138 permits since 2000: 94 completed, 28 never finaled, 16 expired or cancelled.
Of the 28 never-finaled permits, 2 are 3 to 5 years old, 17 are 5 to 10 years old, 9 are over 10 years old.
This is the city’s permit record, not a license check. It does not show whether the state license is active, bonded or insured. How to read these records
Permits filed each year
How long permits take
Each point is the quarter the permits were filed, for all building permits across San Francisco. A median counts only permits that have finished, so the shaded recent quarters look faster than they will end up: their slow permits have not finished yet. Hover a point for the slowest 10%. Gaps mean fewer than 5 permits. A rise in the issue line is the city’s review backlog, not the contractor.
Most recent permits
Showing the 100 most recent of 138.
| Filed | Outcome | Address | Work described on the permit | Declared cost |
|---|---|---|---|---|
| Oct 27, 2021 | Never finaled issued Nov 2021, no final | 10 Innes Ct | temp change of occ/use in (e) dwelling unit 104 for a temp on-site leasing office. (e) r-2 in unit shall change to a b occupancy for a duration of 12-16 months and revert back to original occupancy/use after this durationg has ended.Details
temp change of occ/use in (e) dwelling unit 104 for a temp on-site leasing office. (e) r-2 in unit shall change to a b occupancy for a duration of 12-16 months and revert back to original occupancy/use after this durationg has ended. | |
| Aug 11, 2021 | Completed final sign-off Nov 2024 | 52 Kirkwood Av | revision to pa# 202002134438 s3. addendum 3 arch/mep. changes include: 1.deletion of fire sprinklers at pavilion building (bldg 4).Details
revision to pa# 202002134438 s3. addendum 3 arch/mep. changes include: 1.deletion of fire sprinklers at pavilion building (bldg 4). | |
| May 11, 2021 | Never finaled issued Sep 2021, no final | 879 La Salle Av | building j: revision to previously approved structural addendum pa@ 2016-0217-9818/s-1. work includes adjstments to pt and framing plan, updated wall schedules and other details.Details
building j: revision to previously approved structural addendum pa@ 2016-0217-9818/s-1. work includes adjstments to pt and framing plan, updated wall schedules and other details. | $15,000 |
| Mar 26, 2021 | Never finaled issued Nov 2021, no final | 879 La Salle Av | plumbing only-stormwater control system for bpa#201602179818Details
plumbing only-stormwater control system for bpa#201602179818 | $10,000 |
| Nov 19, 2020 | Never finaled issued Jul 2021, no final | 899 La Salle Av | shoring work for future construction under pa# 201602129567the work shown on these drawings involves the construction of temporary cantilevered beams, and tiebacks soldier beams with wood lagging at building bDetails
shoring work for future construction under pa# 201602129567the work shown on these drawings involves the construction of temporary cantilevered beams, and tiebacks soldier beams with wood lagging at building b | $75,000 |
| Nov 19, 2020 | Never finaled issued May 2021, no final | 869 La Salle Av | plumbing only: alternate water plumbing system & cistern systems systems for future work under 2016-0217-9819.Details
plumbing only: alternate water plumbing system & cistern systems systems for future work under 2016-0217-9819. | $20,000 |
| Nov 2, 2020 | Never finaled issued Mar 2021, no final | 898 La Salle Av | mayor dir# 17-02. plumbing only: alternate water plumbing system & cistern systems systems for future work under pa# 201603141951-s. ** maher: n/a **Details
mayor dir# 17-02. plumbing only: alternate water plumbing system & cistern systems systems for future work under pa# 201603141951-s. ** maher: n/a ** | $10,000 |
| Nov 2, 2020 | Never finaled issued Mar 2021, no final | 888 La Salle Av | mayor dir# 17-02. plumbing only: alternate water plumbing system & cistern systems systems for future work under pa# 201603141960-s. ** maher: n/a **Details
