60 permits since 2000: 51 completed, 1 in progress, 4 never finaled, 4 expired or cancelled.
Of the 4 never-finaled permits, 1 is 3 to 5 years old, 1 is 5 to 10 years old, 2 are over 10 years old. 1 was filed but never issued.
This is the city’s permit record, not a license check. It does not show whether the state license is active, bonded or insured. How to read these records
Permits filed each year
How long permits take
Each point is the quarter the permits were filed, for all building permits across San Francisco. A median counts only permits that have finished, so the shaded recent quarters look faster than they will end up: their slow permits have not finished yet. Hover a point for the slowest 10%. Gaps mean fewer than 5 permits. A rise in the issue line is the city’s review backlog, not the contractor.
Most recent permits
| Filed | Outcome | Address | Work described on the permit | Declared cost |
|---|---|---|---|---|
| Sep 4, 2026 | In progress issued Sep 2026 | 208 Girard St | add one window to existing garage.Details
add one window to existing garage. | $6,000 |
| Dec 3, 2025 | Completed final sign-off May 2026 | 2525 Balboa St | revision to 202507030114: removing & replacing e) steel beam & steel post along west wall damaged from dryrotDetails
revision to 202507030114: removing & replacing e) steel beam & steel post along west wall damaged from dryrot | $27,000 |
| Jul 3, 2025 | Completed final sign-off May 2026 | 2525 Balboa St | remove and replace existing stucco and windows in-kind on northwest elevation onlyDetails
remove and replace existing stucco and windows in-kind on northwest elevation only | $330,000 |
| Nov 5, 2024 | Completed final sign-off Nov 2024 | 1555 Oak St | to obtain final inspection for work approved under pa# 202409092051, 201911207762, and 202008182007. all work is complete.Details
to obtain final inspection for work approved under pa# 202409092051, 201911207762, and 202008182007. all work is complete. | |
| Aug 21, 2023 | Completed final sign-off Nov 2024 | 1555 Oak St | administrative permit only to show as-built conditions of units/building per district bid. ref pa# 202002265525 (adu),22103317632 (#11), 20209033429 (#10), 201911307765 (#9), 201911207764 (#7), 201911207762 (#6), 202010217083 (#5), 201911207761 (#4), 201911207760 (#3), 202211307385 (#2)Details
administrative permit only to show as-built conditions of units/building per district bid. ref pa# 202002265525 (adu),22103317632 (#11), 20209033429 (#10), 201911307765 (#9), 201911207764 (#7), 201911207762 (#6), 202010217083 (#5), 201911207761 (#4), 201911207760 (#3), 202211307385 (#2) | |
| Nov 30, 2022 | Completed final sign-off Aug 2024 | 1555 Oak St | 2nd flr - unit 2 remodel - relocate (e) kitchen & bath, remodel bedroom, add 1 bath & 2 bedroom per plan.Details
2nd flr - unit 2 remodel - relocate (e) kitchen & bath, remodel bedroom, add 1 bath & 2 bedroom per plan. | $50,000 |
| Nov 30, 2022 | Never finaled filed Nov 2022, never issued | 875 Vermont St | replace rear deck & stairway in-kind; construct security fence beneath entry landing; replace door to workman's walkway service entrance; patch spalled concrete on entry landingDetails
replace rear deck & stairway in-kind; construct security fence beneath entry landing; replace door to workman's walkway service entrance; patch spalled concrete on entry landing | $20,000 |
| Nov 3, 2022 | Completed final sign-off Apr 2024 | 2525 Balboa St | repair water damage & replace windows on south facade.Details
repair water damage & replace windows on south facade. | $10,000 |
| Jul 12, 2022 | Completed final sign-off Mar 2024 | 2525 Balboa St | mandatory soft story seismic retrofit per san francisco ordinance 66-13, san francisco building code ch 34b & san francisco administrative bulletins 106 & 107. analysis per iebc-a4.Details
