Permits filed each year
How long permits take
Each point is the quarter the permits were filed, for all building permits across San Francisco. A median counts only permits that have finished, so the shaded recent quarters look faster than they will end up: their slow permits have not finished yet. Hover a point for the slowest 10%. Gaps mean fewer than 5 permits. A rise in the issue line is the city’s review backlog, not the contractor.
Most recent permits
| Filed | Outcome | Address | Work described on the permit | Declared cost |
|---|---|---|---|---|
| Sep 10, 2019 | Completed final sign-off Jul 2021 | 3101 Mission St | selective replacement of unit interior items per unit interior replacement schedule. various accessibility upgrades at units and site. bldg mechanical system upgrade, paint all previously painted exterior surfaces, remove and replace membrane roofing atDetails
selective replacement of unit interior items per unit interior replacement schedule. various accessibility upgrades at units and site. bldg mechanical system upgrade, paint all previously painted exterior surfaces, remove and replace membrane roofing at | $2,500,000 |
| May 29, 2019 | Completed final sign-off Dec 2019 | 1000 Tompkins Av | revision to 2018-1210-7904 (original pa) & 2019-0213-2834 (revision to pa 2018-1210-7904) - structural construction system for the new community room, kitchen and accessible restroomsDetails
revision to 2018-1210-7904 (original pa) & 2019-0213-2834 (revision to pa 2018-1210-7904) - structural construction system for the new community room, kitchen and accessible restrooms | |
| Feb 13, 2019 | Completed final sign-off Dec 2019 | 1000 Tompkins Av | ref pa#201812107904; rev to the structural constructon system for the construction of the new community room, kitchen, and accessible restrooms.Details
ref pa#201812107904; rev to the structural constructon system for the construction of the new community room, kitchen, and accessible restrooms. | |
| Dec 10, 2018 | Completed final sign-off Dec 2019 | 1000 Tompkins Av | selected replacement of unit interior items & finishes per unit interior replacement schedule; paint ext surfaces; replacement of e w/h: see units; renovate of e leasing office & laundry; new community rm, kitchen, & accessible restrms; new landscape & play structure & ground finishes @ e courtyard;Details
selected replacement of unit interior items & finishes per unit interior replacement schedule; paint ext surfaces; replacement of e w/h: see units; renovate of e leasing office & laundry; new community rm, kitchen, & accessible restrms; new landscape & play structure & ground finishes @ e courtyard; | $2,900,000 |
| Aug 28, 2015 | Completed final sign-off Nov 2015 | 540 Leavenworth St | revision to 201506229524 for roof deck work. revised path of egress for private deck maher not reqDetails
revision to 201506229524 for roof deck work. revised path of egress for private deck maher not req | |
| Jun 22, 2015 | Completed final sign-off Nov 2015 | 540 Leavenworth St | roof deck for building tenants, private roof deck within view of the back 1/3 of propertyDetails
roof deck for building tenants, private roof deck within view of the back 1/3 of property | $130,000 |
| May 18, 2015 | Expired or cancelled withdrawn Jun 2015 | 540 Leavenworth St | roof deck not visible from streetDetails
roof deck not visible from street | $100,000 |
| May 18, 2015 | Expired or cancelled withdrawn Jun 2015 | 540 Leavenworth St | private roof deck within view of the bacj 1/4 of property. maher naDetails
private roof deck within view of the bacj 1/4 of property. maher na | $30,000 |
| May 13, 2015 | Completed final sign-off Oct 2015 | 1600 Van Ness Av | (n) hydrogen service repair bay, upgrade (e) repair maintenance bay. 550 sf space will include 1-hr wall, 60 min doors, (n) dedicated ventilation & fire suppression for hydrogen detection. adding roof exhaust unit. fire suppression system (high pressure and monitoring system under separate applDetails
(n) hydrogen service repair bay, upgrade (e) repair maintenance bay. 550 sf space will include 1-hr wall, 60 min doors, (n) dedicated ventilation & fire suppression for hydrogen detection. adding roof exhaust unit. fire suppression system (high pressure and monitoring system under separate appl | $41,000 |
