- 1 permit filed
58 permits since 2000: 55 completed, 1 in progress, 2 never finaled.
Of the 2 never-finaled permits, 1 is 5 to 10 years old, 1 is over 10 years old.
This is the city’s permit record, not a license check. It does not show whether the state license is active, bonded or insured. How to read these records
Permits filed each year
How long permits take
Each point is the quarter the permits were filed, for all building permits across San Francisco. A median counts only permits that have finished, so the shaded recent quarters look faster than they will end up: their slow permits have not finished yet. Hover a point for the slowest 10%. Gaps mean fewer than 5 permits. A rise in the issue line is the city’s review backlog, not the contractor.
Most recent permits
| Filed | Outcome | Address | Work described on the permit | Declared cost |
|---|---|---|---|---|
| Dec 13, 2024 | Completed final sign-off Dec 2024 | 3170 25th St | revision to pa# 2024-0226-6583 to document that only 6 windows were removed and replaced rather than the 14 as originally stated on the original application.Details
revision to pa# 2024-0226-6583 to document that only 6 windows were removed and replaced rather than the 14 as originally stated on the original application. | |
| Aug 19, 2024 | In progress issued Aug 2024 | 878 Wisconsin St | window replacement - fiber glass windowesDetails
window replacement - fiber glass windowes | $17,000 |
| Aug 19, 2024 | Completed final sign-off Dec 2024 | 878 Wisconsin St | window replacement, 4 windows at courtyard fiber glass windowsDetails
window replacement, 4 windows at courtyard fiber glass windows | $14,000 |
| Feb 26, 2024 | Completed final sign-off Dec 2024 | 3170 25th St | replace (14) windows in kind on front, side, and back. marvin double hung. wood w/wood outside. u=.30maxDetails
replace (14) windows in kind on front, side, and back. marvin double hung. wood w/wood outside. u=.30max | $38,000 |
| Sep 21, 2023 | Completed final sign-off Feb 2024 | 1302 De Haro St | replace 9 windows in-kind on front and side. metal frame 8200 picture series.Details
replace 9 windows in-kind on front and side. metal frame 8200 picture series. | $22,000 |
| Sep 21, 2023 | Completed final sign-off Feb 2024 | 1304 De Haro St | replace 14 windows in-kind on front and side. metal frame 8200 picture series.Details
replace 14 windows in-kind on front and side. metal frame 8200 picture series. | $34,000 |
| Dec 4, 2018 | Completed final sign-off May 2019 | 1302 De Haro St | repair sheetrock, replace trim (interior) paint.Details
repair sheetrock, replace trim (interior) paint. | $8,000 |
| Aug 8, 2018 | Never finaled issued Aug 2018, no final | 164 Hartford St | repair front steps and pathwway concrete in-kind.Details
repair front steps and pathwway concrete in-kind. | $5,800 |
| May 25, 2018 | Completed final sign-off Nov 2018 | 109 Prospect Av | remodel kitchen: install recess lights, new cabinets, counter , tile, floors, sheetrock, paint house. replace (4) windows at rear (not visible from st).Details
remodel kitchen: install recess lights, new cabinets, counter , tile, floors, sheetrock, paint house. replace (4) windows at rear (not visible from st). | $28,000 |
| Sep 8, 2017 | Completed final sign-off Sep 2017 | 1300 De Haro St | inkind repair of damaged siding and tile at front entry; approx 20 sfDetails
inkind repair of damaged siding and tile at front entry; approx 20 sf | $8,000 |
| Jul 19, 2017 | Completed final sign-off Oct 2017 | 1429 Plymouth Av | upper level: bathroom remodel: lumbing, electricalk, tile work, sheetrock, paint. no change in wall & opening layout, h.e. lighting. replace window in bathroom not visible from street at same opening facing rear yark. u factor 0.32 or better.Details
upper level: bathroom remodel: lumbing, electricalk, tile work, sheetrock, paint. no change in wall & opening layout, h.e. lighting. replace window in bathroom not visible from street at same opening facing rear yark. u factor 0.32 or better. | $25,000 |
