Fisher Development Inc
- Based in
- San Francisco
- On San Francisco permits
- Feb 2000 to Jun 2022
- Last 24 months
- 0 permits filed
364 permits since 2000: 255 completed, 61 never finaled, 48 expired or cancelled.
Of the 61 never-finaled permits, 1 is 3 to 5 years old, 23 are 5 to 10 years old, 37 are over 10 years old. 7 were filed but never issued.
This is the city’s permit record, not a license check. It does not show whether the state license is active, bonded or insured. How to read these records
Permits filed each year
How long permits take
Each point is the quarter the permits were filed, for all building permits across San Francisco. A median counts only permits that have finished, so the shaded recent quarters look faster than they will end up: their slow permits have not finished yet. Hover a point for the slowest 10%. Gaps mean fewer than 5 permits. A rise in the issue line is the city’s review backlog, not the contractor.
Most recent permits
Showing the 100 most recent of 364.
| Filed | Outcome | Address | Work described on the permit | Declared cost |
|---|---|---|---|---|
| Jun 21, 2022 | Completed final sign-off Oct 2022 | 432 Jackson St | blade sign to be installed "thom browne new york"Details
blade sign to be installed "thom browne new york" | $4,000 |
| Mar 30, 2022 | Expired or cancelled expired Apr 2026 | 2789 25th St | revision to pa#201906052532 to provide manuverablity clearance at bottom landing of provided liftDetails
revision to pa#201906052532 to provide manuverablity clearance at bottom landing of provided lift | |
| Mar 2, 2022 | Completed final sign-off Oct 2024 | 99 Harding Rd | priority process - new building construction recreation centerDetails
priority process - new building construction recreation center | $700,000 |
| Aug 17, 2021 | Completed final sign-off May 2022 | 139 Townsend St | 4th floor: provide 7 new vav box with reheat coil to service office area. provide new duct work heating water piping and refrigerant piping as required. ref bpa#202103045904Details
4th floor: provide 7 new vav box with reheat coil to service office area. provide new duct work heating water piping and refrigerant piping as required. ref bpa#202103045904 | $50,000 |
| Jul 28, 2021 | Completed final sign-off May 2022 | 139 Townsend St | reference 202103045904 new indoor lighting for office space tiDetails
reference 202103045904 new indoor lighting for office space ti | |
| Jul 27, 2021 | Completed final sign-off May 2022 | 139 Townsend St | ref 202103045904 new indoor lighting for office space tiDetails
ref 202103045904 new indoor lighting for office space ti | |
| Jun 14, 2021 | Completed final sign-off Oct 2022 | 432 Jackson St | interior non-structural t.i. (n) partitions, flooring, ceiling, (n) pantry, cabinetry, mopsink, (n) elec & lighting. no exterior work. mech & sprinklers under separate permit. ref pa# 202011309841.Details
interior non-structural t.i. (n) partitions, flooring, ceiling, (n) pantry, cabinetry, mopsink, (n) elec & lighting. no exterior work. mech & sprinklers under separate permit. ref pa# 202011309841. | $310,000 |
| Mar 4, 2021 | Completed final sign-off Jan 2024 | 2240 Market St | fire only permit for new fire hydrant location. associated w/ work under site permit 2017-0331-2940Details
fire only permit for new fire hydrant location. associated w/ work under site permit 2017-0331-2940 | $18,000 |
| Mar 4, 2021 | Completed final sign-off May 2022 | 139 Townsend St | 4th fl: t.i. of an (e) office space. new walls. new partition. new finishes. mechanical and electrical work.Details
4th fl: t.i. of an (e) office space. new walls. new partition. new finishes. mechanical and electrical work. | $800,000 |
| Feb 26, 2021 | Completed final sign-off Jul 2021 | 139 Townsend St | suite 100: soft demo per ab-017 of an existing office space at ground floor.Details
suite 100: soft demo per ab-017 of an existing office space at ground floor. | $60,000 |
| Jan 28, 2021 | Never finaled issued Mar 2022, no final | 1554 Market St | revision to issused pa# 201311222657-s3 (mep) to capture: - electrical impacts of mechanical ve items. - pg & e incoming electrical service coordination. ** maher: n/a **Details
revision to issused pa# 201311222657-s3 (mep) to capture: - electrical impacts of mechanical ve items. - pg & e incoming electrical service coordination. ** maher: n/a ** | |
| Dec 21, 2020 | Expired or cancelled cancelled Jul 2024 | 468 Jackson St | non-structural demo at interior of building for future t.i. ref pa# 202009154239.Details
non-structural demo at interior of building for future t.i. ref pa# 202009154239. | $50,000 |
