixtures & repalce in kind, 10 total kitchens. | $85,000 |
| Mar 25, 2010 | Completed final sign-off Dec 2010 | 1225 Steiner St | bldg 5 - remove existing base & upper cabients, existing appliances, & exisitng plumbing fixtures & repalce in kind, 19 total kitchens.Details
bldg 5 - remove existing base & upper cabients, existing appliances, & exisitng plumbing fixtures & repalce in kind, 19 total kitchens. | $27,911 |
| Mar 25, 2010 | Completed final sign-off Feb 2011 | 1675 Eddy St | bldg 3 - remove existing base & upper cabients, existing appliances, & exisitng plumbing fixtures & repalce in kind, 20 total kitchens.Details
bldg 3 - remove existing base & upper cabients, existing appliances, & exisitng plumbing fixtures & repalce in kind, 20 total kitchens. | $170,000 |
| Mar 25, 2010 | Completed final sign-off Oct 2010 | 1315 Steiner St | bldg 1.2 -remove existing base & upper cabients, existing appliances, & exisitng plumbing fixtures & repalce in kind, 20 total kitchens.Details
bldg 1.2 -remove existing base & upper cabients, existing appliances, & exisitng plumbing fixtures & repalce in kind, 20 total kitchens. | $29,380 |
| Mar 25, 2010 | Completed final sign-off Mar 2011 | 1797 Ellis St | bldg 22 -to comply w/his nov #200866799 dated 8/1/2008: remove existing base & upper cabients, existing appliances, & exisitng plumbing fixtures & repalce in kind, 10 total kitchens. at least 50% high efficiency lighting (by wattage) cec 150 (k)8, no chagne to exhaust system, to comply with his novDetails
bldg 22 -to comply w/his nov #200866799 dated 8/1/2008: remove existing base & upper cabients, existing appliances, & exisitng plumbing fixtures & repalce in kind, 10 total kitchens. at least 50% high efficiency lighting (by wattage) cec 150 (k)8, no chagne to exhaust system, to comply with his nov | $7,345 |
| Mar 25, 2010 | Completed final sign-off Sep 2010 | 1349 Steiner St | bldg 1.1 - to comply w/his nov #200866799 dated 8/1/2008: remove existing base & upper cabients, existing appliances, & existing plumbing fixtures & replace in kind, 10 total kitchens.Details
bldg 1.1 - to comply w/his nov #200866799 dated 8/1/2008: remove existing base & upper cabients, existing appliances, & existing plumbing fixtures & replace in kind, 10 total kitchens. | $14,690 |
| Mar 25, 2010 | Completed final sign-off Apr 2011 | 1520 Turk St | bldg 6 - remove existing base & upper cabients, existing appliances, & exisitng plumbing fixtures & repalce in kind, 13 total kitchens.Details
bldg 6 - remove existing base & upper cabients, existing appliances, & exisitng plumbing fixtures & repalce in kind, 13 total kitchens. | $19,097 |
| Mar 25, 2010 | Completed final sign-off Apr 2011 | 1150 Pierce St | bldg 2 - remove existing base & upper cabients, existing appliances, & exisitng plumbing fixtures & repalce in kind, 15 total kitchens.Details
bldg 2 - remove existing base & upper cabients, existing appliances, & exisitng plumbing fixtures & repalce in kind, 15 total kitchens. | $22,035 |
| Mar 25, 2010 | Completed final sign-off Sep 2010 | 1250 Pierce St | bldg 3.2 - remove existing base & upper cabients, existing appliances, & exisitng plumbing fixtures & repalce in kind, 10 total kitchens.Details
bldg 3.2 - remove existing base & upper cabients, existing appliances, & exisitng plumbing fixtures & repalce in kind, 10 total kitchens. | $85,000 |
| Mar 25, 2010 | Completed final sign-off Apr 2011 | 1214 Pierce St | remove existing base & upper cabients, existing appliances, & exisitng plumbing fixtures & repalce in kind, 10 total kitchens. at least 50% high efficiency lighting (by wattage) cec 150 (k) 8 no change to exhaust systemDetails
remove existing base & upper cabients, existing appliances, & exisitng plumbing fixtures & repalce in kind, 10 total kitchens. at least 50% high efficiency lighting (by wattage) cec 150 (k) 8 no change to exhaust system | $16,159 |
| Mar 25, 2010 | Completed final sign-off Mar 2011 | 1624 Eddy St | bldg 1.3 -to comply w/his nov #200866799 dated 8/1/2008: remove existing base & upper cabients, existing appliances, & exisitng plumbing fixtures & repalce in kind, 10 total kitchens.Details
bldg 1.3 -to comply w/his nov #200866799 dated 8/1/2008: remove existing base & upper cabients, existing appliances, & exisitng plumbing fixtures & repalce in kind, 10 total kitchens. | $14,690 |