mayor dir# 17-02. plumbing only: alternate water plumbing system & cistern systems systems for future work under pa# 201603141960-s. ** maher: n/a ** | $10,000 |
| Oct 9, 2020 | Never finaled issued Mar 2021, no final | 52 Kirkwood Av | priority processing, mayor dir 17-02. stormwater system permit for future construction of buildings at 52 kirkwood under pa# 2019-1003-3486 & 2020-0213-4438.Details
priority processing, mayor dir 17-02. stormwater system permit for future construction of buildings at 52 kirkwood under pa# 2019-1003-3486 & 2020-0213-4438. | $50,000 |
| Feb 13, 2020 | Completed final sign-off Apr 2025 | 52 Kirkwood Av | mayor dir# 17-02. to erect a one story type five construction fitness center. ** maher: yes, route to dph **Details
mayor dir# 17-02. to erect a one story type five construction fitness center. ** maher: yes, route to dph ** | $7,500 |
| Oct 3, 2019 | Completed final sign-off Apr 2025 | 52 Kirkwood Av | mayor dir# 17-02. to erect 4 stories, no basement, type i-a & type v-a, 77 units residential condominiums with mixed use building. (r-2,b,a-3,s-2) ** maher: yes, route to dph **Details
mayor dir# 17-02. to erect 4 stories, no basement, type i-a & type v-a, 77 units residential condominiums with mixed use building. (r-2,b,a-3,s-2) ** maher: yes, route to dph ** | $25,378,500 |
| Apr 14, 2016 | Never finaled issued Aug 2021, no final | 989 Oakdale Av | (bldg d)to erect 3 stories of 12 dwelling with parkingDetails
(bldg d)to erect 3 stories of 12 dwelling with parking | $4,800,000 |
| Mar 29, 2016 | Never finaled issued Aug 2021, no final | 969 Oakdale Av | bldg k-1. to erect 3 stories, no basement, type v-a, 15 units residential building. deck connect to bldg k-2. ** maher: n/a **Details
bldg k-1. to erect 3 stories, no basement, type v-a, 15 units residential building. deck connect to bldg k-2. ** maher: n/a ** | $4,500,000 |
| Mar 29, 2016 | Never finaled issued Aug 2021, no final | 969 Oakdale Av | bldg k-2. to erect 3 stories, no basement, type v-a, 11 units residential building. deck connect from bldg k-1. ** maher: n/a **Details
bldg k-2. to erect 3 stories, no basement, type v-a, 11 units residential building. deck connect from bldg k-1. ** maher: n/a ** | $4,000,000 |
| Mar 14, 2016 | Never finaled issued Sep 2017, no final | 888 La Salle Av | aka address; 888 la salle ave. to erect 4 story, 1 basement, type ia / va, 34 units residential building. ** maher: n/a **Details
aka address; 888 la salle ave. to erect 4 story, 1 basement, type ia / va, 34 units residential building. ** maher: n/a ** | $9,900,000 |
| Feb 29, 2016 | Never finaled issued Aug 2021, no final | 988 Oakdale Av | 3/11/20: ars propose address: aka address 988 oakdale ave. wf to erect a type 1a, 4 story residential bldg w/ 22 units. aka address:Details
3/11/20: ars propose address: aka address 988 oakdale ave. wf to erect a type 1a, 4 story residential bldg w/ 22 units. aka address: | $8,900,000 |
| Feb 29, 2016 | Never finaled issued Aug 2021, no final | 968 Oakdale Av | phase 2b, building l. to erect 3 stories, no basement, 15 units residential building. dph / article-31 applies.Details
phase 2b, building l. to erect 3 stories, no basement, 15 units residential building. dph / article-31 applies. | $4,900,000 |
| Feb 29, 2016 | Never finaled issued Aug 2021, no final | 978 Oakdale Av | phase 2b, building i. to erect 3 stories, no basement, 15 units residential building. ** maher: n/a **Details
phase 2b, building i. to erect 3 stories, no basement, 15 units residential building. ** maher: n/a ** | $4,900,000 |
| Feb 17, 2016 | Never finaled issued Apr 2017, no final | 869 La Salle Av | phase 2a, building# m. to erect 4 stories, 1 basement, 40 units residential building. type v-a over type i-a. ** maher: n/a **Details
phase 2a, building# m. to erect 4 stories, 1 basement, 40 units residential building. type v-a over type i-a. ** maher: n/a ** | $11,300,000 |
| Feb 17, 2016 | Never finaled issued Apr 2017, no final | 889 La Salle Av | phase 2a, building# f. to erect 4 stories, 1 basement, 40 units residential building. ** maher: n/a **Details