| Jul 19, 2017 | Completed final sign-off Oct 2017 | 2372 Bay St | bathroom remodel: plumbing, elecrical, sheetrock, tilework, panting. powder room remodel: tile work, electrical, plumbing, sheetrock, paiting, no change in wall & opening layout. h.e. lighting.Details
bathroom remodel: plumbing, elecrical, sheetrock, tilework, panting. powder room remodel: tile work, electrical, plumbing, sheetrock, paiting, no change in wall & opening layout. h.e. lighting. | $30,000 |
| Jul 19, 2017 | Completed final sign-off Oct 2017 | 1338 Union St | bathroom remodel: electrical, pluming, tile work, sheetrock, paint. no change in wlal & opening layout, h.e. lighting.Details
bathroom remodel: electrical, pluming, tile work, sheetrock, paint. no change in wlal & opening layout, h.e. lighting. | $25,000 |
| Jun 1, 2017 | Completed final sign-off Aug 2017 | 3014 California St | remodel master bathroom. electrical, plumbing, sheetrock, tiles, insulationDetails
remodel master bathroom. electrical, plumbing, sheetrock, tiles, insulation | $25,000 |
| May 15, 2017 | Completed final sign-off Jul 2017 | 868 Wisconsin St | replace left side siding & 1 window (not visible from the street) & paint.Details
replace left side siding & 1 window (not visible from the street) & paint. | $15,000 |
| Apr 25, 2017 | Completed final sign-off Oct 2017 | 874 Wisconsin St | rear building: remodel kitchen: install recessed lights, new cabinets, counters. remodel bathroom: tiles, recessed lights, sheet rock, insulation, painting. install floors throughout house, new door & trim. repair siding back of the house. replace 2 windws not visible from the street.Details
rear building: remodel kitchen: install recessed lights, new cabinets, counters. remodel bathroom: tiles, recessed lights, sheet rock, insulation, painting. install floors throughout house, new door & trim. repair siding back of the house. replace 2 windws not visible from the street. | $28,000 |
| Apr 6, 2017 | Completed final sign-off Apr 2017 | 872 Wisconsin St | replace four (4) windows in kind @ front facade. wood clod windows double hung. u-factor 0.32 or better.Details
replace four (4) windows in kind @ front facade. wood clod windows double hung. u-factor 0.32 or better. | $3,000 |
| Feb 28, 2017 | Completed final sign-off Jun 2017 | 3014 California St | remodel (2) bathrooms: tilework, electrical, plumbing, sheetrock, painting,insulation, etc., same level.Details
remodel (2) bathrooms: tilework, electrical, plumbing, sheetrock, painting,insulation, etc., same level. | $35,000 |
| Jan 25, 2017 | Completed final sign-off May 2017 | 650 02nd St | unit #402: remodel and surface upgrade. removal of non load bearing wall. install new doors. elec, painting, carpetDetails
unit #402: remodel and surface upgrade. removal of non load bearing wall. install new doors. elec, painting, carpet | $20,000 |
| Dec 9, 2016 | Completed final sign-off Apr 2017 | 872 Wisconsin St | remodel kitchen electrical work )install recessed light), tilework, new cabinets & counter, floors throughout house, painting & sheetrock, insulation, install tankless water heater.Details
remodel kitchen electrical work )install recessed light), tilework, new cabinets & counter, floors throughout house, painting & sheetrock, insulation, install tankless water heater. | $28,000 |
| Sep 30, 2016 | Completed final sign-off Nov 2016 | 3014 California St | remove stucco on west elevation and replace with siding to match existing siding on front facadeDetails
remove stucco on west elevation and replace with siding to match existing siding on front facade | $18,000 |
| Sep 13, 2016 | Completed final sign-off Sep 2016 | 418 Precita Av | repair siding at back of house and dry rot.Details
repair siding at back of house and dry rot. | $2,500 |
| Jan 22, 2016 | Completed final sign-off Jul 2016 | 1429 Plymouth Av | remove wall between kitchen & dining room & install new ceiling beam.Details
remove wall between kitchen & dining room & install new ceiling beam. | $4,000 |
| Jan 6, 2016 | Completed final sign-off Jun 2016 | 1363 Greenwich St | remodel kitchen, bathroom, powder room, paint unit, add unit luandry, etc. no walls to be removed or altered.Details