| Dec 7, 2020 | Completed final sign-off Aug 2021 | 2222 Market St | in-kind siding repairs on sw wall.Details
in-kind siding repairs on sw wall. | $14,790 |
| Nov 25, 2020 | Never finaled issued Apr 2021, no final | 139 Townsend St | rooftop: addition of 1 new skylight. maher n/aDetails
rooftop: addition of 1 new skylight. maher n/a | $20,000 |
| Nov 16, 2020 | Never finaled issued Feb 2021, no final | 2240 Market St | pid only, plumbing design associated w/ site permit #201703312941, review for storm water control plan.Details
pid only, plumbing design associated w/ site permit #201703312941, review for storm water control plan. | |
| Nov 12, 2020 | Completed final sign-off May 2022 | 139 Townsend St | 4th & 5th floor: commercial ti including partitions, flooring, and new conevenience stairs between 4th/5th floor. mep under separate permit.Details
4th & 5th floor: commercial ti including partitions, flooring, and new conevenience stairs between 4th/5th floor. mep under separate permit. | $1,500,000 |
| Nov 9, 2020 | Completed final sign-off Sep 2024 | 2240 Market St | revision to pa# 201703312940. addendum 3. arch/mep to include weather tight hatch to elevator hoistway.Details
revision to pa# 201703312940. addendum 3. arch/mep to include weather tight hatch to elevator hoistway. | $5,000 |
| Sep 15, 2020 | Completed final sign-off Mar 2021 | 139 Townsend St | ground fl barrier removal. tenant improvement of existing restroom at ground floor to comply with current code.Details
ground fl barrier removal. tenant improvement of existing restroom at ground floor to comply with current code. | $130,000 |
| Sep 15, 2020 | Expired or cancelled withdrawn Aug 2024 | 468 Jackson St | tenant improvements at all floors to provide showroom, offices & staff amenities. upgrade ada bathrooms. replace stair to basement at #470 and one column at #472. seismic upgrade performed under separate permit. mep deferred.Details
tenant improvements at all floors to provide showroom, offices & staff amenities. upgrade ada bathrooms. replace stair to basement at #470 and one column at #472. seismic upgrade performed under separate permit. mep deferred. | $700,000 |
| Jun 4, 2020 | Never finaled issued Jun 2020, no final | 139 Townsend St | 4th flr. demolition of an (e) office space on the fourth floor of a commercialoffice building. ab-017.Details
4th flr. demolition of an (e) office space on the fourth floor of a commercialoffice building. ab-017. | $45,000 |
| Feb 3, 2020 | Never finaled issued Feb 2020, no final | 601 California St | minor changes to ductwork at new stair includes lighting. reference pa #2019-1226-0684.Details
minor changes to ductwork at new stair includes lighting. reference pa #2019-1226-0684. | $18,000 |
| Dec 26, 2019 | Never finaled issued Feb 2020, no final | 601 California St | 20/f: tenant convienience stair be6tween floors 2-21. strutural & architectural only. work is associated with t.i pa20191226. maher n/a.Details
20/f: tenant convienience stair be6tween floors 2-21. strutural & architectural only. work is associated with t.i pa20191226. maher n/a. | $45,000 |
| Dec 26, 2019 | Never finaled issued Feb 2020, no final | 601 California St | 20/f: interior t.i. including drywall, millwork, finisehs, ceiling, lighting, plumbing, eletrical & mechanical. maher n/a.Details
20/f: interior t.i. including drywall, millwork, finisehs, ceiling, lighting, plumbing, eletrical & mechanical. maher n/a. | $1,431,060 |
| Nov 26, 2019 | Completed final sign-off Jan 2020 | 2222 Market St | achorage of stucco to east wall to secure stucco during work related to 201811166151 and 201803194011Details
achorage of stucco to east wall to secure stucco during work related to 201811166151 and 201803194011 | $2,000 |
| Nov 12, 2019 | Completed final sign-off Sep 2024 | 2240 Market St | free standing tower craneDetails
free standing tower crane | $25,000 |
| Nov 6, 2019 | Completed final sign-off Sep 2024 | 2240 Market St | revision to pa 2017-0331-2940 s1. revision to foundation designDetails
revision to pa 2017-0331-2940 s1. revision to foundation design | |
| Oct 16, 2019 | Never finaled issued Aug 2020, no final | 299 Macalla Rd | gradeing, excavation, dry utilities, joint tranch for parcel 4y.Details
gradeing, excavation, dry utilities, joint tranch for parcel 4y. | $1,695,150 |
| Oct 15, 2019 | Never finaled issued Aug 2020, no final | 109 Forest Rd | bldg# 25. shoring & tiebacks for new construction at yerba buena parcel 4y. reference pa#2019/0517/0933Details
bldg# 25. shoring & tiebacks for new construction at yerba buena parcel 4y. reference pa#2019/0517/0933 | $300,000 |