| Feb 19, 2015 | Completed final sign-off Oct 2015 | 1600 Van Ness Av | removal of (e) beams, replace with glu-lam beamsDetails
removal of (e) beams, replace with glu-lam beams | $25,000 |
| Dec 16, 2014 | Completed final sign-off Mar 2015 | 1600 Van Ness Av | revision to 201311252751. revisions to finishes, millwork, change in interior storefront unit to window, electrical power to elevator, smoke guard door, smoke detector, power to millwork coffee station, car warning light. electrical work under pa#e201408061712Details
revision to 201311252751. revisions to finishes, millwork, change in interior storefront unit to window, electrical power to elevator, smoke guard door, smoke detector, power to millwork coffee station, car warning light. electrical work under pa#e201408061712 | $9,500 |
| Nov 13, 2014 | Completed final sign-off Mar 2015 | 1600 Van Ness Av | fire escape permit . revision to 2014 0910 6013 - necessary because of (e) conflicts on site w/ building column and sloping side walk. revision entails request to place final land at counter weight at 9'-0" rather than 10'-0"Details
fire escape permit . revision to 2014 0910 6013 - necessary because of (e) conflicts on site w/ building column and sloping side walk. revision entails request to place final land at counter weight at 9'-0" rather than 10'-0" | $3,000 |
| Sep 10, 2014 | Completed final sign-off Mar 2015 | 1600 Van Ness Av | installation of fire escape, replace in kind per reference pa201311252751Details
installation of fire escape, replace in kind per reference pa201311252751 | $47,000 |
| Feb 25, 2014 | Completed final sign-off Nov 2015 | 540 Leavenworth St | remove interior non-structural wall. additon of new non-structural walls & ceiling. new kitchens & bathrooms in all units. new laundry machines in 10 units. infill 5 (e) vent shafts with new floor framing. mep on separate permit, no exterior work. compliance with ordinance #155-13 not requird.Details
remove interior non-structural wall. additon of new non-structural walls & ceiling. new kitchens & bathrooms in all units. new laundry machines in 10 units. infill 5 (e) vent shafts with new floor framing. mep on separate permit, no exterior work. compliance with ordinance #155-13 not requird. | $1,800,000 |
| Nov 25, 2013 | Completed final sign-off Mar 2015 | 1600 Van Ness Av | ti @(e) bldg demolition of structure @1/f columns and addition of (n) long span beams; (n) elevator, update (e) toilets, (n) toilet rm, conference/breakrm, locker area, parts storage rm on 3rd; (n) flooring on 2nd, (n) light fixtures all floors; (n) pg & e service in basement and (n) fire escapeDetails
ti @(e) bldg demolition of structure @1/f columns and addition of (n) long span beams; (n) elevator, update (e) toilets, (n) toilet rm, conference/breakrm, locker area, parts storage rm on 3rd; (n) flooring on 2nd, (n) light fixtures all floors; (n) pg & e service in basement and (n) fire escape | $1,200,000 |
| Nov 27, 2012 | Completed final sign-off Feb 2013 | 15 Marina Bl | revision to pa#2012-07-03-4006. relocate janitor's closet.Details
revision to pa#2012-07-03-4006. relocate janitor's closet. | |
| Jul 3, 2012 | Completed final sign-off Feb 2013 | 15 Marina Bl | install 2nd consultation room & relocate janitors closet.Details
install 2nd consultation room & relocate janitors closet. | $45,000 |
| Jun 18, 2012 | Completed final sign-off Oct 2012 | 1335 Webster St | install 2nd consultation room in pharmacyDetails
install 2nd consultation room in pharmacy | $25,000 |
| May 8, 2012 | Completed final sign-off Aug 2012 | 581 Market St | revision to appl #2012.03.16.6250 & 2011.11.23.9520: marked in delta 1 and 2:includes non-passenger vertical reciprocating lift conveyor to be installed by manufacturer; close-in openings to shaft on all floors; infill of (e) hoistway pit to a depth of 7'; no exterior or other work.Details
revision to appl #2012.03.16.6250 & 2011.11.23.9520: marked in delta 1 and 2:includes non-passenger vertical reciprocating lift conveyor to be installed by manufacturer; close-in openings to shaft on all floors; infill of (e) hoistway pit to a depth of 7'; no exterior or other work. | $110,000 |