remodel kitchen, bathroom, powder room, paint unit, add unit luandry, etc. no walls to be removed or altered. | $45,000 |
| Jan 6, 2016 | Completed final sign-off Apr 2016 | 1429 Plymouth Av | remodel kitchen. electrical plumbing, sheet rock, tile, cabinets, counter, paint etc. no walls to be altered or removed.Details
remodel kitchen. electrical plumbing, sheet rock, tile, cabinets, counter, paint etc. no walls to be altered or removed. | $25,000 |
| Dec 15, 2015 | Completed final sign-off Dec 2015 | 1550 Page St | to obtain finalinspection for work approved under pa # 201312063489 and 201406027208. all work is complete.Details
to obtain finalinspection for work approved under pa # 201312063489 and 201406027208. all work is complete. | |
| Aug 13, 2015 | Completed final sign-off Dec 2015 | 1904 Baker St | interior renovation of master bath, powder room, & eat-in area in kitchen.Details
interior renovation of master bath, powder room, & eat-in area in kitchen. | $50,000 |
| May 28, 2015 | Completed final sign-off Dec 2015 | 1550 Page St | lower unit a: revision to pa 2014 1010 8618 - replacement of (e) non structural concrete slab with (n) non structural slab.Details
lower unit a: revision to pa 2014 1010 8618 - replacement of (e) non structural concrete slab with (n) non structural slab. | $2,000 |
| May 11, 2015 | Completed final sign-off Mar 2016 | 106 Collins St | bathroom remodel - tile, sheetrock, paint, plumbing, electrical, to comply with cec150.0(k)5Details
bathroom remodel - tile, sheetrock, paint, plumbing, electrical, to comply with cec150.0(k)5 | $8,000 |
| Mar 31, 2015 | Completed final sign-off Aug 2015 | 67 Wilmot St | kitchen and bathroom remodel- install new floor, smooth wall and paint unit interior, improvements only no structural improvements or modificaitoin to building exterior. to comply with cec150.0(k)3 & 5Details
kitchen and bathroom remodel- install new floor, smooth wall and paint unit interior, improvements only no structural improvements or modificaitoin to building exterior. to comply with cec150.0(k)3 & 5 | $38,000 |
| Mar 19, 2015 | Completed final sign-off Dec 2015 | 1550 Page St | unit a lower level - revision & modifications to bathroom layout (bathroom serving each room) per #2014.1010.8618 & provision of anchor bolts @ sill plates where not installed, final work associated with fire repairs to building, interior improvements only.Details
unit a lower level - revision & modifications to bathroom layout (bathroom serving each room) per #2014.1010.8618 & provision of anchor bolts @ sill plates where not installed, final work associated with fire repairs to building, interior improvements only. | $5,000 |
| Nov 25, 2014 | Completed final sign-off Feb 2015 | 1550 Page St | repair unit, plumbing, electrical, sheetrock, insulation, demolition, paint, floors, etc. in upper floor - install new gas line for fire places (2)Details
repair unit, plumbing, electrical, sheetrock, insulation, demolition, paint, floors, etc. in upper floor - install new gas line for fire places (2) | $10,000 |
| Nov 25, 2014 | Completed final sign-off Jan 2015 | 119 Albion St | remodel bathroom, electrical, plumbing, tile work, painting, sheetrock repair frame if needed. one (1) and half (1/2) bathroom demolitionDetails
remodel bathroom, electrical, plumbing, tile work, painting, sheetrock repair frame if needed. one (1) and half (1/2) bathroom demolition | $18,000 |
| Oct 10, 2014 | Completed final sign-off Dec 2015 | 1550 Page St | unit a lower level:fire repairs and bathroom remodel. interior improvements only with no structural improvements or modifications to bldg exterior.Details
unit a lower level:fire repairs and bathroom remodel. interior improvements only with no structural improvements or modifications to bldg exterior. | $15,000 |
| Oct 3, 2014 | Completed final sign-off Oct 2014 | 1340 Union St | to obtain final inspection for work approved under pa#200110050085. all work is complete. compliance with maher ordinance no. 155-13 not required.Details
to obtain final inspection for work approved under pa#200110050085. all work is complete. compliance with maher ordinance no. 155-13 not required. | |
