8 permits since 2000: 5 completed, 3 in progress.
This is the city’s permit record, not a license check. It does not show whether the state license is active, bonded or insured. How to read these records
Permits filed each year
How long permits take
Each point is the quarter the permits were filed, for all building permits across San Francisco. A median counts only permits that have finished, so the shaded recent quarters look faster than they will end up: their slow permits have not finished yet. Hover a point for the slowest 10%. Gaps mean fewer than 5 permits. A rise in the issue line is the city’s review backlog, not the contractor.
Most recent permits
| Filed | Outcome | Address | Work described on the permit | Declared cost |
|---|---|---|---|---|
| Jan 20, 2026 | In progress issued Jul 2026 | 4390 Cesar Chavez St | add bathroom to crawl space, add kitchenette to basement. foundation & structural work per plans. electrical & plumbing work to be carried out. adding new laundry in crawl space.Details
add bathroom to crawl space, add kitchenette to basement. foundation & structural work per plans. electrical & plumbing work to be carried out. adding new laundry in crawl space. | $222,000 |
| Nov 20, 2025 | In progress issued Jan 2026 | 570 Jersey St | kitchen and bathrooom remodel at 2nd floor. bathroom remodel at 3rd floor. reframe (e) addition at rear. partal (n) foundation. rebuilt/reconfigure stairs. (*n) doors and windows in rearDetails
kitchen and bathrooom remodel at 2nd floor. bathroom remodel at 3rd floor. reframe (e) addition at rear. partal (n) foundation. rebuilt/reconfigure stairs. (*n) doors and windows in rear | $250,000 |
| Nov 10, 2025 | Completed final sign-off Jan 2026 | 34 Lagunitas Dr | bathroom remodel in kind. electrical work, plumbing work, sheet rock & taping, tile work. size of bathroom approx 80 sq. ft. no expansion to size of original bathroom.Details
bathroom remodel in kind. electrical work, plumbing work, sheet rock & taping, tile work. size of bathroom approx 80 sq. ft. no expansion to size of original bathroom. | $32,000 |
| Aug 27, 2025 | In progress issued Aug 2025 | 4390 Cesar Chavez St | bathroom remodel in kind located on the 1st floor, approx 75 sqft. add extra lighting and outlets throughout the 1st floor approx 4 new light fixtures and 6 new outlets.Details
bathroom remodel in kind located on the 1st floor, approx 75 sqft. add extra lighting and outlets throughout the 1st floor approx 4 new light fixtures and 6 new outlets. | $35,000 |
| Apr 22, 2025 | Completed final sign-off Jun 2025 | 4390 Cesar Chavez St | bathroom remodel in kind located on 2nd floor. electrical work, plumbing work, tile work, insulation, sheetrock & taping & painting. size of bathroom 90 sq. ft.Details
bathroom remodel in kind located on 2nd floor. electrical work, plumbing work, tile work, insulation, sheetrock & taping & painting. size of bathroom 90 sq. ft. | $28,000 |
| Mar 21, 2025 | Completed final sign-off May 2026 | 520 Jersey St | new trash receptacle storage area. reconstruction of (e) exterior stair to match (e) stair dimensions/location & details. (e) landscape area to be redisigned to incorporate a new permeable terrace area of cobblestones with a seating wall & planting areaDetails
new trash receptacle storage area. reconstruction of (e) exterior stair to match (e) stair dimensions/location & details. (e) landscape area to be redisigned to incorporate a new permeable terrace area of cobblestones with a seating wall & planting area | $65,000 |
| Aug 27, 2024 | Completed final sign-off Apr 2025 | 3984 26th St | kitchen remodel in kind. bathroom remodel, add a bathroom, relocate laundry. move two doors, demo existing chimney, electrical & plumbing work. tile work, sheetrock/taping, flooring & painting. all work to be carried out on the second fl of the buildingDetails
kitchen remodel in kind. bathroom remodel, add a bathroom, relocate laundry. move two doors, demo existing chimney, electrical & plumbing work. tile work, sheetrock/taping, flooring & painting. all work to be carried out on the second fl of the building | $150,000 |
| Jan 25, 2024 | Completed final sign-off Apr 2024 | 2470 25th Av | bathroom remodel in kind- located in middle of first floor. electrical work, plumbing work, tile work, sheetrock and taping and painting. size of bathroom- 45 square foot. no expansion to size of original bathroom.Details
bathroom remodel in kind- located in middle of first floor. electrical work, plumbing work, tile work, sheetrock and taping and painting. size of bathroom- 45 square foot. no expansion to size of original bathroom. | $15,000 |