| Mar 25, 2010 | Completed final sign-off Jan 2011 | 1303 Steiner St | bldg 2.4 -to comply w/his nov #200866801 dated 7/31/2008: remove existing base & upper cabients, existing appliances, & existing plumbing fixtures & replace in kind, 10 total kitchens.Details
bldg 2.4 -to comply w/his nov #200866801 dated 7/31/2008: remove existing base & upper cabients, existing appliances, & existing plumbing fixtures & replace in kind, 10 total kitchens. | $14,690 |
| Mar 25, 2010 | Completed final sign-off Mar 2011 | 1747 Ellis St | bldg 2.1 - remove existing base & upper cabients, existing appliances, & existing plumbing fixtures & replace in kind, 16 total kitchens.Details
bldg 2.1 - remove existing base & upper cabients, existing appliances, & existing plumbing fixtures & replace in kind, 16 total kitchens. | $33,787 |
| Mar 25, 2010 | Expired or cancelled expired May 2013 | 1625 Eddy St | bldg 4 -remove existing base & upper cabients, existing appliances, & exisitng plumbing fixtures & repalce in kind, 20 total kitchens.Details
bldg 4 -remove existing base & upper cabients, existing appliances, & exisitng plumbing fixtures & repalce in kind, 20 total kitchens. | $29,380 |
| Mar 11, 2010 | Completed final sign-off Mar 2011 | 1303 Steiner St | to complete work and obtain final inspection for work approved under app#200812309315Details
to complete work and obtain final inspection for work approved under app#200812309315 | $75,000 |
| Mar 11, 2010 | Completed final sign-off Mar 2011 | 1315 Steiner St | to complete work and obtain final inspection for work; approved under pa 200812309369Details
to complete work and obtain final inspection for work; approved under pa 200812309369 | $250,000 |
| Mar 11, 2010 | Completed final sign-off Mar 2011 | 1747 Ellis St | to complete work and obtain final inspection for work; approved under pa 2008-1230-9312Details
to complete work and obtain final inspection for work; approved under pa 2008-1230-9312 | $225,000 |
| Mar 11, 2010 | Completed final sign-off Mar 2011 | 1349 Steiner St | to complete work and obtain final inspection for work approved under app#200812309309.Details
to complete work and obtain final inspection for work approved under app#200812309309. | $160,000 |
| Mar 11, 2010 | Completed final sign-off Mar 2011 | 1355 Steiner St | to complete work and obtain final inspection for work; aproved under pa 200812309314Details
to complete work and obtain final inspection for work; aproved under pa 200812309314 | $125,000 |
| Mar 11, 2010 | Completed final sign-off Apr 2011 | 1150 Pierce St | to complete work and obtain final inspection for work approved under app#200812309306.Details
to complete work and obtain final inspection for work approved under app#200812309306. | $175,000 |
| Mar 11, 2010 | Completed final sign-off Oct 2010 | 1250 Pierce St | to complete work and obtain final inspection for work; aproved under pa 200812309321Details
to complete work and obtain final inspection for work; aproved under pa 200812309321 | $75,000 |
| Mar 11, 2010 | Never finaled issued Mar 2010, no final | 1797 Ellis St | to complete work and obtain final inspection for work; aproved under pa 200812309313Details
to complete work and obtain final inspection for work; aproved under pa 200812309313 | $75,000 |
| Mar 11, 2010 | Completed final sign-off Feb 2011 | 1675 Eddy St | to complete work and obtain final inspection for work approved under app#200812309317Details
to complete work and obtain final inspection for work approved under app#200812309317 | $200,000 |
| Mar 11, 2010 | Completed final sign-off Apr 2011 | 1214 Pierce St | to complete work and obtain final inspection for work; approved under pa 200812309322Details
to complete work and obtain final inspection for work; approved under pa 200812309322 | $190,000 |
| Mar 11, 2010 | Completed final sign-off Dec 2010 | 1624 Eddy St | to complete work and obtain final inspection for work; aproved under pa 2008-1230-9311Details
to complete work and obtain final inspection for work; aproved under pa 2008-1230-9311 | $160,000 |
| Mar 11, 2010 | Completed final sign-off Feb 2011 | 1625 Eddy St | to complete work and obtain final inspection for work approved under app#200812309318Details
to complete work and obtain final inspection for work approved under app#200812309318 | $200,000 |