| Oct 2, 2014 | Completed final sign-off Oct 2014 | 1340 Union St | to obtain final inspection for work approved under pa# 200702134084. all work is complete.Details
to obtain final inspection for work approved under pa# 200702134084. all work is complete. | |
| Oct 2, 2014 | Completed final sign-off Oct 2014 | 1340 Union St | to obtain final inspection for work approved under pa# 200109259144. all work is complete.Details
to obtain final inspection for work approved under pa# 200109259144. all work is complete. | |
| Aug 19, 2014 | Completed final sign-off Oct 2014 | 1338 Union St | to obtain final inspection for work approved under pa # 9817984. all work is complete. n/a maher ordinance # 155-13Details
to obtain final inspection for work approved under pa # 9817984. all work is complete. n/a maher ordinance # 155-13 | $13,000 |
| Jul 31, 2014 | Completed final sign-off Oct 2014 | 1550 Page St | remodel unit. kitchen cabinet, bath tile, repair frame, electrical, plumbing, insulation, sheetrock, paint, install 2 windowDetails
remodel unit. kitchen cabinet, bath tile, repair frame, electrical, plumbing, insulation, sheetrock, paint, install 2 window | $40,000 |
| Jun 2, 2014 | Never finaled issued Jun 2014, no final | 1550 Page St | revision to 201312063409 to stairs at 1st fl and framing detail changesDetails
revision to 201312063409 to stairs at 1st fl and framing detail changes | |
| May 22, 2014 | Completed final sign-off Nov 2014 | 1550 Page St | remodel bathroom: shower pan, tile, sheetrock, insulation, electrical, plumbing, paint, cabinet, frame.Details
remodel bathroom: shower pan, tile, sheetrock, insulation, electrical, plumbing, paint, cabinet, frame. | $12,000 |
| Apr 23, 2014 | Completed final sign-off Dec 2014 | 1550 Page St | repair fire damage to e tenant improvements to 3rd fl unit c including kitchen cabinets and drywall wall and ceiling and floors. thermal insulation at wall and roof framing. no modifications to e building envelope except relocatio of e skylights. roof repairs and window replacement under separate peDetails
repair fire damage to e tenant improvements to 3rd fl unit c including kitchen cabinets and drywall wall and ceiling and floors. thermal insulation at wall and roof framing. no modifications to e building envelope except relocatio of e skylights. roof repairs and window replacement under separate pe | $45,000 |
| Apr 9, 2014 | Completed final sign-off Oct 2014 | 1338 Union St | to comply with physical inspection report cc-7675Details
to comply with physical inspection report cc-7675 | $2,000 |
| Apr 9, 2014 | Completed final sign-off Oct 2014 | 1340 Union St | to comply with physical inspection report #cc-7401 (1340,1340a,1340b)Details
to comply with physical inspection report #cc-7401 (1340,1340a,1340b) | $7,000 |
| Feb 7, 2014 | Completed final sign-off Apr 2014 | 69 Wilmot St | remodel bathroom & kitchen including new electricla lighting, plumbing, cabinets, sheetrock, paint.Details
remodel bathroom & kitchen including new electricla lighting, plumbing, cabinets, sheetrock, paint. | $18,300 |
| Nov 27, 2012 | Completed final sign-off Mar 2013 | 1555 Burke Av | mechanical only. ref. 201209180035; new residental type exhaust hood, provide exhaust ductwork from hood to existing 10" exhaust stub-upDetails
mechanical only. ref. 201209180035; new residental type exhaust hood, provide exhaust ductwork from hood to existing 10" exhaust stub-up | |
| Sep 18, 2012 | Completed final sign-off Mar 2013 | 1555 Burke Av | extend opening between open studio space. install washer and dryer. instal pony wall for new non commercial stove. comply with complaint 201211961. change of use from med/dental clinic to retail personal services. remodel bathroom to meet adaDetails
extend opening between open studio space. install washer and dryer. instal pony wall for new non commercial stove. comply with complaint 201211961. change of use from med/dental clinic to retail personal services. remodel bathroom to meet ada | $12,500 |
