25 permits since 2000: 8 completed, 12 never finaled, 5 expired or cancelled.
Of the 12 never-finaled permits, 3 are 5 to 10 years old, 9 are over 10 years old.
This is the city’s permit record, not a license check. It does not show whether the state license is active, bonded or insured. How to read these records
Permits filed each year
How long permits take
Each point is the quarter the permits were filed, for all building permits across San Francisco. A median counts only permits that have finished, so the shaded recent quarters look faster than they will end up: their slow permits have not finished yet. Hover a point for the slowest 10%. Gaps mean fewer than 5 permits. A rise in the issue line is the city’s review backlog, not the contractor.
Most recent permits
| Filed | Outcome | Address | Work described on the permit | Declared cost |
|---|---|---|---|---|
| Feb 9, 2021 | Never finaled issued Feb 2021, no final | 915 Franklin St | unit 304: replace kitchen cabinets. remodel kitdchen and one bathroom. no change to layout of walls and openings. maintain 1 hr separation between units at area of work.Details
unit 304: replace kitchen cabinets. remodel kitdchen and one bathroom. no change to layout of walls and openings. maintain 1 hr separation between units at area of work. | $18,000 |
| Feb 9, 2021 | Never finaled issued Feb 2021, no final | 15 Guerrero St | unit 4: remodel kitdchen and one bathroom. no change to layout of walls and openings. maintain 1 hr separation between units at area of work.Details
unit 4: remodel kitdchen and one bathroom. no change to layout of walls and openings. maintain 1 hr separation between units at area of work. | $18,000 |
| Dec 15, 2020 | Never finaled issued Dec 2020, no final | 915 Franklin St | renovate kitchen, replace bathroom vanity, plumbing and electrical as needed in units# 401 and 2012. no layout change.Details
renovate kitchen, replace bathroom vanity, plumbing and electrical as needed in units# 401 and 2012. no layout change. | $24,000 |
| Jan 7, 2020 | Expired or cancelled expired Feb 2021 | 915 Franklin St | units 305 and 405. renovate 2 kitchens and 2 bathrooms. upgrade electrical and plumbing as neededDetails
units 305 and 405. renovate 2 kitchens and 2 bathrooms. upgrade electrical and plumbing as needed | $32,000 |
| Dec 17, 2019 | Expired or cancelled expired Feb 2021 | 915 Franklin St | to obtain final inspection for work approved under pa# 201509237758. units 101 and 104Details
to obtain final inspection for work approved under pa# 201509237758. units 101 and 104 | |
| Mar 19, 2018 | Completed final sign-off Apr 2018 | 915 Franklin St | replace garage door leading to back stairs. replace boiler room door, both are to be fire-rated in response to notice #201725171 1-hour door.Details
replace garage door leading to back stairs. replace boiler room door, both are to be fire-rated in response to notice #201725171 1-hour door. | $1,800 |
| Feb 13, 2018 | Completed final sign-off Mar 2018 | 21 Dalewood Wy | to obtain final inspection for work approved under pa# 201609268774. all work is completeDetails
to obtain final inspection for work approved under pa# 201609268774. all work is complete | |
| May 23, 2017 | Completed final sign-off Dec 2024 | 3365 Cesar Chavez St | add unit per ordinance no. 162-16. add two dwelling units to 1st flr as result of seismic retrofit pa#201601147099. n/a for maher ordinance.Details
add unit per ordinance no. 162-16. add two dwelling units to 1st flr as result of seismic retrofit pa#201601147099. n/a for maher ordinance. | $45,000 |
| Sep 26, 2016 | Expired or cancelled expired Mar 2018 | 21 Dalewood Wy | porposed remodeling (e) kitchen, bath room, dining room and living room at 2nd floor. installing new bedroom and bathroom at 1st floor. rebuild (e) interior stairs. new electrical for whole buildingDetails
porposed remodeling (e) kitchen, bath room, dining room and living room at 2nd floor. installing new bedroom and bathroom at 1st floor. rebuild (e) interior stairs. new electrical for whole building | $88,000 |
| Jun 21, 2016 | Never finaled issued Jun 2016, no final | 449 Bella Vista Wy | replace 2x6 floor decking & handrail on exterior deck (8'x29') with similar 2x6 redwood decking not visible to the street (replace less than 50% of total deck elements.)Details
replace 2x6 floor decking & handrail on exterior deck (8'x29') with similar 2x6 redwood decking not visible to the street (replace less than 50% of total deck elements.) | $4,500 |
| Sep 9, 2015 | Never finaled issued Sep 2015, no final | 419 Lansdale Av | repair leaking shower pan, replace shower faucet, replace toilet, vanity and tileDetails
repair leaking shower pan, replace shower faucet, replace toilet, vanity and tile | $3,500 |
