Colony Construction
- Based in
- Sacramento
- On San Francisco permits
- Oct 2019 to Jun 2021
- Last 24 months
- 0 permits filed
2 permits since 2000: 2 completed.
This is the city’s permit record, not a license check. It does not show whether the state license is active, bonded or insured. How to read these records
Permits filed each year
How long permits take
Each point is the quarter the permits were filed, for all building permits across San Francisco. A median counts only permits that have finished, so the shaded recent quarters look faster than they will end up: their slow permits have not finished yet. Hover a point for the slowest 10%. Gaps mean fewer than 5 permits. A rise in the issue line is the city’s review backlog, not the contractor. Too few of this contractor’s permits have finished to plot them.
Most recent permits
| Filed | Outcome | Address | Work described on the permit | Declared cost |
|---|---|---|---|---|
| Jun 29, 2021 | Completed final sign-off Feb 2022 | 1995 15th Av | rev to pa 201910094083: change of elevator manufacturer due to field conditions requested by bid.Details
rev to pa 201910094083: change of elevator manufacturer due to field conditions requested by bid. | |
| Oct 9, 2019 | Completed final sign-off Feb 2022 | 1995 15th Av | propose new lift for personal need. the lift will be added inside of the existing house.Details
propose new lift for personal need. the lift will be added inside of the existing house. | $30,000 |