Permit GraphShortlistSan Francisco building permits since 2000

E & C Builders Inc

Contractor license
1042374
State license record
Based in
Turlock
On San Francisco permits
Dec 2019 to Sep 2026
Last 24 months
9 permits filed

29 permits since 2000: 11 completed, 9 in progress, 6 never finaled, 3 expired or cancelled.

Of the 6 never-finaled permits, 6 are 3 to 5 years old.

CompletedIn progressNever finaledExpired or cancelled

This is the city’s permit record, not a license check. It does not show whether the state license is active, bonded or insured. How to read these records

Permits filed each year

How long permits take

Median days to final inspection, citywideMedian days to permit issued, citywideThis contractor’s finished permits

Each point is the quarter the permits were filed, for all building permits across San Francisco. A median counts only permits that have finished, so the shaded recent quarters look faster than they will end up: their slow permits have not finished yet. Hover a point for the slowest 10%. Gaps mean fewer than 5 permits. A rise in the issue line is the city’s review backlog, not the contractor.

Most recent permits

AllStairs 1Kitchen remodel 5
FiledOutcomeAddressWork described on the permitDeclared cost
Sep 8, 2026In progress
issued Sep 2026
121 07th Stto obtain final inspection for work approved under pa# 202310279705 all work completed
Details
Permit
202609087808
Status
issued
Filed
Sep 8, 2026
Permit issued
Sep 14, 2026
Address
121 07th St

to obtain final inspection for work approved under pa# 202310279705 all work completed

Open the permit page

Aug 5, 2026In progress
issued Aug 2026
940 Sutter Strecommencement and completion of work approved under 202208059981 and 202401103722
Details
Permit
202608056088
Status
issued
Filed
Aug 5, 2026
Permit issued
Aug 31, 2026
Declared cost
$6,500
Address
940 Sutter St

recommencement and completion of work approved under 202208059981 and 202401103722

Open the permit page

$6,500
Jul 1, 2026In progress
issued Jul 2026
940 Sutter Strevision 202311271378 to document fire dept assembly stamp
Details
Permit
202607014461
Status
issued
Filed
Jul 1, 2026
Permit issued
Jul 22, 2026
Address
940 Sutter St

revision 202311271378 to document fire dept assembly stamp

Open the permit page

Jun 25, 2026In progress
issued Jul 2026
121 07th Strevision to 202312082184, level 1. to document fire assembly stamp.
Details
Permit
202606253914
Status
issued
Filed
Jun 25, 2026
Permit issued
Jul 10, 2026
Address
121 07th St

revision to 202312082184, level 1. to document fire assembly stamp.

Open the permit page

Jun 18, 2026In progress
filed Jun 2026, not yet issued
121 07th Stto renew pa#202401194324
Details
Permit
202606183513
Status
filed
Filed
Jun 18, 2026
Address
121 07th St

to renew pa#202401194324

Open the permit page

Oct 24, 2025Completed
final sign-off Aug 2026
121 07th Stto obtain final inspection for work approved under pa# 202403208290. all work is complete.
Details
Permit
202510248117
Status
complete
Filed
Oct 24, 2025
Permit issued
Oct 28, 2025
Final sign-off
Aug 19, 2026
Address
121 07th St

to obtain final inspection for work approved under pa# 202403208290. all work is complete.

Open the permit page

Sep 9, 2025Completed
final sign-off Sep 2026
121 07th Strevision to 202312082184. revise (e) doors to remain, finishes, kitchen equipment, venting. remove (e) prephood.
Details
Permit
202509094857
Status
complete
Filed
Sep 9, 2025
Permit issued
Nov 25, 2025
Final sign-off
Sep 1, 2026
Address
121 07th St

revision to 202312082184. revise (e) doors to remain, finishes, kitchen equipment, venting. remove (e) prephood.

Open the permit page

May 5, 2025In progress
issued Jun 2026
121 07th Stemergency evacuation signage public areas
Details
Permit
202505055803
Status
issued
Filed
May 5, 2025
Permit issued
Jun 4, 2026
Declared cost
$1,000
Address
121 07th St

emergency evacuation signage public areas

Open the permit page

$1,000
Mar 5, 2025Completed
final sign-off Sep 2025
940 Sutter Strevision to permit 202311271378. add push button actuator in lieu of pushside clearance.
Details
Permit
202503051654
Status
complete
Filed
Mar 5, 2025
Permit issued
Mar 24, 2025
Final sign-off
Sep 24, 2025
Address
940 Sutter St

revision to permit 202311271378. add push button actuator in lieu of pushside clearance.