phase 2a, building# f. to erect 4 stories, 1 basement, 40 units residential building. ** maher: n/a ** | $11,300,000 |
| Feb 17, 2016 | Never finaled issued Apr 2017, no final | 879 La Salle Av | phase 2a, building# j. to erect 4 stories, 1 basement, type va over ia, 40 units residential building with car stackers, 1500 gpm fire pump ** maher: n/a **Details
phase 2a, building# j. to erect 4 stories, 1 basement, type va over ia, 40 units residential building with car stackers, 1500 gpm fire pump ** maher: n/a ** | $11,300,000 |
| Feb 12, 2016 | Never finaled issued May 2017, no final | 899 La Salle Av | phase ii-a building b. erect 4 stories of 44 residential unitsDetails
phase ii-a building b. erect 4 stories of 44 residential units | $16,200,000 |
| Dec 16, 2014 | Never finaled issued Sep 2015, no final | 878 La Salle Av | bldg 1: construct (n) 4-story, 18 units residential over garage.Details
bldg 1: construct (n) 4-story, 18 units residential over garage. | $7,000,000 |
| Jun 13, 2014 | Never finaled issued Jun 2014, no final | 0 Galvez Av | to obtain final inspection for work approved under pa # 200509163130. all work is complete.Details
to obtain final inspection for work approved under pa # 200509163130. all work is complete. | $88,516 |
| Jun 22, 2011 | Never finaled issued Jun 2011, no final | 0 Galvez Av | to obtain final inspection for work approved under pa (200509163130) 200810013151; all work has been completedDetails
to obtain final inspection for work approved under pa (200509163130) 200810013151; all work has been completed | |
| Jun 22, 2011 | Completed final sign-off Jun 2012 | 0 Innes Av | to obtain final inspection for work approved under pa 200611107383; all work has been completedDetails
to obtain final inspection for work approved under pa 200611107383; all work has been completed | |
| Jun 22, 2011 | Completed final sign-off Jun 2012 | 0 Innes Av | to obtain final inspection for work approved under pa(200601263179) 200803066551; all work has been completedDetails
to obtain final inspection for work approved under pa(200601263179) 200803066551; all work has been completed | |
| Jul 13, 2010 | Completed final sign-off Jun 2012 | 0 Oakdale Av | to obtain final inspection for work approved under appl# 200803066463. all work has been completed.Details
to obtain final inspection for work approved under appl# 200803066463. all work has been completed. | |
| Jul 13, 2010 | Completed final sign-off Jun 2012 | 0 Galvez Av | to obtain final inspection for work approved under appl# 200512059530. all work has been completed.Details
to obtain final inspection for work approved under appl# 200512059530. all work has been completed. | |
| Jul 13, 2010 | Completed final sign-off Jun 2012 | 0 Galvez Av | to obtain final inspection for work approved under appl# 200505233211. all work has been completed.Details
to obtain final inspection for work approved under appl# 200505233211. all work has been completed. | |
| Jul 13, 2010 | Completed final sign-off Jun 2012 | 0 Oakdale Av | to obtain final inspection for work approved under appl# 200601263172. all work has been completed.Details
to obtain final inspection for work approved under appl# 200601263172. all work has been completed. | |
| Jul 13, 2010 | Completed final sign-off Jun 2012 | 0 Innes Av | to obtain final inspection for work approved under appl# 200601263179. all work has been completed.Details
to obtain final inspection for work approved under appl# 200601263179. all work has been completed. | |
| Jul 13, 2010 | Expired or cancelled expired Mar 2013 | 0 Galvez Av | to obtain final inspection for work approved under appl# 200509163130. all work has been completed.Details
to obtain final inspection for work approved under appl# 200509163130. all work has been completed. | |
| Jul 13, 2010 | Completed final sign-off Jun 2012 | 0 Galvez Av | to obtain final inspection for work approved under appl# 200512059525. all work has been completed.Details