| Oct 15, 2019 | Never finaled issued Aug 2020, no final | 119 Forest Rd | bldg# 27. shoring & tiebacks for new construction at yerba buena 4y. reference permit application #2019/0517/0935.Details
bldg# 27. shoring & tiebacks for new construction at yerba buena 4y. reference permit application #2019/0517/0935. | $300,000 |
| Oct 15, 2019 | Never finaled issued Aug 2020, no final | 101 Forest Rd | bldg# 24. shoring & tiebacks for new construction at yerba buena parce 4y. reference permit #2019/0517/0932.Details
bldg# 24. shoring & tiebacks for new construction at yerba buena parce 4y. reference permit #2019/0517/0932. | $300,000 |
| Oct 3, 2019 | Completed final sign-off Nov 2019 | 601 California St | interior, non structural pre construction demo per sfab-017 approved sprinkler permit 201910023319Details
interior, non structural pre construction demo per sfab-017 approved sprinkler permit 201910023319 | $60,000 |
| Sep 24, 2019 | Never finaled issued Oct 2019, no final | 777 Tennessee St | removal of car stackers on basement level. ref 201507141485s3Details
removal of car stackers on basement level. ref 201507141485s3 | |
| Aug 8, 2019 | Completed final sign-off Mar 2021 | 139 Townsend St | interior improvement of an office on the 5th floor of commercial office bldg. nw construction will consist of modification of extg board room and converted extg conference room to 2 offices. includes finishes, mech, elec, modifiction. no exterior work or structural work. mep deferredDetails
interior improvement of an office on the 5th floor of commercial office bldg. nw construction will consist of modification of extg board room and converted extg conference room to 2 offices. includes finishes, mech, elec, modifiction. no exterior work or structural work. mep deferred | $372,171 |
| Aug 2, 2019 | Never finaled issued Aug 2019, no final | 1554 Market St | street spaceDetails
street space | |
| Jun 13, 2019 | Completed final sign-off Sep 2019 | 777 Tennessee St | revision to pa 2015071485 s3. addition of a 2-hr rated closet / room for das equipment on basement level.Details
revision to pa 2015071485 s3. addition of a 2-hr rated closet / room for das equipment on basement level. | |
| Jun 5, 2019 | Expired or cancelled expired Apr 2026 | 2789 25th St | 2nd floor: office t.i. and accessibility upgrade per mod review. non structural upgrades to include walls, doors, ceiling, finishes, mech, elec, and plmg work. n/a for maherDetails
2nd floor: office t.i. and accessibility upgrade per mod review. non structural upgrades to include walls, doors, ceiling, finishes, mech, elec, and plmg work. n/a for maher | $1,413,231 |
| Jun 3, 2019 | Never finaled filed Jun 2019, never issued | 1 Signal Rd | yerba buena island project. to erect a type v-b, 2-story amenity building with one basement.Details
yerba buena island project. to erect a type v-b, 2-story amenity building with one basement. | $2,660,000 |
| May 17, 2019 | Expired or cancelled withdrawn Mar 2023 | 225 Forest Rd | yerba buena island project. bldg# 22 (4y). to erect 4 stories, no basement, type iii-a, 4 units residential townhouse.Details
yerba buena island project. bldg# 22 (4y). to erect 4 stories, no basement, type iii-a, 4 units residential townhouse. | $3,100,000 |
| May 17, 2019 | Never finaled filed May 2019, never issued | 209 Forest Rd | yerba buena island project. bldg# 20 (4y). to erect 4 stories, no basement, type iii-a, 4 units residential townhouse. 3/07/24: change address from 209 forest rd 8954/001 to 33 meadow dr 8954/004 at permit issuance. wfDetails
yerba buena island project. bldg# 20 (4y). to erect 4 stories, no basement, type iii-a, 4 units residential townhouse. 3/07/24: change address from 209 forest rd 8954/001 to 33 meadow dr 8954/004 at permit issuance. wf | $3,000,000 |
| May 17, 2019 | Never finaled filed May 2019, never issued | 3 Signal Rd | yerba buena island project. to erect 4 stories, no basement, type iii-a, of a total 11 units at buildings 17ab.Details
yerba buena island project. to erect 4 stories, no basement, type iii-a, of a total 11 units at buildings 17ab. | $4,940,000 |
| May 17, 2019 | Expired or cancelled withdrawn Nov 2021 | 15 Signal Rd | yerba buena island project. bldg# 18 (3y). to erect 4 stories, no basement, type iii-a, 6 units residential townhouse.Details
yerba buena island project. bldg# 18 (3y). to erect 4 stories, no basement, type iii-a, 6 units residential townhouse. | $6,400,000 |
| May 17, 2019 | Never finaled filed May 2019, never issued | 101 Forest Rd | yerba buena island project. bldg# 24 (4y). to erect 5 stories, no basement, type iii-a, 4 units residential townhouse. 3/07/24: change address from 101 forest rd 8954/001 to 51 forest rd 8954/004 at permit issuance. wfDetails