mandatory soft story seismic retrofit per san francisco ordinance 66-13, san francisco building code ch 34b & san francisco administrative bulletins 106 & 107. analysis per iebc-a4. | $100,000 |
| Jun 8, 2022 | Completed final sign-off Mar 2023 | 3253 16th St | revision to pa# 201906203947. revert approved swing outdoor back to existing in swing. all upgrades ada shall remain per pa# 201906203947.Details
revision to pa# 201906203947. revert approved swing outdoor back to existing in swing. all upgrades ada shall remain per pa# 201906203947. | |
| Jun 16, 2021 | Completed final sign-off Jun 2025 | 1470 09th Av | revision to pa 201709209110. alterating to unit 2 garage as follows: construction of non bearing partition walls at garage and relocation of back wall of unit 2.Details
revision to pa 201709209110. alterating to unit 2 garage as follows: construction of non bearing partition walls at garage and relocation of back wall of unit 2. | |
| Jun 9, 2021 | Expired or cancelled expired Nov 2024 | 1555 Oak St | revision to bldg permit 202009244911. relocate boiler room.Details
revision to bldg permit 202009244911. relocate boiler room. | |
| Apr 12, 2021 | Completed final sign-off Nov 2024 | 1555 Oak St | revision to pa# 201911207764. structural work only. no exterior work no change to unit size or locationDetails
revision to pa# 201911207764. structural work only. no exterior work no change to unit size or location | |
| Apr 9, 2021 | Completed final sign-off Nov 2024 | 1555 Oak St | apt 6 remodel: revision to pa 201911207762. structural changes only.Details
apt 6 remodel: revision to pa 201911207762. structural changes only. | |
| Apr 9, 2021 | Completed final sign-off Nov 2024 | 1555 Oak St | apt 3 remodel: revision to pa 201911207760. structural changes only. double joist over bedrom 2 and kitchen and shearwall. no exterior work, no change to unit size or location.Details
apt 3 remodel: revision to pa 201911207760. structural changes only. double joist over bedrom 2 and kitchen and shearwall. no exterior work, no change to unit size or location. | |
| Mar 31, 2021 | Completed final sign-off May 2024 | 1555 Oak St | unit #11: remodel 4th floor. 1 extg bathroom to 2 new bedroom. relocate extg kitchen. relocate extg bath.Details
unit #11: remodel 4th floor. 1 extg bathroom to 2 new bedroom. relocate extg kitchen. relocate extg bath. | $70,000 |
| Nov 13, 2020 | Completed final sign-off Jan 2021 | 1555 Oak St | garage: install 5/8" wall board to provide 1 hr. rating at garage ceiling & exterior wall. 2000 sq ft. approx. for replace ment of (e) lath & plaster removed w/o permit to address complaint # 202065731Details
garage: install 5/8" wall board to provide 1 hr. rating at garage ceiling & exterior wall. 2000 sq ft. approx. for replace ment of (e) lath & plaster removed w/o permit to address complaint # 202065731 | $4,000 |
| Oct 21, 2020 | Completed final sign-off Feb 2023 | 1555 Oak St | unit #5/3rd flr remodel: 1(e) bedroom to 2(n) bedrooms. 1(e) bathroom to 2(n) bathrooms. relocate (e) kitchen. (n) window (visible from street). must comply with sffc 1103.7.6.1: fire alarm modification under separate permit.Details
unit #5/3rd flr remodel: 1(e) bedroom to 2(n) bedrooms. 1(e) bathroom to 2(n) bathrooms. relocate (e) kitchen. (n) window (visible from street). must comply with sffc 1103.7.6.1: fire alarm modification under separate permit. | $60,000 |
| Sep 24, 2020 | Completed final sign-off Nov 2024 | 1555 Oak St | replace e boiler and domestic hot water tank with new for e 12 apts. replace e baseboard heater in unit 3,4,5,6,7,9,10. replace all e associated piping with new, leave sub-up for apt 1,2,11,12 for new base board heater during future remodelDetails
