This is the city’s permit record, not a license check. It does not show whether the state license is active, bonded or insured. How to read these records
Permits filed each year
How long permits take
Each point is the quarter the permits were filed, for all building permits across San Francisco. A median counts only permits that have finished, so the shaded recent quarters look faster than they will end up: their slow permits have not finished yet. Hover a point for the slowest 10%. Gaps mean fewer than 5 permits. A rise in the issue line is the city’s review backlog, not the contractor. Too few of this contractor’s permits have finished to plot them.
Most recent permits
| Filed | Outcome | Address | Work described on the permit | Declared cost |
|---|---|---|---|---|
| Dec 17, 2019 | Completed final sign-off Jan 2020 | 1225 Minnesota St | revision to 201906183748, new rooftop units and new ductworkDetails
revision to 201906183748, new rooftop units and new ductwork | |
| Oct 28, 2019 | Completed final sign-off Jan 2021 | 1225 Minnesota St | to pay penalty fees on nov#201983991 pa#201906183748 was issued however penalty fee were not paid. 9x100000 per novDetails
to pay penalty fees on nov#201983991 pa#201906183748 was issued however penalty fee were not paid. 9x100000 per nov | |
| Jun 18, 2019 | Completed final sign-off Jan 2020 | 1225 Minnesota St | installation of two pre fab built offices in (e) warehouse bldg.Details