Open the permit page

Mar 25, 2024Completed
final sign-off Jul 2026
121 07th Stfloors 1-2 bldg a. install (n) temporary heaters and provide power connections. max. 180 days per cbc 108
Details
Permit
202403258573
Status
complete
Filed
Mar 25, 2024
Permit issued
Apr 12, 2024
Final sign-off
Jul 14, 2026
Declared cost
$133,000
Address
121 07th St

floors 1-2 bldg a. install (n) temporary heaters and provide power connections. max. 180 days per cbc 108

Open the permit page

$133,000
Mar 25, 2024Completed
final sign-off Jul 2026
121 07th Stfloors 3-4 bldg a. install (n) temporary heaters and prvid power connections
Details
Permit
202403258575
Status
complete
Filed
Mar 25, 2024
Permit issued
Apr 12, 2024
Final sign-off
Jul 14, 2026
Declared cost
$266,000
Address
121 07th St

floors 3-4 bldg a. install (n) temporary heaters and prvid power connections

Open the permit page

$266,000
Mar 20, 2024Expired or cancelled
expired Aug 2026
121 07th Strevision to pa 202312041851 - minor project structural modifications to new guest rooms; floors 2-4 to lobby and to public restrooms;
Details
Permit
202403208290
Status
expired
Filed
Mar 20, 2024
Permit issued
Apr 18, 2024
Address
121 07th St

revision to pa 202312041851 - minor project structural modifications to new guest rooms; floors 2-4 to lobby and to public restrooms;

Open the permit page

Feb 23, 2024Completed
final sign-off Jan 2026
112 07th Stdeferred m.e.p for pa 202312223043
Details
Permit
202402236475
Status
complete
Filed
Feb 23, 2024
Permit issued
Apr 12, 2024
Final sign-off
Jan 20, 2026
Declared cost
$96,341
Address
112 07th St

deferred m.e.p for pa 202312223043

Open the permit page

$96,341
Jan 19, 2024Completed
final sign-off Aug 2026
121 07th Stlevels 2-4 deferred mep for pa 202312041851
Details
Permit
202401194324
Status
complete
Filed
Jan 19, 2024
Permit issued
Mar 6, 2024
Final sign-off
Aug 19, 2026
Declared cost
$369,863
Address
121 07th St

levels 2-4 deferred mep for pa 202312041851

Open the permit page

$369,863
Jan 10, 2024In progress
issued Jan 2024
940 Sutter Stdeferred electrical and plumbing work on extg bar and kitchen, ti under pa#202311271378
Details
Permit
202401103722
Status
issued
Filed
Jan 10, 2024
Permit issued
Jan 30, 2024
Declared cost
$38,759
Address
940 Sutter St

deferred electrical and plumbing work on extg bar and kitchen, ti under pa#202311271378

Open the permit page

$38,759
Dec 22, 2023Completed
final sign-off Sep 2026
112 07th Stti modify 5 extg guest suites and add 5 new guest rooms, new/renovated doors, walls, finishes, mep and fire protection. modify extg parking and lobby for ada. mep and fire deferred.
Details
Permit
202312223043
Status
complete
Filed
Dec 22, 2023
Permit issued
Feb 23, 2024
Final sign-off
Sep 10, 2026
Declared cost
$195,358
Address
112 07th St

ti modify 5 extg guest suites and add 5 new guest rooms, new/renovated doors, walls, finishes, mep and fire protection. modify extg parking and lobby for ada. mep and fire deferred.

Open the permit page

$195,358
Dec 8, 2023Completed
final sign-off Apr 2026
121 07th St1st fl ti. minor demo and interior construction, finishes, m ep. minor cosmetic exterior changes. no structural
Details
Permit
202312082184
Status
complete
Filed
Dec 8, 2023
Permit issued
Apr 26, 2024
Final sign-off
Apr 21, 2026
Declared cost
$290,000
Address
121 07th St

1st fl ti. minor demo and interior construction, finishes, m ep. minor cosmetic exterior changes. no structural

Open the permit page

$290,000
Dec 4, 2023Completed
final sign-off Aug 2026
121 07th Strenovate (17) guestrooms, including ada upgrades. convert (e) suites into floors 2-4. (9) new guest rooms, including (n) walls, doors, windows, finishes, mewp, ada upgrades to (e) lobby, public restrooms, park. no modifications to primary structure system. mep deferred.
Details
Permit
202312041851
Status
complete
Filed
Dec 4, 2023
Permit issued
Mar 6, 2024
Final sign-off
Aug 19, 2026
Declared cost
$290,000
Address
121 07th St

renovate (17) guestrooms, including ada upgrades. convert (e) suites into floors 2-4. (9) new guest rooms, including (n) walls, doors, windows, finishes, mewp, ada upgrades to (e) lobby, public restrooms, park. no modifications to primary structure system. mep deferred.

Open the permit page

$290,000
Nov 27, 2023In progress
issued Jan 2024
940 Sutter Stinterior renovation e bars & kitchen. no structural change. mep deferred
Details
Permit
202311271378
Status
issued
Filed
Nov 27, 2023
Permit issued
Jan 11, 2024
Declared cost
$250,000
Address
940 Sutter St

interior renovation e bars & kitchen. no structural change. mep deferred

Open the permit page

$250,000
Oct 27, 2023In progress
issued Mar 2024
121 07th Stelectrical only new distribution panels & feeders. upgrade (e) electrical panel boards.
Details
Permit
202310279705
Status
issued
Filed
Oct 27, 2023
Permit issued
Mar 7, 2024
Declared cost
$25,000
Address
121 07th St

electrical only new distribution panels & feeders. upgrade (e) electrical panel boards.

