Kendall S Miller Construction
- Based in
- Nampa
- On San Francisco permits
- May 2016 to May 2022
- Last 24 months
- 0 permits filed
5 permits since 2000: 4 completed, 1 never finaled.
Of the 1 never-finaled permit, 1 is 3 to 5 years old.
This is the city’s permit record, not a license check. It does not show whether the state license is active, bonded or insured. How to read these records
Permits filed each year
How long permits take
Each point is the quarter the permits were filed, for all building permits across San Francisco. A median counts only permits that have finished, so the shaded recent quarters look faster than they will end up: their slow permits have not finished yet. Hover a point for the slowest 10%. Gaps mean fewer than 5 permits. A rise in the issue line is the city’s review backlog, not the contractor. Too few of this contractor’s permits have finished to plot them.
Most recent permits
| Filed | Outcome | Address | Work described on the permit | Declared cost |
|---|---|---|---|---|
| May 11, 2022 | Never finaled issued May 2022, no final | 1738 Lake St | revision to pa# 202103126449: reduced lowering family room slab. structural work only. proposed ceiling ht at family room to be 8'-3"+/-Details
revision to pa# 202103126449: reduced lowering family room slab. structural work only. proposed ceiling ht at family room to be 8'-3"+/- | |
| Mar 17, 2022 | Completed final sign-off Dec 2022 | 1896 Green St | 1 complete bathroom remodel & sub panel upgrade. install shower stall, replace vertical pipes, install linear drain, electrical recessed light & fixtures. tile on floor.Details
1 complete bathroom remodel & sub panel upgrade. install shower stall, replace vertical pipes, install linear drain, electrical recessed light & fixtures. tile on floor. | $35,000 |
| Mar 12, 2021 | Completed final sign-off Oct 2023 | 1738 Lake St | renovation of (e) family room, bathroom & new patio at backyard. lowering family room floor slab, electrical & plumbing.Details
renovation of (e) family room, bathroom & new patio at backyard. lowering family room floor slab, electrical & plumbing. | $150,000 |
| Sep 2, 2016 | Completed final sign-off Oct 2019 | 3425 Scott St | compliance with mandatory seismic retrofit program per sfbc ch 34b: 2012 iebc appendix a-4; maher n/aDetails
compliance with mandatory seismic retrofit program per sfbc ch 34b: 2012 iebc appendix a-4; maher n/a | $60,000 |
| May 19, 2016 | Completed final sign-off Oct 2019 | 3425 Scott St | interior remodel of units 2,3 and 5 - each includes the relocation of kitchen. units 2 & 3 addition of mechanical room, laundry room & single bedroom.windows facing light well in the (n) bedroom of units 2 & 3 are to be replaced w/ double pane vinyl windows. all windows in unit 5 able to be replacedDetails
interior remodel of units 2,3 and 5 - each includes the relocation of kitchen. units 2 & 3 addition of mechanical room, laundry room & single bedroom.windows facing light well in the (n) bedroom of units 2 & 3 are to be replaced w/ double pane vinyl windows. all windows in unit 5 able to be replaced | $75,000 |