Minerva - Graniterock Jv
- Based in
- San Jose
- On San Francisco permits
- Sep 2020 to Jul 2021
- Last 24 months
- 0 permits filed
11 permits since 2000: 11 never finaled.
Of the 11 never-finaled permits, 6 are 3 to 5 years old, 5 are 5 to 10 years old.
This is the city’s permit record, not a license check. It does not show whether the state license is active, bonded or insured. How to read these records
Permits filed each year
How long permits take
Each point is the quarter the permits were filed, for all building permits across San Francisco. A median counts only permits that have finished, so the shaded recent quarters look faster than they will end up: their slow permits have not finished yet. Hover a point for the slowest 10%. Gaps mean fewer than 5 permits. A rise in the issue line is the city’s review backlog, not the contractor. Too few of this contractor’s permits have finished to plot them.
Most recent permits
| Filed | Outcome | Address | Work described on the permit | Declared cost |
|---|---|---|---|---|
| Jul 15, 2021 | Never finaled issued Jan 2022, no final | 978 Oakdale Av | building i: the work on these drawings involves the construction of permanent cantilevered beams & tieback soldier beams with shotcrete lagging will be constructed @ building i. shoring work for future construction under bpa #2016-02229-0745-sDetails
building i: the work on these drawings involves the construction of permanent cantilevered beams & tieback soldier beams with shotcrete lagging will be constructed @ building i. shoring work for future construction under bpa #2016-02229-0745-s | $200,000 |
| Jul 15, 2021 | Never finaled issued Jan 2022, no final | 878 La Salle Av | building n1: the work on thee drawings involves temporary soil nailing will be constructed at building n1. shoring work for future construction bpa #2014-1216-3800-sDetails
building n1: the work on thee drawings involves temporary soil nailing will be constructed at building n1. shoring work for future construction bpa #2014-1216-3800-s | $200,000 |
| Jul 15, 2021 | Never finaled issued Jan 2022, no final | 968 Oakdale Av | building l: the work shown on these drawings involves the construction of permanent cantilevered beams & tieback soldier beams with shotcrete lagging will be constructed at building l. shoring work for future construction uncer bpa #2016-0229-0747-sDetails
building l: the work shown on these drawings involves the construction of permanent cantilevered beams & tieback soldier beams with shotcrete lagging will be constructed at building l. shoring work for future construction uncer bpa #2016-0229-0747-s | $200,000 |
| Jul 15, 2021 | Never finaled issued Jan 2022, no final | 988 Oakdale Av | building e: the work on these drawings involves the construction of temoraray cantilevered beams & tiedback soldier beams with wood lagging. shoring work for future construction under bpa#2016-0229-0780-sDetails
building e: the work on these drawings involves the construction of temoraray cantilevered beams & tiedback soldier beams with wood lagging. shoring work for future construction under bpa#2016-0229-0780-s | $200,000 |
| Jul 15, 2021 | Never finaled issued Jan 2022, no final | 966 Oakdale Av | building n1: the work on these drawings involves construction of temporary cantilevered beams & tiedback soldier beams with wood lagging @ buildg p. shoring work for future construction under bpa#2014-1216-3796-sDetails
building n1: the work on these drawings involves construction of temporary cantilevered beams & tiedback soldier beams with wood lagging @ buildg p. shoring work for future construction under bpa#2014-1216-3796-s | $200,000 |
| Jul 15, 2021 | Never finaled issued Jan 2022, no final | 762 La Salle Av | building o: the work on thee drawings involves temporary soil nailing will be constructed at building o. shoring work for future construction bpa #2014-1216-3806-sDetails
building o: the work on thee drawings involves temporary soil nailing will be constructed at building o. shoring work for future construction bpa #2014-1216-3806-s | $200,000 |
| Sep 12, 2020 | Never finaled issued Aug 2021, no final | 869 La Salle Av | bldg m-temporary shoring - the work shown on these drawings involves the construction of temporary cantilevered beams, and tiebacks soldier beams with wood lagging at building m.shoring work for future construction under pa# 201602179819.**comply w/ maher ord, route to dph**Details
bldg m-temporary shoring - the work shown on these drawings involves the construction of temporary cantilevered beams, and tiebacks soldier beams with wood lagging at building m.shoring work for future construction under pa# 201602179819.**comply w/ maher ord, route to dph** | $657,430 |
| Sep 12, 2020 | Never finaled issued Aug 2021, no final | 879 La Salle Av | bldg j-temporary shoring - the work shown on these drawings involves the construction of temporary cantilevered beams, and tiebacks soldier beams with wood lagging at building j. shoring work for future construction under pa#201602179818.**comply w/ maher ord, route to dph**Details
bldg j-temporary shoring - the work shown on these drawings involves the construction of temporary cantilevered beams, and tiebacks soldier beams with wood lagging at building j. shoring work for future construction under pa#201602179818.**comply w/ maher ord, route to dph** | $150,000 |
| Sep 12, 2020 | Never finaled issued Aug 2021, no final | 889 La Salle Av | bldg f-shoring work for future construction under pa#201602179815the work shown on these drawings involves the construction of temporary cantilevered beams, and tiebacks soldier beams with wood lagging at building f. **comply w/ maher ord, route to dph**Details
bldg f-shoring work for future construction under pa#201602179815the work shown on these drawings involves the construction of temporary cantilevered beams, and tiebacks soldier beams with wood lagging at building f. **comply w/ maher ord, route to dph** | $75,000 |
| Sep 12, 2020 | Never finaled issued Aug 2021, no final | 898 La Salle Av | bldg a-temporary shoring - shoring work for future construction under pa# 201603141951the work shown on these drawings involves the construction of temporary cantilevered beams with wood lagging at building a.**comply w/ maher ord, route to dph**Details
bldg a-temporary shoring - shoring work for future construction under pa# 201603141951the work shown on these drawings involves the construction of temporary cantilevered beams with wood lagging at building a.**comply w/ maher ord, route to dph** | $75,000 |
| Sep 8, 2020 | Never finaled issued Aug 2021, no final | 888 La Salle Av | bldg g-temporary shoring - the work shown on these drawings involves the construction of temporary cantilevered beams with wood lagging at building g. shoring work for future construction under pa# 201603141960.**comply w/ maher ord, route to dph**Details
bldg g-temporary shoring - the work shown on these drawings involves the construction of temporary cantilevered beams with wood lagging at building g. shoring work for future construction under pa# 201603141960.**comply w/ maher ord, route to dph** | $35,000 |