replace e boiler and domestic hot water tank with new for e 12 apts. replace e baseboard heater in unit 3,4,5,6,7,9,10. replace all e associated piping with new, leave sub-up for apt 1,2,11,12 for new base board heater during future remodel | $11,000 |
| Sep 23, 2020 | Completed final sign-off May 2024 | 1555 Oak St | to comply with nov2020047514: ground sand along the p|l at reion to be excavated. demolosh (e4) patient retaining wall. excavate to enlarge patio approx 5ft in width. construction new allan block retaning wall & patio. new fence.Details
to comply with nov2020047514: ground sand along the p|l at reion to be excavated. demolosh (e4) patient retaining wall. excavate to enlarge patio approx 5ft in width. construction new allan block retaning wall & patio. new fence. | $20,000 |
| Sep 3, 2020 | Completed final sign-off Feb 2023 | 1555 Oak St | unit #10 remodel: 1 existing bedroom to 3 new bedrooms. 1 existing bathroom to 2 new bathrooms. relocate existing kitchen.Details
unit #10 remodel: 1 existing bedroom to 3 new bedrooms. 1 existing bathroom to 2 new bathrooms. relocate existing kitchen. | $60,000 |
| Aug 18, 2020 | Expired or cancelled expired Nov 2024 | 1555 Oak St | clear nov 202046221 dated 7/29/20. submit lead and absbestos test report. demolish ceiling and wall for running boiler/gas piping ceiling 2800 sq ft wall 58 lfDetails
clear nov 202046221 dated 7/29/20. submit lead and absbestos test report. demolish ceiling and wall for running boiler/gas piping ceiling 2800 sq ft wall 58 lf | $4,500 |
| Feb 26, 2020 | Completed final sign-off Nov 2024 | 1555 Oak St | construct (3) adu per ord 162-16. remove (e) hss & replace w/ (n) foundations & moment frames #1-4 & to add footing for (n) load bearing wall & to add footing @ lobby/garageDetails
construct (3) adu per ord 162-16. remove (e) hss & replace w/ (n) foundations & moment frames #1-4 & to add footing for (n) load bearing wall & to add footing @ lobby/garage | $70,000 |
| Nov 20, 2019 | Completed final sign-off Feb 2023 | 1555 Oak St | remodel unit# 4. 1 (e) bedroom to 3 new bedrooms. replace 1 new casement window - match (e) window. visible from street. relocate kitchen & bathroom. n new bathroom. replace 1 new window (not visiable from street).Details
remodel unit# 4. 1 (e) bedroom to 3 new bedrooms. replace 1 new casement window - match (e) window. visible from street. relocate kitchen & bathroom. n new bathroom. replace 1 new window (not visiable from street). | $80,000 |
| Nov 20, 2019 | Expired or cancelled expired Nov 2024 | 1555 Oak St | unit #6: remodel unit. one existing bedroom to three new bedrooms. relocating kitchen & bathroom. replace 1 new window (double-hung) to match existing window (egress), not visible from street. add new bathroomDetails
unit #6: remodel unit. one existing bedroom to three new bedrooms. relocating kitchen & bathroom. replace 1 new window (double-hung) to match existing window (egress), not visible from street. add new bathroom | $50,000 |
| Nov 20, 2019 | Completed final sign-off Feb 2023 | 1555 Oak St | unit #7: remodel unit. one existing bedroom to two new bedrooms. relocating kitchen & bathroomDetails
unit #7: remodel unit. one existing bedroom to two new bedrooms. relocating kitchen & bathroom | $50,000 |
| Nov 20, 2019 | Completed final sign-off Feb 2023 | 1555 Oak St | unit #3: remodel unit. one existing bedroom to two new bedrooms. relocating kitchen & bathroomDetails
unit #3: remodel unit. one existing bedroom to two new bedrooms. relocating kitchen & bathroom | $50,000 |
| Nov 20, 2019 | Completed final sign-off Mar 2024 | 1555 Oak St | unit #9: remodel unit. one existing bedroom to two new bedrooms. relocating kitchen & bathroom.Details
