Permit GraphShortlistSan Francisco building permits since 2000

Sebastian Asvaraksh

License
M36623
Look the license up with the state
Listed as
engineer
Firm
Glumac
On San Francisco permits
Nov 2013 to Nov 2017

8 permits since 2000 (engineer on 8 permits): 7 completed, 1 never finaled.

CompletedIn progressNever finaledExpired or cancelled

This is the city’s permit record, not a license check: the role and the number come from what was written on each permit (the number spelled one way). It does not show whether the license is current. How to read these records

Most recent permits

FiledOutcomeAddressContractorWork described on the permitDeclared cost
Nov 15, 2017Completed
final sign-off Jun 2019
121 Spear StBcci Construction Company4/f- partial floor t.i. includes wellness center & 2 hr. rated enclosure of stairs that will be under seperate permit. mep. included. n/a ordinance #155-13
Details
Permit
201711154071
Status
complete
Filed
Nov 15, 2017
Permit issued
Nov 28, 2017
Final sign-off
Jun 25, 2019
Declared cost
$1,700,000
Address
121 Spear St

4/f- partial floor t.i. includes wellness center & 2 hr. rated enclosure of stairs that will be under seperate permit. mep. included. n/a ordinance #155-13

Open the permit page

$1,700,000
Sep 28, 2017Never finaled
issued Sep 2017, no final
601 Montgomery StStructural & Refrigeration Mechanicalrefroof: change out old cooling towers - install new heat exchange & 2 pumps. maher na
Details
Permit
201709289777
Status
issued
Filed
Sep 28, 2017
Permit issued
Sep 29, 2017
Declared cost
$899,000
Address
601 Montgomery St

roof: change out old cooling towers - install new heat exchange & 2 pumps. maher na

Open the permit page

$899,000
Jun 19, 2017Completed
final sign-off Nov 2017
227 Front StUpcycle Builders Inc.ti of (e) ground floor space to accomodate new coffee shop. no change to exterior of bld except for ada push button & paint. maher na
Details
Permit
201706199690
Status
complete
Filed
Jun 19, 2017
Permit issued
Aug 18, 2017
Final sign-off
Nov 9, 2017
Declared cost
$75,000
Address
227 Front St

ti of (e) ground floor space to accomodate new coffee shop. no change to exterior of bld except for ada push button & paint. maher na

Open the permit page

$75,000
Dec 19, 2016Completed
final sign-off May 2017
188 The EmbarcaderoDpr Construction#420 - interior alterations including walls, coilings, flooring and casework. mechanical, electrical and plumbing work to support new interior space, demo and safe off per the demo drawings. ref. sprinkler permit app#2016-1202-4076. n/a ordinance #155-13
Details
Permit
201612195265
Status
complete
Filed
Dec 19, 2016
Permit issued
Dec 22, 2016
Final sign-off
May 3, 2017
Declared cost
$1,200,000
Address
188 The Embarcadero

#420 - interior alterations including walls, coilings, flooring and casework. mechanical, electrical and plumbing work to support new interior space, demo and safe off per the demo drawings. ref. sprinkler permit app#2016-1202-4076. n/a ordinance #155-13

Open the permit page

$1,200,000
Jun 8, 2016Completed
final sign-off Mar 2017
188 The EmbarcaderoDpr Constructionbasement & roof- m.e.p. work - new lighting fixtures, controls, power & signal outlets for central plant upgrades, replace existing mechanical equipment. ref pa #201505126148. n/a meher ordinance
Details
Permit
201606089353
Status
complete
Filed
Jun 8, 2016
Permit issued
Jun 14, 2016
Final sign-off
Mar 6, 2017
Declared cost
$3,500,000
Address
188 The Embarcadero

basement & roof- m.e.p. work - new lighting fixtures, controls, power & signal outlets for central plant upgrades, replace existing mechanical equipment. ref pa #201505126148. n/a meher ordinance

Open the permit page

$3,500,000
Mar 14, 2016Completed
final sign-off Oct 2017
685 Market StLegacy Mechanical & Energy Services, Increplace existing cooling tower, pumps and associated control. maher na
Details
Permit
201603141895
Status
complete
Filed
Mar 14, 2016
Permit issued
Mar 14, 2016
Final sign-off
Oct 20, 2017
Declared cost
$88,000
Address
685 Market St

replace existing cooling tower, pumps and associated control. maher na

Open the permit page

$88,000
Aug 6, 2015Completed
final sign-off Jun 2016
345 Spear StBcci Construction Companymechanical and electrical work associated with 201507020572 including new lighting, new ductwork, and heat pumps
Details
Permit
201508063526
Status
complete
Filed
Aug 6, 2015
Permit issued
Aug 7, 2015
Final sign-off
Jun 6, 2016
Declared cost
$1,450,000
Address
345 Spear St

mechanical and electrical work associated with 201507020572 including new lighting, new ductwork, and heat pumps

Open the permit page

$1,450,000
Nov 21, 2013Completed
final sign-off Jun 2015
425 Market StSkanska Usa Building Increlocate existing water cooled crac unit from level 19 to 20. provide connection to existing condense water system and existing ductwork. relocate existing data racks to level 20. new power distribtion for racks and relocate hvac. extend existing epo to include relocated equipment.no lighting,partit
Details
Permit
201311212461
Status
complete
Filed
Nov 21, 2013
Permit issued
Feb 24, 2014
Final sign-off
Jun 23, 2015
Declared cost
$250,000
Address
425 Market St

relocate existing water cooled crac unit from level 19 to 20. provide connection to existing condense water system and existing ductwork. relocate existing data racks to level 20. new power distribtion for racks and relocate hvac. extend existing epo to include relocated equipment.no lighting,partit

Open the permit page