| Mar 11, 2010 | Completed final sign-off Mar 2011 | 1769 Ellis St | to complete work and obtain final inspection for work; aproved under pa 200812309316Details
to complete work and obtain final inspection for work; aproved under pa 200812309316 | $125,000 |
| Mar 11, 2010 | Completed final sign-off Feb 2011 | 1225 Steiner St | to complete work and obtain final inspection for work approved under app#200812309312Details
to complete work and obtain final inspection for work approved under app#200812309312 | $250,000 |
| Mar 11, 2010 | Never finaled issued Mar 2010, no final | 1520 Turk St | to complete work and obtain final inspection for work approved under app#200812309320Details
to complete work and obtain final inspection for work approved under app#200812309320 | $150,000 |
| Mar 8, 2010 | Completed final sign-off Mar 2011 | 1329 Steiner St | building 1.2-1329 steiner st. (units #72,81). enclose the (e) balconies into attic space. non-habitable space, no lighting.Details
building 1.2-1329 steiner st. (units #72,81). enclose the (e) balconies into attic space. non-habitable space, no lighting. | $8,000 |
| Mar 8, 2010 | Completed final sign-off Mar 2011 | 1775 Ellis St | building 3.1-1775 ellis st. (unit #30). enclose 1-(e) balcony into attic. non-habitable space, no lighting.Details
building 3.1-1775 ellis st. (unit #30). enclose 1-(e) balcony into attic. non-habitable space, no lighting. | $4,000 |
| Mar 8, 2010 | Completed final sign-off Mar 2011 | 1755 Ellis St | enclosed two existing balconies into attic space, non habitable space, no lighting. work at bldg 2.1 - 1755 ellis st only. units #21 & 26.Details
enclosed two existing balconies into attic space, non habitable space, no lighting. work at bldg 2.1 - 1755 ellis st only. units #21 & 26. | $8,000 |
| Mar 8, 2010 | Completed final sign-off Mar 2011 | 1349 Steiner St | enclosed 1 (e) deck (balcony) into attic space, no lighting work & non-habitable space, work at bldg 1.1 - 1349 steiner st only. (unit #15)Details
enclosed 1 (e) deck (balcony) into attic space, no lighting work & non-habitable space, work at bldg 1.1 - 1349 steiner st only. (unit #15) | $4,000 |
| Mar 8, 2010 | Completed final sign-off Apr 2011 | 1214 Pierce St | building #4-1214 pierce st. (unit#46). enclose 1-(e) balcony into attic space. non habitable space, no lighting.Details
building #4-1214 pierce st. (unit#46). enclose 1-(e) balcony into attic space. non habitable space, no lighting. | $4,000 |
| Mar 8, 2010 | Completed final sign-off Mar 2011 | 1624 Eddy St | enclosed 1 (e) deck (balcony) into attic space, no lighting work & non-habitable space, work at bldg 1.3 - 1624 eddy st. (unit #11).Details
enclosed 1 (e) deck (balcony) into attic space, no lighting work & non-habitable space, work at bldg 1.3 - 1624 eddy st. (unit #11). | $4,000 |
| Mar 1, 2010 | Completed final sign-off Feb 2011 | 1150 Pierce St | enclose (e) balconies at 6-locationsDetails
enclose (e) balconies at 6-locations | $24,000 |
| Mar 1, 2010 | Completed final sign-off Apr 2011 | 1520 Turk St | enclouse (e) balcony at 6-locations.Details
enclouse (e) balcony at 6-locations. | $24,000 |
| Mar 1, 2010 | Completed final sign-off Feb 2011 | 1675 Eddy St | enclose (e) balconies at 8-locations.Details
enclose (e) balconies at 8-locations. | $32,000 |
| Mar 1, 2010 | Completed final sign-off Feb 2011 | 1225 Steiner St | enclose (e) balconies at 10-locations.Details
enclose (e) balconies at 10-locations. | $40,000 |
| Mar 1, 2010 | Completed final sign-off Feb 2011 | 1560 Turk St | enclosed (e) balconies at 10 locations.Details
enclosed (e) balconies at 10 locations. | $40,000 |
| Mar 1, 2010 | Completed final sign-off Feb 2011 | 1625 Eddy St | enclose (e) balcony at 8-locations.Details
enclose (e) balcony at 8-locations. | $32,000 |
| Feb 26, 2010 | Never finaled issued Mar 2010, no final | 1560 Turk St | replacement in kind of (e) windows, new double glazed to replace single glazed, repair and/or replace exterior finishes, no interior work except painting & carpet. re-roofing under seperate permit.Details
replacement in kind of (e) windows, new double glazed to replace single glazed, repair and/or replace exterior finishes, no interior work except painting & carpet. re-roofing under seperate permit. | $175,000 |