unit #9: remodel unit. one existing bedroom to two new bedrooms. relocating kitchen & bathroom. | $50,000 |
| Jun 20, 2019 | Completed final sign-off Mar 2023 | 3253 16th St | mandatory disability access improvements for accessible business entrance program per ordinance 51-16.Details
mandatory disability access improvements for accessible business entrance program per ordinance 51-16. | $9,000 |
| Mar 8, 2019 | Completed final sign-off Mar 2019 | 2763 Filbert St | to obtain final inspection for work approved under pa# 2013-1203-3254 and 2017-0601-8071. all work is complete.Details
to obtain final inspection for work approved under pa# 2013-1203-3254 and 2017-0601-8071. all work is complete. | |
| Dec 7, 2018 | Completed final sign-off Mar 2019 | 2763 Filbert St | renewal pa #201610281428 and 201606018071 for final inspection.Details
renewal pa #201610281428 and 201606018071 for final inspection. | |
| Oct 23, 2017 | Completed final sign-off Aug 2019 | 1211 14th Av | soft story retrofit per sfebc chapter 4d engineering criteria : 2016 cebc appendix a-4. per sf ord 66-13, sf building code chapter 34b & sf administrative bulletin 106 & 107.Details
soft story retrofit per sfebc chapter 4d engineering criteria : 2016 cebc appendix a-4. per sf ord 66-13, sf building code chapter 34b & sf administrative bulletin 106 & 107. | $150,000 |
| Sep 20, 2017 | Completed final sign-off Jun 2025 | 1470 09th Av | accessory dwelling unit per sf ordinance #162-16 (add two adu units)Details
accessory dwelling unit per sf ordinance #162-16 (add two adu units) | $180,000 |
| Sep 13, 2017 | Completed final sign-off Aug 2020 | 1470 09th Av | soft story retrofit per sfebc chapter 4d: 2016 cebc appendix a-4Details
soft story retrofit per sfebc chapter 4d: 2016 cebc appendix a-4 | $180,000 |
| Aug 30, 2017 | Completed final sign-off Feb 2019 | 185 Parnassus Av | walkway repair concrete slab on gradeDetails
walkway repair concrete slab on grade | $2,000 |
| Jun 14, 2017 | Completed final sign-off Aug 2021 | 1251 08th Av | add unit per ordinance no. 162-16. add 2 units. unit#1 & unit#2 have 1 new bathroom , 1 new kitchen, & 1 new bedroom. fire alarm and sprinklers deferred.Details
add unit per ordinance no. 162-16. add 2 units. unit#1 & unit#2 have 1 new bathroom , 1 new kitchen, & 1 new bedroom. fire alarm and sprinklers deferred. | $150,000 |
| Jun 13, 2017 | Completed final sign-off Aug 2021 | 1251 08th Av | soft story retrofit per sf ordinance 66-13 building code ch 34 b admin bulletin 106/107. soft story retrofit per sfebc chapter 4d, 2016 cebc appendix a-4Details
soft story retrofit per sf ordinance 66-13 building code ch 34 b admin bulletin 106/107. soft story retrofit per sfebc chapter 4d, 2016 cebc appendix a-4 | $100,000 |
| Jun 1, 2017 | Expired or cancelled expired Mar 2019 | 2763 Filbert St | revise pa 2016-1028-1428 to add foundation/retaining walls at east & south foundations. replace garage slabDetails
revise pa 2016-1028-1428 to add foundation/retaining walls at east & south foundations. replace garage slab | $40,000 |
| Oct 28, 2016 | Never finaled issued Apr 2017, no final | 2763 Filbert St | revision to 201305287983 reconfigure 2nd egress stair to enclose area of (e) exterior stair with new interior stairs from garage to 3rd flr. new bath and laundry room at garage levelDetails
revision to 201305287983 reconfigure 2nd egress stair to enclose area of (e) exterior stair with new interior stairs from garage to 3rd flr. new bath and laundry room at garage level | $48,000 |
| Aug 3, 2016 | Completed final sign-off Apr 2021 | 1165 Francisco St | construct 2 accessory dwelling units per sf ordinance 30-15. mandatory soft story retrofit previously completed #2016-0801-5824.Details
