Grid Alternatives
- Based in
- Oakland
- On San Francisco permits
- Feb 2024 to Apr 2024
- Last 24 months
- 0 permits filed
2 permits since 2000: 2 completed.
This is the city’s permit record, not a license check. It does not show whether the state license is active, bonded or insured. How to read these records
Permits filed each year
How long permits take
Each point is the quarter the permits were filed, for all building permits across San Francisco. A median counts only permits that have finished, so the shaded recent quarters look faster than they will end up: their slow permits have not finished yet. Hover a point for the slowest 10%. Gaps mean fewer than 5 permits. A rise in the issue line is the city’s review backlog, not the contractor. Too few of this contractor’s permits have finished to plot them.
Most recent permits
| Filed | Outcome | Address | Work described on the permit | Declared cost |
|---|---|---|---|---|
| Apr 10, 2024 | Completed final sign-off Jan 2025 | 243 Rey St | trench existing softscape in bld 2 and mount ev chargers adjacent to parking space. trench sidewalk at bldg 14 and mount ev chargers on pedestal.Details
trench existing softscape in bld 2 and mount ev chargers adjacent to parking space. trench sidewalk at bldg 14 and mount ev chargers on pedestal. | $46,000 |
| Feb 1, 2024 | Completed final sign-off Apr 2024 | 1250 Sunnydale Av | install (16) level-2 ev chargers (evcs) from existing common area electrical panels and mount to pedestals adjacent to vehicle parking space. parking for evcs will be assigned to tenants and not visible to the general public.Details
install (16) level-2 ev chargers (evcs) from existing common area electrical panels and mount to pedestals adjacent to vehicle parking space. parking for evcs will be assigned to tenants and not visible to the general public. | $80,000 |