Open the permit page

$25,000
Jul 11, 2023Never finaled
issued Sep 2023, no final
940 Sutter St3rd and 4th floors: building mep upgrades.no architectural work.
Details
Permit
202307111884
Status
issued
Filed
Jul 11, 2023
Permit issued
Sep 13, 2023
Declared cost
$198,000
Address
940 Sutter St

3rd and 4th floors: building mep upgrades.no architectural work.

Open the permit page

$198,000
Jul 11, 2023Never finaled
issued Sep 2023, no final
940 Sutter St1st and 2nd floors: building mep upgrades.no architectural. ref to 201912311068 lobby & mezz remodel
Details
Permit
202307111882
Status
issued
Filed
Jul 11, 2023
Permit issued
Sep 13, 2023
Declared cost
$198,000
Address
940 Sutter St

1st and 2nd floors: building mep upgrades.no architectural. ref to 201912311068 lobby & mezz remodel

Open the permit page

$198,000
Jul 11, 2023Never finaled
issued Sep 2023, no final
940 Sutter St7/f & 8/f: building mep upgrades. no architectural work. new roof equpment. (entire building upgrade in separate permits)
Details
Permit
202307111891
Status
issued
Filed
Jul 11, 2023
Permit issued
Sep 13, 2023
Declared cost
$198,000
Address
940 Sutter St

7/f & 8/f: building mep upgrades. no architectural work. new roof equpment. (entire building upgrade in separate permits)

Open the permit page

$198,000
Jul 11, 2023Never finaled
issued Sep 2023, no final
940 Sutter St5/f & 6/f: mep upgrades. no architectural work.
Details
Permit
202307111890
Status
issued
Filed
Jul 11, 2023
Permit issued
Sep 13, 2023
Declared cost
$198,000
Address
940 Sutter St

5/f & 6/f: mep upgrades. no architectural work.

Open the permit page

$198,000
Apr 17, 2023Completed
final sign-off Jul 2026
940 Sutter Stin-kind window replacement, remove existing aluminum windows in guest rooms from north elevation lvls 1-8 and interior court yard elevations lvls 2-8, no increase in sqft, no change to egress. 125 windows total
Details
Permit
202304175883
Status
complete
Filed
Apr 17, 2023
Permit issued
Aug 1, 2023
Final sign-off
Jul 7, 2026
Declared cost
$40,000
Address
940 Sutter St

in-kind window replacement, remove existing aluminum windows in guest rooms from north elevation lvls 1-8 and interior court yard elevations lvls 2-8, no increase in sqft, no change to egress. 125 windows total

Open the permit page

$40,000
Nov 22, 2022Expired or cancelled
withdrawn Jun 2023
940 Sutter Stlobby/reception area construction of (e) fitness center and (e) guestroom 102. create new kitchen and adjusting of office space. the 2nd fl renovation included removing 1 guestroom and converting it into small lounge area.
Details
Permit
202211227047
Status
withdrawn
Filed
Nov 22, 2022
Declared cost
$300,000
Address
940 Sutter St

lobby/reception area construction of (e) fitness center and (e) guestroom 102. create new kitchen and adjusting of office space. the 2nd fl renovation included removing 1 guestroom and converting it into small lounge area.

Open the permit page

$300,000
Aug 5, 2022Never finaled
issued May 2023, no final
940 Sutter Stadd ada chair lift at entry (platform lift) demolish existing entry stair to accomodate new platform lift. build new stairs.
Details
Permit
202208059981
Status
issued
Filed
Aug 5, 2022
Permit issued
May 12, 2023
Declared cost
$60,000
Address
940 Sutter St

add ada chair lift at entry (platform lift) demolish existing entry stair to accomodate new platform lift. build new stairs.

Open the permit page

$60,000
Dec 31, 2019Never finaled
issued Aug 2023, no final
940 Sutter Strenovation of the extg vertigo hotel. work is being done to floors 1-2 only. renovations on level, include to lobby/reception area, moving fitness center to new location. adjusting small office space and adding a small kitchen. the level 2 renovations include coverting guestroom to lounge.
Details
Permit
201912311068
Status
issued
Filed
Dec 31, 2019
Permit issued
Aug 1, 2023
Declared cost
$75,000
Address
940 Sutter St

renovation of the extg vertigo hotel. work is being done to floors 1-2 only. renovations on level, include to lobby/reception area, moving fitness center to new location. adjusting small office space and adding a small kitchen. the level 2 renovations include coverting guestroom to lounge.

Open the permit page

$75,000
Dec 31, 2019Expired or cancelled
cancelled Jan 2026
121 07th Strenovation of the (e) american hotel scope includes modifying 8 (e) guest rooms and adding 12 new guest room througout levels 2-4 no increase of sf to building
Details
Permit
201912311069
Status
cancelled
Filed
Dec 31, 2019
Declared cost
$290,000
Address
121 07th St

renovation of the (e) american hotel scope includes modifying 8 (e) guest rooms and adding 12 new guest room througout levels 2-4 no increase of sf to building

Open the permit page

$290,000