Mar 2025 to Mar 2025
Last 24 months
2 permits filed

2 permits since 2000: 2 completed.

CompletedIn progressNever finaledExpired or cancelled

This is the city’s permit record, not a license check. It does not show whether the state license is active, bonded or insured. How to read these records

Permits filed each year

How long permits take

Median days to final inspection, citywideMedian days to permit issued, citywide

Each point is the quarter the permits were filed, for all building permits across San Francisco. A median counts only permits that have finished, so the shaded recent quarters look faster than they will end up: their slow permits have not finished yet. Hover a point for the slowest 10%. Gaps mean fewer than 5 permits. A rise in the issue line is the city’s review backlog, not the contractor. Too few of this contractor’s permits have finished to plot them.

Most recent permits

All
FiledOutcomeAddressWork described on the permitDeclared cost
Mar 19, 2025Completed
final sign-off Jan 2026
365 Main Stdemo of some rpp panels. reusing (e) rpp panels & upsizing them from 225a. reusing pdu's and submitting single line diagrams, power and demo plans re-using majority of (e) single line diagram
Details
Permit
202503192608
Status
complete
Filed
Mar 19, 2025
Permit issued
May 14, 2025
Final sign-off
Jan 6, 2026
Declared cost
$270,000
Address
365 Main St

demo of some rpp panels. reusing (e) rpp panels & upsizing them from 225a. reusing pdu's and submitting single line diagrams, power and demo plans re-using majority of (e) single line diagram

Open the permit page

$270,000
Mar 19, 2025Completed
final sign-off Jan 2026
365 Main Stdemo of pdu/sts. adding (n) cupsized pdu & sts. addition of rpp panels. demo of single line diagram with exception of (e) rpp panels and switch boards c1 and cr1
Details
Permit
202503192611
Status
complete
Filed
Mar 19, 2025
Permit issued
May 14, 2025
Final sign-off
Jan 6, 2026
Declared cost
$680,000
Address
365 Main St

demo of pdu/sts. adding (n) cupsized pdu & sts. addition of rpp panels. demo of single line diagram with exception of (e) rpp panels and switch boards c1 and cr1

Open the permit page

$680,000