construct 2 accessory dwelling units per sf ordinance 30-15. mandatory soft story retrofit previously completed #2016-0801-5824. | $250,000 |
| Aug 1, 2016 | Completed final sign-off Jun 2020 | 1165 Francisco St | mandatory seismic retrofit per sf ord 66-13 sf bld code chapet 34b sf admin bulletins 106 & 107 analysis iebc a4Details
mandatory seismic retrofit per sf ord 66-13 sf bld code chapet 34b sf admin bulletins 106 & 107 analysis iebc a4 | $120,000 |
| Jun 29, 2016 | Completed final sign-off Nov 2019 | 969 Burnett Av | mandatory soft story seismic retrofit per sf ord 6613 sf builkding code chapter 34 b and sf admin bulletins 106 and 107 analysis per iebc a4Details
mandatory soft story seismic retrofit per sf ord 6613 sf builkding code chapter 34 b and sf admin bulletins 106 and 107 analysis per iebc a4 | $120,000 |
| Jun 29, 2016 | Completed final sign-off Jun 2021 | 969 Burnett Av | auxiliary dwelling unit per sf ord 30-15. post mandatory seismic retrofit, reference mandatory soft story ordinance approval re: permit 201606291154. including; direct vent heaters, tankless water heater, new laundry gas dryer, and kitchen hood exhaust. sprinkler & alarm deferred.Details
auxiliary dwelling unit per sf ord 30-15. post mandatory seismic retrofit, reference mandatory soft story ordinance approval re: permit 201606291154. including; direct vent heaters, tankless water heater, new laundry gas dryer, and kitchen hood exhaust. sprinkler & alarm deferred. | $150,000 |
| May 2, 2016 | Completed final sign-off Sep 2019 | 969 Burnett Av | repair decayed balconies on back of building & add missing balcony. extend 2' from current width. associated variance already submitted to planning.Details
repair decayed balconies on back of building & add missing balcony. extend 2' from current width. associated variance already submitted to planning. | $40,000 |
| Mar 23, 2016 | Completed final sign-off Oct 2017 | 183 Parnassus Av | soft story seismic retrofit per sfbc chapter 34b engineering criteria per fema p-807.Details
soft story seismic retrofit per sfbc chapter 34b engineering criteria per fema p-807. | $70,000 |
| Mar 23, 2016 | Completed final sign-off Oct 2017 | 183 Parnassus Av | construct on auxiliary dwelling unit per ordinance # 30-15 in an (e) building after completion of a mandatory soft story retrofit pa# 2016/03/23/2814. fire alarm and sprinkler deferred.Details
construct on auxiliary dwelling unit per ordinance # 30-15 in an (e) building after completion of a mandatory soft story retrofit pa# 2016/03/23/2814. fire alarm and sprinkler deferred. | $70,000 |
| Aug 25, 2015 | Completed final sign-off Feb 2018 | 3606 Taraval St | value engineering front facade back to original. interior layout, simplified and door on rear moved. revision to prmit 201404032416.Details
value engineering front facade back to original. interior layout, simplified and door on rear moved. revision to prmit 201404032416. | |
| Nov 27, 2013 | Completed final sign-off Jun 2014 | 2651 Harrison St | to complete work already started on app# 200709193100 and obtain a final inspection.Details
to complete work already started on app# 200709193100 and obtain a final inspection. | $44,000 |
| Apr 9, 2013 | Completed final sign-off Oct 2025 | 208 Girard St | 2 story horizontal addition. 682 sq. ft. @ 2nd floor & 672 at 1st floor. raise (e) house 2' & add new 615 sq. ft. basement garage. add 3 bedrooms, 2 study, 3 new bathrooms, 1 kitchen & 1 living room.Details
2 story horizontal addition. 682 sq. ft. @ 2nd floor & 672 at 1st floor. raise (e) house 2' & add new 615 sq. ft. basement garage. add 3 bedrooms, 2 study, 3 new bathrooms, 1 kitchen & 1 living room. | $80,000 |
| Mar 4, 2013 | Completed final sign-off Nov 2013 | 255 Shipley St | barrier removal, enlarge entry door to comply w/ada requirement.Details