to obtain final inspection for work approved under appl# 200512059525. all work has been completed. | |
| Jul 13, 2010 | Completed final sign-off Jun 2012 | 0 Oakdale Av | to obtain final inspection for work approved under appl# 200607277775. all work has been completed.Details
to obtain final inspection for work approved under appl# 200607277775. all work has been completed. | |
| Jul 13, 2010 | Completed final sign-off Jun 2012 | 0 Innes Av | to obtain final inspection for work approved under appl# 200607277771. all work has been completed.Details
to obtain final inspection for work approved under appl# 200607277771. all work has been completed. | |
| Jul 13, 2010 | Completed final sign-off Jun 2012 | 0 Donahue St | to obtain final inspection for work approved under appl# 200604128829. all work has been completed.Details
to obtain final inspection for work approved under appl# 200604128829. all work has been completed. | |
| Dec 2, 2008 | Expired or cancelled expired Jul 2010 | 0 Donahue St | to obtain final inspection for work approved under pa#2006-0412-8829. all work has been completed.Details
to obtain final inspection for work approved under pa#2006-0412-8829. all work has been completed. | |
| Oct 30, 2008 | Completed final sign-off Nov 2008 | 0 Innes Av | to obtain final inspection for work approved under 200603307905. all work has been completed.Details
to obtain final inspection for work approved under 200603307905. all work has been completed. | |
| Oct 30, 2008 | Expired or cancelled expired Sep 2010 | 0 Galvez Av | to obtain final inspection for work approved under 200505233211. all work has been completed.Details
to obtain final inspection for work approved under 200505233211. all work has been completed. | |
| Oct 30, 2008 | Completed final sign-off Nov 2008 | 0 Innes Av | to obtain final inspection for work approved under 200602104360. all work has been completed.Details
to obtain final inspection for work approved under 200602104360. all work has been completed. | |
| Oct 30, 2008 | Completed final sign-off Nov 2008 | 0 Donahue St | to obtain final inspection for work approved under 200605161684. all work has been completed.Details
to obtain final inspection for work approved under 200605161684. all work has been completed. | |
| Oct 28, 2008 | Expired or cancelled expired Jul 2010 | 0 Innes Av | to obtain final inspection for work approved under 200601263179. all work has been completed.Details
to obtain final inspection for work approved under 200601263179. all work has been completed. | |
| Oct 28, 2008 | Expired or cancelled expired Jul 2010 | 0 Donahue St | to obtain final inspection for work approved under 200710094870. all work has been completedDetails
to obtain final inspection for work approved under 200710094870. all work has been completed | |
| Oct 28, 2008 | Completed final sign-off Nov 2008 | 0 Innes Av | to obtain final inspection for work approved under 200602275542. all work has been completed.Details
to obtain final inspection for work approved under 200602275542. all work has been completed. | |
| Oct 28, 2008 | Completed final sign-off Nov 2008 | 0 Innes Av | to obtain final inspection for work approved under ap 200608159566. all work has been completedDetails
to obtain final inspection for work approved under ap 200608159566. all work has been completed | |
| Oct 28, 2008 | Expired or cancelled expired Jul 2010 | 0 Innes Av | to obtain final inspection for work approved under app. 200607277771. all work has been completed.Details
to obtain final inspection for work approved under app. 200607277771. all work has been completed. | |
| Oct 1, 2008 | Expired or cancelled expired Sep 2010 | 0 Galvez Av | to obtain final inspection for work approved under app#200512059525. all work has been completed.Details
to obtain final inspection for work approved under app#200512059525. all work has been completed. | |
| Oct 1, 2008 | Expired or cancelled expired Jul 2010 | 0 Oakdale Av | to obtain final inspection for work approved under app#20060727775. all work has been completed.Details