| Jul 10, 2012 | Completed final sign-off Sep 2012 | 109 Prospect Av | replace back fence less than 6', install tile on bathroom floor only, install new tile in balcony approx 5' x 5'.Details
replace back fence less than 6', install tile on bathroom floor only, install new tile in balcony approx 5' x 5'. | $4,500 |
| Sep 26, 2011 | Completed final sign-off Mar 2012 | 124 21st Av | 3rd fl: remodel 1 bath, remove existing chimney flue, relocate existing lights and outlets, relocate existing plumbing. remove a closet and reframe 2 walls. 2nd fl: install (2) new skylight and replace kitchen cabinets.Details
3rd fl: remodel 1 bath, remove existing chimney flue, relocate existing lights and outlets, relocate existing plumbing. remove a closet and reframe 2 walls. 2nd fl: install (2) new skylight and replace kitchen cabinets. | $40,000 |
| Jun 16, 2011 | Completed final sign-off Aug 2011 | 650 03rd Av | remodel bathroom: plumbing and electrical, sheetrock, painting, tiles, remove wall & create new opening (relocate door). install new shower pan. all work on 2nd floor.Details
remodel bathroom: plumbing and electrical, sheetrock, painting, tiles, remove wall & create new opening (relocate door). install new shower pan. all work on 2nd floor. | $12,000 |
| Jan 7, 2011 | Completed final sign-off Jan 2011 | 872 Wisconsin St | bathroom remodel; new bath tub, toilet, sink, tile, replace one window, new fanDetails
bathroom remodel; new bath tub, toilet, sink, tile, replace one window, new fan | $7,000 |
| Oct 14, 2010 | Completed final sign-off Dec 2010 | 167 Caine Av | remodel kitchen, install new sink, stove, dishwasher, garbage disposal, refrigerator, tiles, cabinets in kitchen. replace sheetrock, install new toilet, sink in bathroom, replace floor, work is on 2nd floor.Details
remodel kitchen, install new sink, stove, dishwasher, garbage disposal, refrigerator, tiles, cabinets in kitchen. replace sheetrock, install new toilet, sink in bathroom, replace floor, work is on 2nd floor. | $15,000 |
| Sep 15, 2010 | Completed final sign-off Oct 2010 | 3170 25th St | bathroom remodel, install washer & dryer including plumbing, electrical, tiles & painting. bathroom is on 2nd floorDetails
bathroom remodel, install washer & dryer including plumbing, electrical, tiles & painting. bathroom is on 2nd floor | $15,000 |
| Feb 17, 2010 | Completed final sign-off Dec 2010 | 1340 Union St | new exterior gate, fence/wall w/ new code compliant landing & steps. field verify that gate does not lock from egress side and that there are no deadbolts (key or thumblatch) on egress side.Details
new exterior gate, fence/wall w/ new code compliant landing & steps. field verify that gate does not lock from egress side and that there are no deadbolts (key or thumblatch) on egress side. | $19,000 |
| Nov 5, 2009 | Completed final sign-off Dec 2009 | 414 Dolores St | lower unit.revision to pa#200910209335. enlarge existing opening of 30" to 74" in non bearing wall between kitchen and dining room header 4x8.Details
lower unit.revision to pa#200910209335. enlarge existing opening of 30" to 74" in non bearing wall between kitchen and dining room header 4x8. | $800 |
| Oct 20, 2009 | Completed final sign-off Dec 2009 | 414 Dolores St | remodel existing kitchen and laundry area including new electrical, lighting, plumbing, cabinets, water heater, floors, don't move or add anyw allsDetails
remodel existing kitchen and laundry area including new electrical, lighting, plumbing, cabinets, water heater, floors, don't move or add anyw alls | $20,000 |
| Jul 14, 2009 | Completed final sign-off Oct 2009 | 720 Gough St | remodle kitchen and bathroom: replace cabinets, tiles, repair sheetrock, paint, replace bathtub + sinks. 1 kitchen, 2 bathroom, powder room.Details
remodle kitchen and bathroom: replace cabinets, tiles, repair sheetrock, paint, replace bathtub + sinks. 1 kitchen, 2 bathroom, powder room. | $46,959 |
| May 22, 2009 | Completed final sign-off Jul 2009 | 1363 Greenwich St | in flat # 1365 greenwich street: garden level bedroom: remove and replace sheetrock to remediate dryrot. replace framing as required in-kind on exterior repair shingles. replace deck tiles above bedroomDetails