yerba buena island project. bldg# 24 (4y). to erect 5 stories, no basement, type iii-a, 4 units residential townhouse. 3/07/24: change address from 101 forest rd 8954/001 to 51 forest rd 8954/004 at permit issuance. wf | $3,200,000 |
| May 17, 2019 | Completed final sign-off Feb 2025 | 36 Meadow Dr | yerba buena island project. bldg# 27 (4y). to erect 4 stories, 2 basements, type iii-a / i-a, 14 units residential townhouse.Details
yerba buena island project. bldg# 27 (4y). to erect 4 stories, 2 basements, type iii-a / i-a, 14 units residential townhouse. | $10,350,000 |
| May 17, 2019 | Completed final sign-off Feb 2025 | 38 Meadow Dr | yerba buena island project. bldg# 26 (4y). to erect 4 stories, no basement, type iii-a, 7 units residential townhouse.Details
yerba buena island project. bldg# 26 (4y). to erect 4 stories, no basement, type iii-a, 7 units residential townhouse. | $4,250,000 |
| May 17, 2019 | Never finaled filed May 2019, never issued | 109 Forest Rd | yerba buena island project. bldg# 25 (4y). to erect 4 stories, no basement, type iii-a, 5 units residential townhouse. 3/07/24: change address from 109 forest rd 8954/001 to 55 forest rd 8954/004 at permit issuance. wfDetails
yerba buena island project. bldg# 25 (4y). to erect 4 stories, no basement, type iii-a, 5 units residential townhouse. 3/07/24: change address from 109 forest rd 8954/001 to 55 forest rd 8954/004 at permit issuance. wf | $2,700,000 |
| May 17, 2019 | Completed final sign-off Feb 2025 | 37 Meadow Dr | yerba buena island project. bldg# 23 (4y). to erect 3 stories, no basement, type iii-a, 4 units residential townhouse.Details
yerba buena island project. bldg# 23 (4y). to erect 3 stories, no basement, type iii-a, 4 units residential townhouse. | $2,100,000 |
| May 17, 2019 | Never finaled filed May 2019, never issued | 201 Forest Rd | yerba buena island project. bldg# 19 (4y). to erect 4 stories, no basement, type iii-a, 4 units residential townhouse. 3/07/24: change address from 201 forest rd 8954/002 to 31 meadow dr 8954/004 at permit issuance. wfDetails
yerba buena island project. bldg# 19 (4y). to erect 4 stories, no basement, type iii-a, 4 units residential townhouse. 3/07/24: change address from 201 forest rd 8954/002 to 31 meadow dr 8954/004 at permit issuance. wf | $3,100,000 |
| May 17, 2019 | Completed final sign-off Feb 2025 | 35 Meadow Dr | yerba buena island project. bldg# 21 (4y). to erect 4 stories, no basement, type iii-a , for 5 dwelling unitsDetails
yerba buena island project. bldg# 21 (4y). to erect 4 stories, no basement, type iii-a , for 5 dwelling units | $3,000,000 |
| Apr 5, 2019 | Completed final sign-off Jun 2020 | 777 Tennessee St | strom water control systems. pa# 2015/07/14/1485-s3. ** maher: n/a **Details
strom water control systems. pa# 2015/07/14/1485-s3. ** maher: n/a ** | |
| Mar 28, 2019 | Completed final sign-off Jul 2019 | 440 Turk St | deferred submittal for structural for extg. entry gate. referencing permit 201810304528. 4x4 mesh at rear deck fence. frtw sleepers in lieu of steel. n/a for maherDetails
deferred submittal for structural for extg. entry gate. referencing permit 201810304528. 4x4 mesh at rear deck fence. frtw sleepers in lieu of steel. n/a for maher | $10,000 |
| Dec 12, 2018 | Completed final sign-off Aug 2019 | 360 Spear St | replacement of metal panels in e window frames with safety glass to match adjacent glass panels in color and overall appearance.Details
replacement of metal panels in e window frames with safety glass to match adjacent glass panels in color and overall appearance. | $250,000 |
| Dec 12, 2018 | Completed final sign-off May 2020 | 360 Spear St | cut new window openings in the existing perimeter shearwalls and strengthening the piers and spandrels around these openings by installation of carbon fiber wrap.Details
cut new window openings in the existing perimeter shearwalls and strengthening the piers and spandrels around these openings by installation of carbon fiber wrap. | $500,000 |
| Oct 30, 2018 | Completed final sign-off Aug 2019 | 440 Turk St | priority plan review. work includes removal of (e) int. improvements & installation of (n) int. partitions, doors, ceilings, finishes & (n) mech, elect, plumb & fire protection systems connected to base bldg services. no ext. work is proposed except for replacement of windows glazing for improvedDetails
priority plan review. work includes removal of (e) int. improvements & installation of (n) int. partitions, doors, ceilings, finishes & (n) mech, elect, plumb & fire protection systems connected to base bldg services. no ext. work is proposed except for replacement of windows glazing for improved | $3,800,000 |