to obtain final inspection for work approved under app#20060727775. all work has been completed. | |
| Oct 1, 2008 | Completed final sign-off Nov 2008 | 0 Innes Av | to obtain final inspection for work approved under app#200707116534. all work has been completed.Details
to obtain final inspection for work approved under app#200707116534. all work has been completed. | |
| Oct 1, 2008 | Expired or cancelled expired Sep 2010 | 0 Galvez Av | to obtain final inspection for work approved under app#200512059530. all work has been completed.Details
to obtain final inspection for work approved under app#200512059530. all work has been completed. | |
| Oct 1, 2008 | Completed final sign-off Nov 2008 | 0 Oakdale Av | to complete work and obtain final inspection on app#200707116532 98% of work has been completed.Details
to complete work and obtain final inspection on app#200707116532 98% of work has been completed. | $1,500 |
| Oct 1, 2008 | Completed final sign-off Nov 2008 | 0 Galvez Av | to obtain final inspection for work approved under app#200605161678. all work has been completed.Details
to obtain final inspection for work approved under app#200605161678. all work has been completed. | |
| Oct 1, 2008 | Completed final sign-off Oct 2008 | 0 Oakdale Av | to obtain final inspection for work approved under app#200608159560. all work has been completed.Details
to obtain final inspection for work approved under app#200608159560. all work has been completed. | |
| Oct 1, 2008 | Completed final sign-off Oct 2008 | 0 Oakdale Av | to obtain final inspection for work approved under pa#200602104356 all work has been completed.Details
to obtain final inspection for work approved under pa#200602104356 all work has been completed. | |
| Oct 1, 2008 | Completed final sign-off Oct 2008 | 0 Oakdale Av | to obtain final inspection for work approved under app#200603307892. all work has been completed.Details
to obtain final inspection for work approved under app#200603307892. all work has been completed. | |
| Oct 1, 2008 | Completed final sign-off Oct 2008 | 0 Oakdale Av | to obtain final inspection for work approved under app#200602275541. all work has been completed.Details
to obtain final inspection for work approved under app#200602275541. all work has been completed. | |
| Oct 1, 2008 | Expired or cancelled expired Sep 2010 | 0 Galvez Av | to obtain final inspection for work approved under app#200509163130. all work has been completed.Details
to obtain final inspection for work approved under app#200509163130. all work has been completed. | |
| Mar 6, 2008 | Never finaled issued Mar 2008, no final | 0 Oakdale Av | revision to pa# 2006/01/26/3172, 2006/02/10/4356, 2006/02/27/5541, 2006/03/30/7892 and 2006/07/27/7775, grading at "hillside parcel a'", to provide additional documentation and minor drainage revisionsDetails
revision to pa# 2006/01/26/3172, 2006/02/10/4356, 2006/02/27/5541, 2006/03/30/7892 and 2006/07/27/7775, grading at "hillside parcel a'", to provide additional documentation and minor drainage revisions | $10,000 |
| Mar 6, 2008 | Never finaled issued Mar 2008, no final | 0 Innes Av | revision to app#2006/01/26/3179 w/ revision app#200602104360,200602275542,200603307905 & 200607277771 to provide additional doc. & increase in scope of grading for lot @ south corner of colman st & inness ct intersection & other minor drainage revisions.Details
revision to app#2006/01/26/3179 w/ revision app#200602104360,200602275542,200603307905 & 200607277771 to provide additional doc. & increase in scope of grading for lot @ south corner of colman st & inness ct intersection & other minor drainage revisions. | $60,000 |
| Oct 9, 2007 | Never finaled issued Oct 2007, no final | 0 Donahue St | to demolish 2 stories of a restaurantDetails
to demolish 2 stories of a restaurant | |
| Jul 11, 2007 | Completed final sign-off Nov 2008 | 0 Innes Av | hunters point shipyard parcel a' hilltop: installation of subdrain sump pump, and dispensing riprap, and peripherals.Details
