Permit GraphShortlistSan Francisco building permits since 2000

Campbell Family Electric Inc

Contractor license
876689
State license record
Based in
Tracy
On San Francisco permits
Dec 2018 to Jul 2020
Last 24 months
0 permits filed

6 permits since 2000: 4 completed, 2 never finaled.

Of the 2 never-finaled permits, 2 are 5 to 10 years old.

CompletedIn progressNever finaledExpired or cancelled

This is the city’s permit record, not a license check. It does not show whether the state license is active, bonded or insured. How to read these records

Permits filed each year

How long permits take

Median days to final inspection, citywideMedian days to permit issued, citywide

Each point is the quarter the permits were filed, for all building permits across San Francisco. A median counts only permits that have finished, so the shaded recent quarters look faster than they will end up: their slow permits have not finished yet. Hover a point for the slowest 10%. Gaps mean fewer than 5 permits. A rise in the issue line is the city’s review backlog, not the contractor. Too few of this contractor’s permits have finished to plot them.

Most recent permits

All
FiledOutcomeAddressWork described on the permitDeclared cost
Jul 23, 2020Completed
final sign-off Dec 2020
1750 Fulton Stinstall (2) ev chargers in existing parking structure
Details
Permit
202007230737
Status
complete
Filed
Jul 23, 2020
Permit issued
Oct 28, 2020
Final sign-off
Dec 3, 2020
Declared cost
$162,000
Address
1750 Fulton St

install (2) ev chargers in existing parking structure

Open the permit page

$162,000
Mar 5, 2020Completed
final sign-off Jul 2020
1150 Ocean Avreplace (2) level 2 ev chargers w/(2) level (3) ev chargers.
Details
Permit
202003056282
Status
complete
Filed
Mar 5, 2020
Permit issued
Mar 16, 2020
Final sign-off
Jul 14, 2020
Declared cost
$20,000
Address
1150 Ocean Av

replace (2) level 2 ev chargers w/(2) level (3) ev chargers.

Open the permit page

$20,000
Mar 5, 2020Completed
final sign-off Aug 2020
1000 Van Ness Avinstall (9) level 3 evs e chargers and (1) level 2 charger & require electrical equipment.
Details
Permit
202003056279
Status
complete
Filed
Mar 5, 2020
Permit issued
Mar 16, 2020
Final sign-off
Aug 18, 2020
Declared cost
$150,000
Address
1000 Van Ness Av

install (9) level 3 evs e chargers and (1) level 2 charger & require electrical equipment.

Open the permit page

$150,000
Dec 17, 2019Completed
final sign-off Jun 2020
1160 Mission Stinstall (2) l3 vehicle charging stations
Details
Permit
201912179802
Status
complete
Filed
Dec 17, 2019
Permit issued
Jan 2, 2020
Final sign-off
Jun 23, 2020
Declared cost
$48,000
Address
1160 Mission St

install (2) l3 vehicle charging stations

Open the permit page

$48,000
Feb 6, 2019Never finaled
issued Feb 2019, no final
1160 Mission Stinstall 10 electric vehicle charger and equipment
Details
Permit
201902062285
Status
issued
Filed
Feb 6, 2019
Permit issued
Feb 28, 2019
Declared cost
$115,000
Address
1160 Mission St

install 10 electric vehicle charger and equipment

Open the permit page

$115,000
Dec 10, 2018Never finaled
issued Feb 2019, no final
600 California Stinstall 10 level 3 ev chargers anx 2 level 2 chargers in e parking stalls. install evgo support equipment
Details
Permit
201812107887
Status
issued
Filed
Dec 10, 2018
Permit issued
Feb 6, 2019
Declared cost
$160,000
Address
600 California St

install 10 level 3 ev chargers anx 2 level 2 chargers in e parking stalls. install evgo support equipment

Open the permit page

$160,000