Pepper Construction
- Based in
- Barrington
- On San Francisco permits
- Sep 2013 to Mar 2015
- Last 24 months
- 0 permits filed
11 permits since 2000: 8 completed, 2 never finaled, 1 expired or cancelled.
Of the 2 never-finaled permits, 2 are over 10 years old.
This is the city’s permit record, not a license check. It does not show whether the state license is active, bonded or insured. How to read these records
Permits filed each year
How long permits take
Each point is the quarter the permits were filed, for all building permits across San Francisco. A median counts only permits that have finished, so the shaded recent quarters look faster than they will end up: their slow permits have not finished yet. Hover a point for the slowest 10%. Gaps mean fewer than 5 permits. A rise in the issue line is the city’s review backlog, not the contractor.
Most recent permits
| Filed | Outcome | Address | Work described on the permit | Declared cost |
|---|---|---|---|---|
| Mar 19, 2015 | Never finaled issued Apr 2015, no final | 170 Maiden Ln | revision to 201309166943 r1 minor revision to interior retail space , no exterior workDetails
revision to 201309166943 r1 minor revision to interior retail space , no exterior work | $5,000 |
| Feb 19, 2015 | Completed final sign-off Jul 2016 | 345 Stockton St | structural revisions to addendum 5 structral 201312164258 (aka 300 post)Details
structural revisions to addendum 5 structral 201312164258 (aka 300 post) | |
| Jan 20, 2015 | Completed final sign-off Jul 2016 | 345 Stockton St | decommission 4/f handler; relocate fan coil units and generator aspiration fan, reroute assoc. duct work, reroute basement 2 & 3 exhaust flue;. provide temp. o. s,a duct on 1/f for riser shaft. reroute piping through 3/f ceiling into 4/f. decommision roof con. unit ; relocate dry air coolerDetails
decommission 4/f handler; relocate fan coil units and generator aspiration fan, reroute assoc. duct work, reroute basement 2 & 3 exhaust flue;. provide temp. o. s,a duct on 1/f for riser shaft. reroute piping through 3/f ceiling into 4/f. decommision roof con. unit ; relocate dry air cooler | $120,000 |
| Dec 17, 2014 | Completed final sign-off Jul 2016 | 345 Stockton St | temporary phased egress plan during construction for the hyatt assembly areas at basement level 3 of the hyatt hotel @ 345 stockton aka 300 post. no other work under this permit.Details
temporary phased egress plan during construction for the hyatt assembly areas at basement level 3 of the hyatt hotel @ 345 stockton aka 300 post. no other work under this permit. | |
| Nov 19, 2014 | Completed final sign-off Jul 2016 | 345 Stockton St | revision to pa#201312164258-s2 to clarify demolition phasing and sequencing.Details
revision to pa#201312164258-s2 to clarify demolition phasing and sequencing. | |
| Nov 4, 2014 | Completed final sign-off Jul 2016 | 345 Stockton St | revision to foundation permit addendum pa 201312164258; changing rebar sizing for the stiffening of structural columns.Details
revision to foundation permit addendum pa 201312164258; changing rebar sizing for the stiffening of structural columns. | |
| Nov 4, 2014 | Completed final sign-off Jul 2016 | 345 Stockton St | revision to bar bldg seismic strengthening pa #201406027261; for the addiitions of penetrations in the shear walls for (n) man doors.Details
revision to bar bldg seismic strengthening pa #201406027261; for the addiitions of penetrations in the shear walls for (n) man doors. | |
| Jul 22, 2014 | Expired or cancelled cancelled Jan 2026 | 170 Maiden Ln | to erect electric, projecting, double faced sign.Details
to erect electric, projecting, double faced sign. | $5,000 |
| Jun 2, 2014 | Completed final sign-off Jul 2016 | 345 Stockton St | seismic strengthening of bar building structure. work includes (n) shear walls & moment frames, gravity elements at selected locations for (n) staircase & elevator.Details
seismic strengthening of bar building structure. work includes (n) shear walls & moment frames, gravity elements at selected locations for (n) staircase & elevator. | $179,000 |
| May 30, 2014 | Completed final sign-off Jul 2016 | 345 Stockton St | b2,b3,1st,2nd,3rd,4th & lower roof level - interior demo of (e) unoccupied space per ab-17. work includes non-structural elements, partitions, furniture, equipment, restrooms, hvac, electrical, & plumbing. reference site 2013.1216.4258 (not approved)Details
b2,b3,1st,2nd,3rd,4th & lower roof level - interior demo of (e) unoccupied space per ab-17. work includes non-structural elements, partitions, furniture, equipment, restrooms, hvac, electrical, & plumbing. reference site 2013.1216.4258 (not approved) | $20,000 |
| Sep 16, 2013 | Never finaled issued Aug 2014, no final | 170 Maiden Ln | t.i. of interior retail space. work includes new convenient stair, non-structural partitions, ceiling, finishes, mechanical and plumbing. no change in use. interior work only.Details
t.i. of interior retail space. work includes new convenient stair, non-structural partitions, ceiling, finishes, mechanical and plumbing. no change in use. interior work only. | $800,000 |