hunters point shipyard parcel a' hilltop: installation of subdrain sump pump, and dispensing riprap, and peripherals. | $71,000 |
| Jul 11, 2007 | Completed final sign-off Nov 2008 | 0 Oakdale Av | hunter point parcel a' hillside: installation of subdrain drainage sump pump and dispensing riprap and peripherals.Details
hunter point parcel a' hillside: installation of subdrain drainage sump pump and dispensing riprap and peripherals. | $90,500 |
| Nov 10, 2006 | Expired or cancelled expired Aug 2011 | 0 Innes Av | temporary shoring to support & locally revise site grading & slide mitigation permit pa# 200601263179 & pa# 200607277771. shoring soldier piles (19 total) along stretch of 144 ft. will remain underground at work completion.Details
temporary shoring to support & locally revise site grading & slide mitigation permit pa# 200601263179 & pa# 200607277771. shoring soldier piles (19 total) along stretch of 144 ft. will remain underground at work completion. | $370,000 |
| Aug 15, 2006 | Completed final sign-off Oct 2008 | 0 Oakdale Av | this is a revison permit application to add peer review approval from geotech. engineer to original permit application with revision p 20060123172,200602104356, 200602275541, 200603307892 and 20607277775.Details
this is a revison permit application to add peer review approval from geotech. engineer to original permit application with revision p 20060123172,200602104356, 200602275541, 200603307892 and 20607277775. | |
| Aug 15, 2006 | Completed final sign-off Nov 2008 | 0 Innes Av | this is a revision permit application to add per review dapproval from geotech. engineer to original permit application w/revisons 200601263179 500602101360 200602275542 2006033107905 & 200607277771Details
this is a revision permit application to add per review dapproval from geotech. engineer to original permit application w/revisons 200601263179 500602101360 200602275542 2006033107905 & 200607277771 | |
| Jul 27, 2006 | Never finaled issued Jul 2006, no final | 0 Innes Av | revision to original grading permit 200601263179, with revision permit apps 200602104360,200602275542, 200603307905 to provide additonal documentation and increase workscopes in keystone retaining wallsDetails
revision to original grading permit 200601263179, with revision permit apps 200602104360,200602275542, 200603307905 to provide additonal documentation and increase workscopes in keystone retaining walls | $331,000 |
| Jul 27, 2006 | Never finaled issued Jul 2006, no final | 0 Oakdale Av | revision to original grading app 200601263172, with revision apps 200602104356, 200602275541, 200603307892 to provide additional documentation and increase workscope in keystone retaining walls and drill pier shoring wallsDetails
revision to original grading app 200601263172, with revision apps 200602104356, 200602275541, 200603307892 to provide additional documentation and increase workscope in keystone retaining walls and drill pier shoring walls | $331,000 |
| May 16, 2006 | Completed final sign-off Nov 2008 | 0 Donahue St | grading & fillingDetails
grading & filling | |
| May 16, 2006 | Completed final sign-off Nov 2008 | 0 Galvez Av | rev. to pa#2005/09/16/3130 to reduce the scope of work from original two sewer storage tanks to become a single sewer storage tank installation, and to change from a double layer tank to a single layout tankDetails
rev. to pa#2005/09/16/3130 to reduce the scope of work from original two sewer storage tanks to become a single sewer storage tank installation, and to change from a double layer tank to a single layout tank | $36,290 |
| Apr 12, 2006 | Expired or cancelled expired Aug 2007 | 0 Donahue St | rev 200604078536.orig scope of work-install temporary sewage storage tank sys on private property per attached plans.(duration of 2 yrs)above grd with concrete pad.rev in this pa to chg tank with similar dimensions to 6500 gallon poly tank by barertanks.(hunters point subdivision parcel a hilltop).Details