| Feb 28, 2012 | Never finaled issued Feb 2012, no final | 137 Idora Av | to obtain final inspection for work approved under pa # 200807176995. all work is complete.Details
to obtain final inspection for work approved under pa # 200807176995. all work is complete. | |
| Feb 28, 2012 | Never finaled issued Feb 2012, no final | 137 Idora Av | to obtain final inspection for work approved under pa # 200907213108. all work is complete.Details
to obtain final inspection for work approved under pa # 200907213108. all work is complete. | |
| Feb 28, 2012 | Never finaled issued Feb 2012, no final | 137 Idora Av | to obtain final inspection for work approved under pa # 200902242671. all work is complete.Details
to obtain final inspection for work approved under pa # 200902242671. all work is complete. | |
| Oct 18, 2011 | Never finaled issued Oct 2011, no final | 2009 Vallejo St | apt#1 new kitcen cabinets, countertops, flooring, new bathroom tile, sink, flooring, paint. unit #4 new kitchen, cabinets, counter tops, flooring, new bathroom tile, sink, flooring, paint unit. no structural work.Details
apt#1 new kitcen cabinets, countertops, flooring, new bathroom tile, sink, flooring, paint. unit #4 new kitchen, cabinets, counter tops, flooring, new bathroom tile, sink, flooring, paint unit. no structural work. | $28,000 |
| May 11, 2010 | Completed final sign-off Sep 2010 | 1018 Bush St | proposed a office at (e) ground floor, change of use "m" to "b" over 12 units of residential.Details
proposed a office at (e) ground floor, change of use "m" to "b" over 12 units of residential. | $8,000 |
| Jul 21, 2009 | Never finaled issued Aug 2009, no final | 137 Idora Av | structural upgrade; replace stucco, replace windows + doors. revision to application #2009/0224/2671.(install 1/2" cdx plywood sheathing to strengthened walls) per plan.Details
structural upgrade; replace stucco, replace windows + doors. revision to application #2009/0224/2671.(install 1/2" cdx plywood sheathing to strengthened walls) per plan. | $100,000 |
| Mar 11, 2009 | Completed final sign-off Mar 2009 | 1020 Bush St | replace missing plaster ceiling with 5/8" firerated sheetrock in utility room. 10x12.Details
replace missing plaster ceiling with 5/8" firerated sheetrock in utility room. 10x12. | $800 |
| Feb 24, 2009 | Never finaled issued Feb 2009, no final | 137 Idora Av | proposed remodeling extg bath room, kitchen, dining room & living room at 2nd floor. install new bath room, family rm, play rm, laundry rm, and computer room at 1st floor. rebuild extg interior and exterior stairs. structural change to extg bldg. new skylight at kchn area.Details
proposed remodeling extg bath room, kitchen, dining room & living room at 2nd floor. install new bath room, family rm, play rm, laundry rm, and computer room at 1st floor. rebuild extg interior and exterior stairs. structural change to extg bldg. new skylight at kchn area. | $55,000 |
| Jul 17, 2008 | Expired or cancelled expired Apr 2012 | 137 Idora Av | remodel kitchen & bathroom, no exterior changes, no layout change & no opening changes; kitchen is located on the middle level and bathroom is on top levelDetails
remodel kitchen & bathroom, no exterior changes, no layout change & no opening changes; kitchen is located on the middle level and bathroom is on top level | $15,000 |
| May 15, 2008 | Completed final sign-off Jan 2009 | 360 Valdez Av | 2 (n) bedrooms, storage room, family room, utility room @ ground floor. reduced (e) bathroom, and rebuild (e) stairs. install new windows @ ground floor. install new beam @ ground floor.Details
2 (n) bedrooms, storage room, family room, utility room @ ground floor. reduced (e) bathroom, and rebuild (e) stairs. install new windows @ ground floor. install new beam @ ground floor. | $35,000 |
| Apr 24, 2007 | Expired or cancelled expired Jun 2008 | 360 Valdez Av | replace kitchen cabinets & counter tops, paint, on the main floor.Details
replace kitchen cabinets & counter tops, paint, on the main floor. | $8,000 |
| Apr 23, 2007 | Completed final sign-off Jan 2008 | 337 Molimo Dr | revisions to 200605161732. widen family room, remove stairs at backDetails
revisions to 200605161732. widen family room, remove stairs at back | |
| Dec 12, 2005 | Never finaled issued Dec 2005, no final | 1020 Bush St | remodel r baths, enew fistures, toilet, tub, tile for apts 3, 5, 10, 11. 4 vacant units. remove a kitchen and acap off gas.Details
remodel r baths, enew fistures, toilet, tub, tile for apts 3, 5, 10, 11. 4 vacant units. remove a kitchen and acap off gas. | $18,000 |
| Jul 17, 2003 | Completed final sign-off Apr 2004 | 429 39th Av | convert (e) bsmt into family room, new stairs fm bsmt to 1/f, widen (e)stairs, relocate washer/dryerDetails
convert (e) bsmt into family room, new stairs fm bsmt to 1/f, widen (e)stairs, relocate washer/dryer | $24,000 |