- 0 permits filed
5 permits since 2000: 4 completed, 1 in progress.
This is the city’s permit record, not a license check. It does not show whether the state license is active, bonded or insured. How to read these records
Permits filed each year
How long permits take
Each point is the quarter the permits were filed, for all building permits across San Francisco. A median counts only permits that have finished, so the shaded recent quarters look faster than they will end up: their slow permits have not finished yet. Hover a point for the slowest 10%. Gaps mean fewer than 5 permits. A rise in the issue line is the city’s review backlog, not the contractor. Too few of this contractor’s permits have finished to plot them.
Most recent permits
| Filed | Outcome | Address | Work described on the permit | Declared cost |
|---|---|---|---|---|
| May 13, 2024 | In progress issued May 2024 | 3250 19th Av | ref 202308043739- install of (n) underground fire line from the backflow to the point of conneciton in the basementDetails
ref 202308043739- install of (n) underground fire line from the backflow to the point of conneciton in the basement | $78,491 |
| Aug 4, 2023 | Completed final sign-off Sep 2025 | 3250 19th Av | installation of a new fire sprinkler system as part of a modernization project with a new underground service. ref pa202209082129.Details
installation of a new fire sprinkler system as part of a modernization project with a new underground service. ref pa202209082129. | $477,000 |
| Mar 20, 2023 | Completed final sign-off Jan 2024 | 1011 Turk St | modification to the existing fire sprinkler system for new offices and ceiling elevations.Details
modification to the existing fire sprinkler system for new offices and ceiling elevations. | $24,627 |
| Feb 25, 2021 | Completed final sign-off Sep 2021 | 1011 Turk St | remove existing sprinkler at the top of elevator hoistway and plug off.Details
remove existing sprinkler at the top of elevator hoistway and plug off. | $4,987 |
| Feb 8, 2021 | Completed final sign-off Aug 2021 | 425 07th St | relocate 30 heads to new locations in new t-bar ceiling replace 1 dry pendent head add one (1) new head 3rd floor kitchen remodelDetails
relocate 30 heads to new locations in new t-bar ceiling replace 1 dry pendent head add one (1) new head 3rd floor kitchen remodel |