| Oct 23, 2018 | Completed final sign-off Apr 2019 | 360 Spear St | selective non structural demo on floors 1-4. removal of (e) non operational mep systems, partitions, fixtures & finishes, no exterior demo is proposed maher naDetails
selective non structural demo on floors 1-4. removal of (e) non operational mep systems, partitions, fixtures & finishes, no exterior demo is proposed maher na | $5,000 |
| Aug 24, 2018 | Completed final sign-off Jun 2022 | 201 Macalla Rd | mayor's executive directive 17-02 only. yerba buena project. to erect 6 stories, 1 basement, type iii-a over type i-a, 124 units residential buildng with parking. (r-2,a-3,s-2) ** mitigation measures apply 475475Details
mayor's executive directive 17-02 only. yerba buena project. to erect 6 stories, 1 basement, type iii-a over type i-a, 124 units residential buildng with parking. (r-2,a-3,s-2) ** mitigation measures apply 475475 | $68,285,000 |
| Aug 6, 2018 | Completed final sign-off Mar 2019 | 440 Turk St | demolish all none structural shear walls for interior reconfigurationDetails
demolish all none structural shear walls for interior reconfiguration | $180,000 |
| Jul 18, 2018 | Completed final sign-off Nov 2018 | 218 Stockton St | install new vrf condensing unit including piping. shell & core work only. tenant improvement under separate permitDetails
install new vrf condensing unit including piping. shell & core work only. tenant improvement under separate permit | $50,000 |
| Jul 10, 2018 | Completed final sign-off Aug 2018 | 222 Stockton St | interior "soft demo" existing retail. ground floor/basement/mezz. all exterior work "storefront and sinage" under seperate permit. stairs /walls and doors under separate permit 201805078329Details
interior "soft demo" existing retail. ground floor/basement/mezz. all exterior work "storefront and sinage" under seperate permit. stairs /walls and doors under separate permit 201805078329 | $150,000 |
| Jul 5, 2018 | Never finaled issued Jul 2018, no final | 425 Market St | revision to pa #201805038076. mep work only. addition of 2 duct smoke detectors at 22nd floorDetails
revision to pa #201805038076. mep work only. addition of 2 duct smoke detectors at 22nd floor | |
| May 3, 2018 | Completed final sign-off May 2021 | 425 Market St | 22nd fl: interior renovation of existing office space - walls finishes, mechanical, electrical, plumbing and accessibility upgrade. maher naDetails
22nd fl: interior renovation of existing office space - walls finishes, mechanical, electrical, plumbing and accessibility upgrade. maher na | $375,000 |
| Mar 27, 2018 | Completed final sign-off Sep 2018 | 580 California St | interior work to 23rd fl. remodel of kitchen, restroom vestibule,copy/supply room and small conference room. this scope does not affect existing exit acess, path of egress or exit stairs, exitsting exiting is to remain as is, mep, fire life safety and sprinkler system under separate permit. maher naDetails
interior work to 23rd fl. remodel of kitchen, restroom vestibule,copy/supply room and small conference room. this scope does not affect existing exit acess, path of egress or exit stairs, exitsting exiting is to remain as is, mep, fire life safety and sprinkler system under separate permit. maher na | $250,000 |
| Mar 19, 2018 | Completed final sign-off Apr 2020 | 2240 Market St | temporary shoring system to accommodate foundation construction for pa 2017-0331-2940,Details
temporary shoring system to accommodate foundation construction for pa 2017-0331-2940, | $180,000 |
| Mar 2, 2018 | Completed final sign-off Apr 2018 | 425 Market St | full floor demo on 22nd floor of non-load bearing partitions, door & frames, ceiling, lighting and other finishes. ref pa 2018-0301-2576. maher naDetails
full floor demo on 22nd floor of non-load bearing partitions, door & frames, ceiling, lighting and other finishes. ref pa 2018-0301-2576. maher na | $180,000 |
| Mar 2, 2018 | Completed final sign-off Jul 2018 | 218 Stockton St | new locker rooms & storage in the basementDetails
new locker rooms & storage in the basement | $125,000 |
| Jan 10, 2018 | Never finaled issued Jan 2018, no final | 334 Mason St | street spaceDetails
street space | |
| Dec 13, 2017 | Completed final sign-off Oct 2019 | 777 Tennessee St | revision to pa #201512296028, to modify design excavation & shoring systems. maher: yesDetails
revision to pa #201512296028, to modify design excavation & shoring systems. maher: yes | |
| Nov 29, 2017 | Completed final sign-off Mar 2018 | 146 Geary St | demo existing finishes, casework, non-structural partitions. ab-017Details