| Jan 9, 2012 | Completed final sign-off Apr 2012 | 15 Marina Bl | revision to app#201106208501. these plans are for structural changes/cut hole. in concrete wall to add door way.Details
revision to app#201106208501. these plans are for structural changes/cut hole. in concrete wall to add door way. | $500 |
| Jun 20, 2011 | Completed final sign-off Apr 2012 | 15 Marina Bl | safeway. relocation of pharmacy toilet room, expansion of pharmacy to contain a consulting room and customer waiting area. relocation of hung soffit wall. mep under separate permit.Details
safeway. relocation of pharmacy toilet room, expansion of pharmacy to contain a consulting room and customer waiting area. relocation of hung soffit wall. mep under separate permit. | $100,000 |
| Jun 20, 2011 | Completed final sign-off Feb 2012 | 1335 Webster St | safeway. relocation of 1 toilet rm, construction of a new toilet rm, consulting rm and customer waiting area. mep under separate permit.Details
safeway. relocation of 1 toilet rm, construction of a new toilet rm, consulting rm and customer waiting area. mep under separate permit. | $100,000 |
| Sep 17, 2010 | Completed final sign-off Nov 2012 | 3800 Geary Bl | voluntary seismic strengthening. demo of interior and exterior finishes, replace all int and ext finishes, plus mech, elec, plbg, windows and doors. new roof, new urinal and toilet and seeking leed platinum certificationDetails
voluntary seismic strengthening. demo of interior and exterior finishes, replace all int and ext finishes, plus mech, elec, plbg, windows and doors. new roof, new urinal and toilet and seeking leed platinum certification | $925,000 |
| Dec 3, 2009 | Completed final sign-off May 2010 | 2300 16th St | remove (e) case in deli; replace w/new hot/cold chicken caseDetails
remove (e) case in deli; replace w/new hot/cold chicken case | $6,000 |
| Dec 3, 2009 | Completed final sign-off May 2010 | 1335 Webster St | remove (e) case in deli; replace w/new hot/cold chicken caseDetails
remove (e) case in deli; replace w/new hot/cold chicken case | $6,000 |
| Apr 21, 2009 | Expired or cancelled expired Nov 2012 | 645 05th St | remodel of the (e) locker rooms & shower area. also upgrading mechanical, electrical & plumbing; reconfigure egress path and exit corridors; also occupant load verification for p-142 permit.Details
remodel of the (e) locker rooms & shower area. also upgrading mechanical, electrical & plumbing; reconfigure egress path and exit corridors; also occupant load verification for p-142 permit. | $1,000,000 |
| Apr 29, 2003 | Completed final sign-off Jun 2003 | 140 El Camino Del Mar | remove & replace (e) windows with new dual pane low-e. aluminum clad wood windows, total 45 windowsDetails
remove & replace (e) windows with new dual pane low-e. aluminum clad wood windows, total 45 windows | $50,000 |
| Feb 25, 2003 | Completed final sign-off Mar 2003 | 49 Gold Mine Dr | renew:200109057768 and 200208194369 for finla inspection only no work under this permitDetails
renew:200109057768 and 200208194369 for finla inspection only no work under this permit | |
| Aug 19, 2002 | Completed final sign-off Jan 2004 | 49 Gold Mine Dr | amend original appn. 200103285472 & rev. 200111274205 for shear wall restritutionDetails
amend original appn. 200103285472 & rev. 200111274205 for shear wall restritution | $1,091,134 |
| Jun 7, 2002 | Completed final sign-off Dec 2002 | 3132 Clement St | revision to 200105088680 canopy and stairDetails
revision to 200105088680 canopy and stair | $20,000 |
| Nov 29, 2001 | Expired or cancelled expired Mar 2003 | 49 Gold Mine Dr | addendum to 200103285472 replace 51 upper decks repair all lower decks in kindDetails
addendum to 200103285472 replace 51 upper decks repair all lower decks in kind | $126,000 |
| Sep 6, 2001 | Expired or cancelled expired Mar 2003 | 49 Gold Mine Dr | revision to 200103285472Details
revision to 200103285472 | |
| Mar 28, 2001 | Completed final sign-off Aug 2003 | 49 Gold Mine Dr | replace (e)tng roofing sys. w/new includ gutters & down spouts, (e) t-111 & plywd siding w/new handiDetails
replace (e)tng roofing sys. w/new includ gutters & down spouts, (e) t-111 & plywd siding w/new handi | $2,000,000 |