Permit GraphShortlistSan Francisco building permits since 2000

Palmer Electric Inc.

Contractor license
264817
State license record
Based in
San Carlos
On San Francisco permits
Apr 2000 to Sep 2000
Last 24 months
0 permits filed

2 permits since 2000: 2 completed.

CompletedIn progressNever finaledExpired or cancelled

This is the city’s permit record, not a license check. It does not show whether the state license is active, bonded or insured. How to read these records

Permits filed each year

How long permits take

Median days to final inspection, citywideMedian days to permit issued, citywide

Each point is the quarter the permits were filed, for all building permits across San Francisco. A median counts only permits that have finished, so the shaded recent quarters look faster than they will end up: their slow permits have not finished yet. Hover a point for the slowest 10%. Gaps mean fewer than 5 permits. A rise in the issue line is the city’s review backlog, not the contractor. Too few of this contractor’s permits have finished to plot them.

Most recent permits

All
FiledOutcomeAddressWork described on the permitDeclared cost
Sep 26, 2000Completed
final sign-off Oct 2000
120 Kearny Stmodifications to existing fire alarm system-26th floor
Details
Permit
200009261534
Status
complete
Filed
Sep 26, 2000
Permit issued
Sep 26, 2000
Final sign-off
Oct 19, 2000
Declared cost
$5,000
Address
120 Kearny St

modifications to existing fire alarm system-26th floor

Open the permit page

$5,000
Apr 25, 2000Completed
final sign-off Oct 2000
120 Kearny Stoti-3, ls, 32nd floor
Details
Permit
200004258164
Status
complete
Filed
Apr 25, 2000
Permit issued
May 4, 2000
Final sign-off
Oct 19, 2000
Declared cost
$9,000
Address
120 Kearny St

oti-3, ls, 32nd floor

Open the permit page

$9,000