demo existing finishes, casework, non-structural partitions. ab-017 | $100,000 |
| Oct 26, 2017 | Never finaled issued Dec 2017, no final | 2206 Lake St | (e) game room renovation includes electrical and structural modifcation and (n) enclosure. excavation less than 50cy.Details
(e) game room renovation includes electrical and structural modifcation and (n) enclosure. excavation less than 50cy. | $40,000 |
| Sep 25, 2017 | Completed final sign-off Apr 2019 | 399 Geary St | revision to pa#201611233479, saell and core remodel, additional of partial enclosed 3/f with open air roof terrace, new elevator, new exit stairs, new storefront, new glass curtain wall facade along geary st. revision to mep. n/a ordinance #155-13Details
revision to pa#201611233479, saell and core remodel, additional of partial enclosed 3/f with open air roof terrace, new elevator, new exit stairs, new storefront, new glass curtain wall facade along geary st. revision to mep. n/a ordinance #155-13 | |
| Jul 11, 2017 | Completed final sign-off Feb 2018 | 800 Presidio Av | administration to change lot number from block #1073/013 to 1073/055 and 1073/056 on pa #201204168406, including site permit + six addenda.Details
administration to change lot number from block #1073/013 to 1073/055 and 1073/056 on pa #201204168406, including site permit + six addenda. | |
| Jul 7, 2017 | Completed final sign-off Feb 2018 | 800 Presidio Av | revision to addendum 2(s2) of pa #201204168406 issued 1/4/17: install playground in lower yard of non profit owned community center in place of previously approved decomposed granite. project managed by owner under grant from "kaboom", install pre-fab stair (ada compliant).Details
revision to addendum 2(s2) of pa #201204168406 issued 1/4/17: install playground in lower yard of non profit owned community center in place of previously approved decomposed granite. project managed by owner under grant from "kaboom", install pre-fab stair (ada compliant). | $5,000 |
| Jun 7, 2017 | Completed final sign-off Apr 2019 | 399 Geary St | micropile anchorage and connection to the pile cap.Details
micropile anchorage and connection to the pile cap. | $80,000 |
| May 30, 2017 | Never finaled issued May 2017, no final | 139 Townsend St | tenant improvement of (e) office space - new partitions, new finishes, meup under separate permitDetails
tenant improvement of (e) office space - new partitions, new finishes, meup under separate permit | $250,000 |
| May 24, 2017 | Completed final sign-off Dec 2018 | 399 Geary St | one testing micropile installation onlyDetails
one testing micropile installation only | $10,000 |
| May 12, 2017 | Completed final sign-off Feb 2018 | 800 Presidio Av | revised mechanical drawing elevator hoist way smoke detector detail revision to 201204168406Details
revised mechanical drawing elevator hoist way smoke detector detail revision to 201204168406 | $5,000 |
| Apr 6, 2017 | Completed final sign-off Jul 2017 | 1201 Bryant St | replace portion of (e) roof with (n) soprema 60mil pvc roof.Details
replace portion of (e) roof with (n) soprema 60mil pvc roof. | $40,000 |
| Mar 31, 2017 | Completed final sign-off Sep 2024 | 2240 Market St | priority permit processing. change of use from funural home to apartment & retail. vertical & horizontal addition to existing. 5-story, 44 dwelling units with commercial over basement garage building. assigned to fpe sagiv 3.9.21, lt. deenDetails
priority permit processing. change of use from funural home to apartment & retail. vertical & horizontal addition to existing. 5-story, 44 dwelling units with commercial over basement garage building. assigned to fpe sagiv 3.9.21, lt. deen | $20,000,000 |
| Mar 22, 2017 | Completed final sign-off Mar 2018 | 2 Embarcadero Center | 1,2,3/f-interior renovation to (e) gym include: demo (e) lighting, plumbing, hvac terminals & vav boxes,(e) casework-desks,lockers,storage,flooring, acoustic ceiling & limited non bearing partitions. new lighting,plumbing,hvac fixtures,floor,wall finishes,acoustic ceiling & non bearing partitions.Details
1,2,3/f-interior renovation to (e) gym include: demo (e) lighting, plumbing, hvac terminals & vav boxes,(e) casework-desks,lockers,storage,flooring, acoustic ceiling & limited non bearing partitions. new lighting,plumbing,hvac fixtures,floor,wall finishes,acoustic ceiling & non bearing partitions. | $175,000 |
| Mar 8, 2017 | Completed final sign-off May 2019 | 336 Mason St | grnd flr: soft demo - ab-017 ref pa 201611233479 maher naDetails
grnd flr: soft demo - ab-017 ref pa 201611233479 maher na | $5,000 |
