Becker Electric Inc
- Based in
- San Francisco
- On San Francisco permits
- Apr 2013 to Mar 2021
- Last 24 months
- 0 permits filed
7 permits since 2000: 6 completed, 1 never finaled.
Of the 1 never-finaled permit, 1 is 3 to 5 years old.
This is the city’s permit record, not a license check. It does not show whether the state license is active, bonded or insured. How to read these records
Permits filed each year
How long permits take
Each point is the quarter the permits were filed, for all building permits across San Francisco. A median counts only permits that have finished, so the shaded recent quarters look faster than they will end up: their slow permits have not finished yet. Hover a point for the slowest 10%. Gaps mean fewer than 5 permits. A rise in the issue line is the city’s review backlog, not the contractor.
Most recent permits
| Filed | Outcome | Address | Work described on the permit | Declared cost |
|---|---|---|---|---|
| Mar 18, 2021 | Never finaled issued Jul 2022, no final | 3455 Van Ness Av | furnishing and installing a turn-key fuel oil system per sec having a connection with the diesel generator system with a feul piping system connected to the existing fuel oil piping. pump station 2Details
furnishing and installing a turn-key fuel oil system per sec having a connection with the diesel generator system with a feul piping system connected to the existing fuel oil piping. pump station 2 | $62,000 |
| Aug 30, 2019 | Completed final sign-off Nov 2019 | 461 06th Av | revision to 201806192309. revisoi from orig permit during fire inspection to raise fuel oil vent pipes (emergency generator) install additonal bollardDetails
revision to 201806192309. revisoi from orig permit during fire inspection to raise fuel oil vent pipes (emergency generator) install additonal bollard | $7,000 |
| Jun 19, 2018 | Completed final sign-off Dec 2019 | 461 06th Av | installation of emergency generator and fuel oil delivery system. ref 201609228505Details
installation of emergency generator and fuel oil delivery system. ref 201609228505 | $90,000 |
| Mar 10, 2017 | Completed final sign-off Nov 2017 | 1067 Post St | installation of new 30kw generator, new 220 gallon diesel fuel tank, new fuel oil piping system & controls (on roof & rear elevation only), paint pipe to match exterior color. ** maher: n/a **Details
installation of new 30kw generator, new 220 gallon diesel fuel tank, new fuel oil piping system & controls (on roof & rear elevation only), paint pipe to match exterior color. ** maher: n/a ** | $175,000 |
| Dec 3, 2015 | Completed final sign-off Mar 2021 | 1419 Bryant St | 2 new stories within (e) envelope. no change in building height. renovate (e) bldg to accomodate change of use from mta facility to animal care & control. (e) brick envelop to remain with new struct support. new 2nd fl over half the ground fl w/ new interior walls &(n)struct sys to support (e) roof,Details
2 new stories within (e) envelope. no change in building height. renovate (e) bldg to accomodate change of use from mta facility to animal care & control. (e) brick envelop to remain with new struct support. new 2nd fl over half the ground fl w/ new interior walls &(n)struct sys to support (e) roof, | $26,500,000 |
| Oct 1, 2015 | Completed final sign-off Nov 2016 | 530 Sansome St | installation on c02 monitoring system (maher ordinance extended no.155-13 not requiredDetails
installation on c02 monitoring system (maher ordinance extended no.155-13 not required | $105,000 |
| Apr 19, 2013 | Completed final sign-off Dec 2013 | 135 Sanchez St | replace (e) emergency generator & manual tranfer switch with (n) generator (w/integral base tank) & automatic transfer switch.Details
replace (e) emergency generator & manual tranfer switch with (n) generator (w/integral base tank) & automatic transfer switch. | $190,000 |