barrier removal, enlarge entry door to comply w/ada requirement. | $40,000 |
| Jan 25, 2013 | Completed final sign-off Aug 2013 | 255 Shipley St | reroofingDetails
reroofing | $3,500 |
| Apr 2, 2012 | Completed final sign-off Jul 2012 | 1802 Divisadero St | barrier removal to comply with ada requirement for front entrance and ada restroom.Details
barrier removal to comply with ada requirement for front entrance and ada restroom. | $10,000 |
| Apr 8, 2011 | Completed final sign-off Mar 2013 | 325 Bosworth St | rear yard horizontal addition to create family room, den, laundray and bathroom at ground level. 2nd story infill additon at stairs only.Details
rear yard horizontal addition to create family room, den, laundray and bathroom at ground level. 2nd story infill additon at stairs only. | $120,000 |
| Mar 31, 2011 | Never finaled issued Apr 2011, no final | 2651 Harrison St | for documentation purposes: revision to 200709193100 (s,s1) change in width dimension of lot. changes to addition dimension, narrower in width.Details
for documentation purposes: revision to 200709193100 (s,s1) change in width dimension of lot. changes to addition dimension, narrower in width. | |
| Aug 12, 2010 | Never finaled issued Aug 2010, no final | 485 Corbett Av | revision to extg app#200809080981. new retaining walls will be added to replace or reinforce extg retaining walls. change of occupancy and story cunt issued under app#200809080981 but not yet completed.Details
revision to extg app#200809080981. new retaining walls will be added to replace or reinforce extg retaining walls. change of occupancy and story cunt issued under app#200809080981 but not yet completed. | $20,000 |
| Aug 10, 2010 | Completed final sign-off Mar 2016 | 581 Chenery St | comply with his nov 201032432, dated 2/12/2010. remove all cabs, sink & range from 1st floor (illegal) kitchen & convert to "hobby" space. as required by title 24 energy compliance documentation: replace wh. comply with nov# 201032432 horizontal addition.Details
comply with his nov 201032432, dated 2/12/2010. remove all cabs, sink & range from 1st floor (illegal) kitchen & convert to "hobby" space. as required by title 24 energy compliance documentation: replace wh. comply with nov# 201032432 horizontal addition. | $20,000 |
| Feb 19, 2010 | Completed final sign-off Apr 2010 | 256 14th St | chnage of occupancy from m to s-1. add new accessible office, toilet & entry. all spaces unconditionedDetails
chnage of occupancy from m to s-1. add new accessible office, toilet & entry. all spaces unconditioned | $25,000 |
| Sep 29, 2009 | Completed final sign-off Jan 2010 | 644 Silver Av | to revert kitchen back to laundry room per previous permit #200308061341 & #200004127066.Details
to revert kitchen back to laundry room per previous permit #200308061341 & #200004127066. | $2,500 |
| Sep 15, 2009 | Completed final sign-off Nov 2009 | 848 Girard St | to complete work and obtain final inspection for work approved under 200603227266.Details
to complete work and obtain final inspection for work approved under 200603227266. | $70,000 |
| Sep 8, 2008 | Completed final sign-off Jun 2011 | 485 Corbett Av | remodel each level of an e single family dwelling and add 1 additional unit with a single car garage. unit 3: 2/bdrms, 2 1/2 baths. build into required rear yard per variance 20080722v.new decks at rear, new garage doors and front entry. n sprinkler system under sep permitDetails
remodel each level of an e single family dwelling and add 1 additional unit with a single car garage. unit 3: 2/bdrms, 2 1/2 baths. build into required rear yard per variance 20080722v.new decks at rear, new garage doors and front entry. n sprinkler system under sep permit | $415,000 |