| Feb 14, 2017 | Never finaled issued May 2017, no final | 1201 Bryant St | deferred base building mep for 1201 bryant st. reference appln #201606301320 (architectural)Details
deferred base building mep for 1201 bryant st. reference appln #201606301320 (architectural) | |
| Jan 30, 2017 | Completed final sign-off Sep 2017 | 601 California St | #1900- new work consists of limited demo & new ceiling height partitions, doors, frames and hardware, millwork, power/data, finishes and of ada restroom in the elevator lobby, space is currently unoccupied. mep include. any alteration to sprinkler & life safety system will be under seperate permit.Details
#1900- new work consists of limited demo & new ceiling height partitions, doors, frames and hardware, millwork, power/data, finishes and of ada restroom in the elevator lobby, space is currently unoccupied. mep include. any alteration to sprinkler & life safety system will be under seperate permit. | $620,000 |
| Jan 27, 2017 | Completed final sign-off Apr 2017 | 220 Post St | soft demo ab-017. demoltion or removal of extg flooring, extg casework extg interior partition walls, extg ceiling lights and soffits, and extg cladding to structural. exit enclosure must remain.Details
soft demo ab-017. demoltion or removal of extg flooring, extg casework extg interior partition walls, extg ceiling lights and soffits, and extg cladding to structural. exit enclosure must remain. | $30,000 |
| Jan 25, 2017 | Completed final sign-off May 2017 | 601 California St | 21st floor - revision to pa #201601076559: change location of elevator lobby door. change from s door back to regular elevator lobby doorsDetails
21st floor - revision to pa #201601076559: change location of elevator lobby door. change from s door back to regular elevator lobby doors | |
| Dec 14, 2016 | Completed final sign-off Nov 2018 | 399 Geary St | demo of indicated floor slabs for proposed elevator shaft & stair opening. demo of vault & stair cases. demo of (e) ceilings, partitions & the removal of (e) flooring. structural shoring on separate permit. space to remain vacant per sfbc ab-017.Details
demo of indicated floor slabs for proposed elevator shaft & stair opening. demo of vault & stair cases. demo of (e) ceilings, partitions & the removal of (e) flooring. structural shoring on separate permit. space to remain vacant per sfbc ab-017. | $5,000 |
| Nov 30, 2016 | Completed final sign-off Feb 2017 | 2 Embarcadero Center | promenade - new electrical for gym equipment, new accessible restroom, new finishes, and paint by owner. expansion of extg gym to include 5000 sq ft of new space. total gym use 17,000 sf. n/a for maherDetails
promenade - new electrical for gym equipment, new accessible restroom, new finishes, and paint by owner. expansion of extg gym to include 5000 sq ft of new space. total gym use 17,000 sf. n/a for maher | $75,000 |
| Nov 23, 2016 | Completed final sign-off Apr 2019 | 399 Geary St | change of occupancy. shell & core remodel & (n)3/f -no final completion until all related ti permits are complete. remodel an "e" 2 story concrete & masonry building. addition of partially enclosed 3rd flr with an open air-roof terrace. new elevation, new exit stairs, new mep.Details
change of occupancy. shell & core remodel & (n)3/f -no final completion until all related ti permits are complete. remodel an "e" 2 story concrete & masonry building. addition of partially enclosed 3rd flr with an open air-roof terrace. new elevation, new exit stairs, new mep. | $2,000,000 |
| Nov 15, 2016 | Completed final sign-off May 2017 | 601 California St | revision to pa 2016-0418-4999 install small interior hutz unit for idf & av room. install 2 208-120v panel boardDetails
revision to pa 2016-0418-4999 install small interior hutz unit for idf & av room. install 2 208-120v panel board | $30,000 |
| Nov 15, 2016 | Completed final sign-off May 2017 | 601 California St | electrical work on floor 23 - install 600a panel for new ups & mechanical equipment. new ups system for equipment on floor 21 & 22. convert new ac power to mechanical equipment on floor 23 revision to 2016-0405-3932Details
electrical work on floor 23 - install 600a panel for new ups & mechanical equipment. new ups system for equipment on floor 21 & 22. convert new ac power to mechanical equipment on floor 23 revision to 2016-0405-3932 | $42,000 |
| Nov 15, 2016 | Completed final sign-off May 2017 | 601 California St | revision to pa 2016-0425-5908. install small interior hvac unit for idf and av closet. install 2 208/120 u panel boards.Details
revision to pa 2016-0425-5908. install small interior hvac unit for idf and av closet. install 2 208/120 u panel boards. | $30,000 |