rev 200604078536.orig scope of work-install temporary sewage storage tank sys on private property per attached plans.(duration of 2 yrs)above grd with concrete pad.rev in this pa to chg tank with similar dimensions to 6500 gallon poly tank by barertanks.(hunters point subdivision parcel a hilltop). | |
| Apr 7, 2006 | Completed final sign-off Aug 2006 | 0 Donahue St | install temporary sewage storage tank, system on private property per attached plans. duration of 2 years above ground with concrete pad. hunters point subdivisiion parcel a hilltopDetails
install temporary sewage storage tank, system on private property per attached plans. duration of 2 years above ground with concrete pad. hunters point subdivisiion parcel a hilltop | $35,000 |
| Feb 27, 2006 | Completed final sign-off Nov 2008 | 0 Innes Av | revision to org.pa3200601263179 & 3200602104360 to: revise permit plan per final peer reviewers comments as required by org. permit. request and document an extension request for an additional 30 days fromthe issuance date of this permit to previde cal/ohsa safety permit for the construction of retaDetails
revision to org.pa3200601263179 & 3200602104360 to: revise permit plan per final peer reviewers comments as required by org. permit. request and document an extension request for an additional 30 days fromthe issuance date of this permit to previde cal/ohsa safety permit for the construction of reta | |
| Feb 27, 2006 | Completed final sign-off Oct 2008 | 0 Oakdale Av | rev.to appl#200601263172 & 200602104356 to:revise plan per final peer reviewer's comments as required by original permit. request & documents an extension request for an additional 30 days from the issuance date of this permit to provide cal/ohsa safety permit for the construction of retaining wallDetails
rev.to appl#200601263172 & 200602104356 to:revise plan per final peer reviewer's comments as required by original permit. request & documents an extension request for an additional 30 days from the issuance date of this permit to provide cal/ohsa safety permit for the construction of retaining wall | |
| Feb 10, 2006 | Completed final sign-off Oct 2008 | 0 Oakdale Av | revision pa#200601263172 to ducument an extension request of the dealine to tile revision permit to document changes needed per review comments from peer review panel and dbi and to provide cal/ohsa safety permit for construction of retaining wall over 35 feet. the extension of deadline is increasedDetails
revision pa#200601263172 to ducument an extension request of the dealine to tile revision permit to document changes needed per review comments from peer review panel and dbi and to provide cal/ohsa safety permit for construction of retaining wall over 35 feet. the extension of deadline is increased | |
| Feb 10, 2006 | Completed final sign-off Nov 2008 | 0 Innes Av | revision pa#200601263179 tro document an extension request of the deadline to file revision permit to document changes needed per review cmments from peer review panel and dbi, and to provide cal/ohsa safety permit for the construciton of retaining wall over 35 feet. the extension of deadline is incDetails
revision pa#200601263179 tro document an extension request of the deadline to file revision permit to document changes needed per review cmments from peer review panel and dbi, and to provide cal/ohsa safety permit for the construciton of retaining wall over 35 feet. the extension of deadline is inc | |
| Jan 26, 2006 | Never finaled issued Jan 2006, no final | 0 Oakdale Av | grading gradingDetails
grading grading | |
| Jan 26, 2006 | Expired or cancelled expired Aug 2011 | 0 Innes Av | mass grading, with cut and fill, including landslide repair and a retaining wall per plan. note conditions of approval on plan, file revision permit with peer review panel approval within 15 days.Details
mass grading, with cut and fill, including landslide repair and a retaining wall per plan. note conditions of approval on plan, file revision permit with peer review panel approval within 15 days. | |
