On San Francisco permits
Oct 2025 to Oct 2025
Last 24 months
1 permit filed

1 permit since 2000: 1 expired or cancelled.

CompletedIn progressNever finaledExpired or cancelled

This is the city’s permit record, not a license check. It does not show whether the state license is active, bonded or insured. How to read these records

Permits filed each year

How long permits take

Median days to final inspection, citywideMedian days to permit issued, citywide

Each point is the quarter the permits were filed, for all building permits across San Francisco. A median counts only permits that have finished, so the shaded recent quarters look faster than they will end up: their slow permits have not finished yet. Hover a point for the slowest 10%. Gaps mean fewer than 5 permits. A rise in the issue line is the city’s review backlog, not the contractor. Too few of this contractor’s permits have finished to plot them.

Most recent permits

All
FiledOutcomeAddressWork described on the permitDeclared cost
Oct 22, 2025Expired or cancelled
suspend Jan 2026
330 Wilde Avsolar permit: installing 8 solar pv modules, 410 watts per module, total no. of rating 3.28 kw. mounted: roof, ballasted: n, including 2 energy storage unit, with 3.84 kwh each in capacity, ess units will be closer than 3 feet | installation of a 3.2 kw rooftop pv sys
Details
Permit
S20251020229
Status
suspend
Filed
Oct 22, 2025
Address
330 Wilde Av

solar permit: installing 8 solar pv modules, 410 watts per module, total no. of rating 3.28 kw. mounted: roof, ballasted: n, including 2 energy storage unit, with 3.84 kwh each in capacity, ess units will be closer than 3 feet | installation of a 3.2 kw rooftop pv sys

Open the permit page