| Oct 20, 2016 | Completed final sign-off Jan 2017 | 601 California St | install 9 new fsd's & associated duct & rated enclosure at 4 corner vertical shaftsDetails
install 9 new fsd's & associated duct & rated enclosure at 4 corner vertical shafts | $30,000 |
| Sep 23, 2016 | Completed final sign-off Mar 2017 | 210 Post St | demo of indicated floor slabs for staircase opening. demo of indicated guardrails at mezzanine. demo of selected vaults & stairs ref 2015 0727 2539Details
demo of indicated floor slabs for staircase opening. demo of indicated guardrails at mezzanine. demo of selected vaults & stairs ref 2015 0727 2539 | $5,000 |
| Sep 8, 2016 | Completed final sign-off Jan 2017 | 601 California St | 18th floor - work consists of limited demo & new ceiling height partitions, doors, frames & hardware, millwork, power/data & finishes. space is currently unoccupied. any alterations to mep, sprinkler & life safety will be under separate permit.Details
18th floor - work consists of limited demo & new ceiling height partitions, doors, frames & hardware, millwork, power/data & finishes. space is currently unoccupied. any alterations to mep, sprinkler & life safety will be under separate permit. | $200,000 |
| Sep 6, 2016 | Completed final sign-off Mar 2017 | 601 California St | flrs: 21,22&23: provide environmental control (5 split ac units) for idf/mdf/ups/av rooms.work associated with 201605056602,201606230658 and 201605056607; not a computer toom per ab 060.Details
flrs: 21,22&23: provide environmental control (5 split ac units) for idf/mdf/ups/av rooms.work associated with 201605056602,201606230658 and 201605056607; not a computer toom per ab 060. | $52,000 |
| Aug 8, 2016 | Completed final sign-off Mar 2017 | 601 California St | 21st & 22nd floor - stairs between level 21 & 22. this work associated with #201601076559 & 3201601227687.Details
21st & 22nd floor - stairs between level 21 & 22. this work associated with #201601076559 & 3201601227687. | $40,000 |
| Jun 30, 2016 | Completed final sign-off Jul 2016 | 233 Maple St | revision to app#2014-0624-9281 s2. this change includes a revision to the egress route from the bldg as discussed with the bldg inspector.Details
revision to app#2014-0624-9281 s2. this change includes a revision to the egress route from the bldg as discussed with the bldg inspector. | |
| Jun 30, 2016 | Completed final sign-off Dec 2017 | 1201 Bryant St | building interior alterations. work includes (n) bathrooms, elevator & core build-out. no change in area, use or occupancy classification. exterior work & barrier removal under separate permit. mep deferred.Details
building interior alterations. work includes (n) bathrooms, elevator & core build-out. no change in area, use or occupancy classification. exterior work & barrier removal under separate permit. mep deferred. | $3,200,000 |
| Jun 23, 2016 | Completed final sign-off May 2017 | 601 California St | 22/f- new mechanical system on 22 floor associated with 2016 0122 7687Details
22/f- new mechanical system on 22 floor associated with 2016 0122 7687 | $204,000 |
| Jun 23, 2016 | Completed final sign-off Feb 2017 | 601 California St | 22nd flr: revision to pa 2016-0122-7687, provide rated construction between 2 vertical duct connections.Details
22nd flr: revision to pa 2016-0122-7687, provide rated construction between 2 vertical duct connections. | $15,000 |
| Jun 7, 2016 | Completed final sign-off Feb 2017 | 2000 Fillmore St | t.i. to (e) retail space. (n) interior lighting & power, (n) mech, (n) partitions, finishes & fixtures. minor structural modifications to mezzanine. minor modifications to (e) storefront windows. signage under sep permit. this follows an approved conditional use for formula retail. ** maher: n/a **Details
t.i. to (e) retail space. (n) interior lighting & power, (n) mech, (n) partitions, finishes & fixtures. minor structural modifications to mezzanine. minor modifications to (e) storefront windows. signage under sep permit. this follows an approved conditional use for formula retail. ** maher: n/a ** | $173,000 |
| Jun 3, 2016 | Completed final sign-off Aug 2016 | 2000 Fillmore St | ground floor: non-structural interior demolition of display fixtures, finishes, light fixtures & plumbing fixtures. accessibility features will be provided in subsequent bldg permit per sfbc ab-017. n/a maher ordinanceDetails
ground floor: non-structural interior demolition of display fixtures, finishes, light fixtures & plumbing fixtures. accessibility features will be provided in subsequent bldg permit per sfbc ab-017. n/a maher ordinance | $8,000 |