8 permits since 2000: 7 completed, 1 never finaled.
Of the 1 never-finaled permit, 1 is 5 to 10 years old.
This is the city’s permit record, not a license check. It does not show whether the state license is active, bonded or insured. How to read these records
Permits filed each year
How long permits take
Each point is the quarter the permits were filed, for all building permits across San Francisco. A median counts only permits that have finished, so the shaded recent quarters look faster than they will end up: their slow permits have not finished yet. Hover a point for the slowest 10%. Gaps mean fewer than 5 permits. A rise in the issue line is the city’s review backlog, not the contractor.
Most recent permits
| Filed | Outcome | Address | Work described on the permit | Declared cost |
|---|---|---|---|---|
| Jun 26, 2025 | Completed final sign-off Jul 2025 | 1201 Harrison St | revision to 202406275366 involving changes to ada path of traval & bollard's in the ada path (in front of the existing c-store) modification. all changes are on-site, no off-site workDetails
revision to 202406275366 involving changes to ada path of traval & bollard's in the ada path (in front of the existing c-store) modification. all changes are on-site, no off-site work | $37,000 |
| Oct 16, 2024 | Completed final sign-off Jul 2025 | 1201 Harrison St | remove/demo (e) hydrogen equip enclosure, tanks, 2 dispensers & associated equip/piping and electrical switcgear (remove/cap). remove piping trench and recompact. landscape and paving modifcations to affected areas. 3 new parking spaces. 1 new yard light. no new hydrogen equipment or enclosures.Details
remove/demo (e) hydrogen equip enclosure, tanks, 2 dispensers & associated equip/piping and electrical switcgear (remove/cap). remove piping trench and recompact. landscape and paving modifcations to affected areas. 3 new parking spaces. 1 new yard light. no new hydrogen equipment or enclosures. | $400,000 |
| Sep 23, 2024 | Completed final sign-off Sep 2025 | 3550 Mission St | remove/demolish: hydrogen equipment enclosure, hydro tanks, 2 hydro dispensers, associated equipment/piping, & elec transformer & switchgear. remove piping trench & recompact. landscape & paving modifications. relocate air/water unit, vacuum & 2 yard lights. remove & replace concrete swale near (e)Details
remove/demolish: hydrogen equipment enclosure, hydro tanks, 2 hydro dispensers, associated equipment/piping, & elec transformer & switchgear. remove piping trench & recompact. landscape & paving modifications. relocate air/water unit, vacuum & 2 yard lights. remove & replace concrete swale near (e) | $400,000 |
| Oct 24, 2019 | Completed final sign-off Nov 2023 | 1875 Marin St | install an 85 gallon new oil above ground storage tank. connect to an existing air lineDetails
install an 85 gallon new oil above ground storage tank. connect to an existing air line | $2,500 |
| Jun 7, 2019 | Completed final sign-off Jul 2019 | 1201 Harrison St | as-built set for fire alarm permit application 201904188345Details
as-built set for fire alarm permit application 201904188345 | |
| Apr 18, 2019 | Never finaled issued May 2019, no final | 1201 Harrison St | fire alarm permit for (n) hydrogen fuel facility. ref permit# 201711133812. **maher n/a**Details
fire alarm permit for (n) hydrogen fuel facility. ref permit# 201711133812. **maher n/a** | $10,000 |
| Jan 30, 2019 | Completed final sign-off Jul 2019 | 1201 Harrison St | revision to issued permit #201711133812, structural sheet revision. maher naDetails
revision to issued permit #201711133812, structural sheet revision. maher na | |
| Nov 13, 2017 | Completed final sign-off Jul 2019 | 1201 Harrison St | new proposed hydrogen fuel dispensers for passenger vehicles.associated equiptment foundations for auxilliary equiptment. ** maher: disturbance of at least 50 cu. yd of soil. route to dph **Details
new proposed hydrogen fuel dispensers for passenger vehicles.associated equiptment foundations for auxilliary equiptment. ** maher: disturbance of at least 50 cu. yd of soil. route to dph ** | $200,000 |