| Dec 5, 2005 | Expired or cancelled expired Mar 2013 | 0 Galvez Av | removal of contaminated soul & replace with clean fill for approx total 6800 sq. ft of site from approx 6 inches to 1 foot depth at various locations as noted on plan.Details
removal of contaminated soul & replace with clean fill for approx total 6800 sq. ft of site from approx 6 inches to 1 foot depth at various locations as noted on plan. | |
| Sep 16, 2005 | Expired or cancelled expired Aug 2011 | 0 Galvez Av | install temporary sewage pumping & storage system on private property per attached plans. (partialDetails
install temporary sewage pumping & storage system on private property per attached plans. (partial | $88,516 |
| Jun 30, 2005 | Completed final sign-off Oct 2005 | 0 Kirkwood Av | to demolish 1 story, single family dwelling.Details
to demolish 1 story, single family dwelling. | |
| Jun 30, 2005 | Completed final sign-off Oct 2005 | 0 Jerrold Av | to demolish 1 story, single family dwelling.Details
to demolish 1 story, single family dwelling. | |
| Jun 30, 2005 | Completed final sign-off Oct 2005 | 0 Jerrold Av | to demolish 1 story, single family dwelling.Details
to demolish 1 story, single family dwelling. | |
| Jun 30, 2005 | Completed final sign-off Oct 2005 | 0 Hudson Av | to demolish 1 story, single family dwelling.Details
to demolish 1 story, single family dwelling. | |
| Jun 30, 2005 | Completed final sign-off Oct 2005 | 0 Kirkwood Av | to demolish 1 story single family dwelling.Details
to demolish 1 story single family dwelling. | |
| Jun 30, 2005 | Completed final sign-off Oct 2005 | 0 Innes Av | to demolish 2 stories, single family dwelling.Details
to demolish 2 stories, single family dwelling. | |
| Jun 30, 2005 | Completed final sign-off Dec 2005 | 0 Donahue St | to demolish 1 story electric substation.Details
to demolish 1 story electric substation. | |
| Jun 30, 2005 | Completed final sign-off Oct 2005 | 0 Innes Av | to demolish 1 story, single family dwelling.Details
to demolish 1 story, single family dwelling. | |
| Jun 30, 2005 | Completed final sign-off Oct 2005 | 0 Jerrold Av | to demolish 1 story, single family dwelling.Details
to demolish 1 story, single family dwelling. | |
| Jun 30, 2005 | Completed final sign-off Oct 2005 | 0 Innes Av | to demolish 1 story, single family dwelling.Details
to demolish 1 story, single family dwelling. | |
| Jun 30, 2005 | Completed final sign-off Oct 2005 | 0 Innes Av | to demolish 1 story, single family dwelling.Details
to demolish 1 story, single family dwelling. | |
| Jun 30, 2005 | Completed final sign-off Oct 2005 | 0 Hudson Av | to demolish 1 story, single family dwelling.Details
to demolish 1 story, single family dwelling. | |
| Jun 30, 2005 | Completed final sign-off Oct 2005 | 0 Innes Av | to demolish 1 story, single family dwelling.Details
to demolish 1 story, single family dwelling. | |
| Jun 30, 2005 | Completed final sign-off Oct 2005 | 0 Hudson Av | to demolish 1 story, single family dwelling.Details
to demolish 1 story, single family dwelling. | |
| Jun 30, 2005 | Completed final sign-off Oct 2005 | 0 Hudson Av | to demolish 1 story, single family dwelling.Details
to demolish 1 story, single family dwelling. | |
| Jun 30, 2005 | Completed final sign-off Dec 2005 | 0 Coleman St | to demolish 1 story,water tank.Details
to demolish 1 story,water tank. | |
| Jun 30, 2005 | Completed final sign-off Dec 2005 | 0 Kirkwood Av | to demolish 1 story, ammo bunker.Details
to demolish 1 story, ammo bunker. | |
| Jun 30, 2005 | Completed final sign-off Oct 2005 | 0 Innes Av | to demolish 1 story, single family dwelling.Details
to demolish 1 story, single family dwelling. | |
| Jun 30, 2005 | Completed final sign-off Oct 2005 | 0 Hudson Av | to demolish 1 story single family dwelling.Details
to demolish 1 story single family dwelling. | |
| Jun 30, 2005 | Completed final sign-off Oct 2005 | 0 Innes Av | to demolish 1 story, single family dwelling.Details
to demolish 1 story, single family dwelling. |