Permit GraphShortlistSan Francisco building permits since 2000

Nova Corp Dba Nova Cm Corp

Contractor license
887361
State license record
Based in
Nyack
On San Francisco permits
Nov 2014 to May 2019
Last 24 months
0 permits filed

5 permits since 2000: 1 completed, 3 never finaled, 1 expired or cancelled.

Of the 3 never-finaled permits, 2 are 5 to 10 years old, 1 is over 10 years old.

CompletedIn progressNever finaledExpired or cancelled

This is the city’s permit record, not a license check. It does not show whether the state license is active, bonded or insured. How to read these records

Permits filed each year

How long permits take

Median days to final inspection, citywideMedian days to permit issued, citywide

Each point is the quarter the permits were filed, for all building permits across San Francisco. A median counts only permits that have finished, so the shaded recent quarters look faster than they will end up: their slow permits have not finished yet. Hover a point for the slowest 10%. Gaps mean fewer than 5 permits. A rise in the issue line is the city’s review backlog, not the contractor. Too few of this contractor’s permits have finished to plot them.

Most recent permits

All
FiledOutcomeAddressWork described on the permitDeclared cost
May 23, 2019Never finaled
issued Jun 2019, no final
400 Paul Avfire service for new bld
Details
Permit
201905231555
Status
issued
Filed
May 23, 2019
Permit issued
Jun 5, 2019
Declared cost
$15,000
Address
400 Paul Av

fire service for new bld

Open the permit page

$15,000
Jun 25, 2018Never finaled
issued Jul 2018, no final
303 02nd Stsuite 900 -mep only in ref to 201802020269. demo (e) diffusers in revised office areas, install new diffusersa in new ceiling and duct as shown maher na
Details
Permit
201806252865
Status
issued
Filed
Jun 25, 2018
Permit issued
Jul 12, 2018
Declared cost
$46,669
Address
303 02nd St

suite 900 -mep only in ref to 201802020269. demo (e) diffusers in revised office areas, install new diffusersa in new ceiling and duct as shown maher na

Open the permit page

$46,669
Feb 2, 2018Completed
final sign-off Jan 2020
303 02nd Stinterior office tenant improvement in suite 9co. 4 new offices added in existing open space. 827 sq ft total. office renovations to e offices. no mep proposed work entirely within interior of e building. no exterior work proposed
Details
Permit
201802020269
Status
complete
Filed
Feb 2, 2018
Permit issued
Apr 26, 2018
Final sign-off
Jan 27, 2020
Declared cost
$53,755
Address
303 02nd St

interior office tenant improvement in suite 9co. 4 new offices added in existing open space. 827 sq ft total. office renovations to e offices. no mep proposed work entirely within interior of e building. no exterior work proposed

Open the permit page

$53,755
Mar 29, 2016Expired or cancelled
expired Aug 2023
400 Paul Avremodel (e) building with new offices, new ceilings, new interior walls.
Details
Permit
201603293329
Status
expired
Filed
Mar 29, 2016
Permit issued
Jul 25, 2016
Address
400 Paul Av

remodel (e) building with new offices, new ceilings, new interior walls.

Open the permit page

Nov 17, 2014Never finaled
issued Oct 2015, no final
400 Paul Avto erect 2 stories, no basement, data center building. ** maher: compliance with ordinance no# 155-13 not required
Details
Permit
201411171675
Status
issued
Filed
Nov 17, 2014
Permit issued
Oct 20, 2015
Declared cost
$300,000
Address
400 Paul Av

to erect 2 stories, no basement, data center building. ** maher: compliance with ordinance no# 155-13 not required

Open the permit page

$300,000