99 permits since 2000 (contractor on 99 permits, authorized agent-others on 1 permit): 67 completed, 7 in progress, 17 never finaled, 8 expired or cancelled.
This is the city’s permit record, not a license check: the role and the number come from what was written on each permit (the number spelled one way). It does not show whether the license is current. Their ranked record as a contractor is on their contractor page. How to read these records
Most recent permits
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Apr 29, 2026 | Completed final sign-off May 2026 | 484 Eureka St | Fastnet Engineering & Const Inc | to obtain final inspection for work approved under pa# 202012291891. all work is complete.Details
to obtain final inspection for work approved under pa# 202012291891. all work is complete. | |
| Apr 21, 2026 | In progress issued Apr 2026 | 130 Hazelwood Av | Fastnet Engineering & Const Inc | revision to bpa# 202506209055 2nd floor: remove walls between kitchen dining & living rooms, remodel bathroom. structural strengthening of roof. 1/f: remove closet wall. reconfigure access to beds. infill (e) doorway at 1/f.Details
revision to bpa# 202506209055 2nd floor: remove walls between kitchen dining & living rooms, remodel bathroom. structural strengthening of roof. 1/f: remove closet wall. reconfigure access to beds. infill (e) doorway at 1/f. | $50,000 |
| Feb 26, 2026 | In progress issued Apr 2026 | 825 Faxon Av | Fastnet Engineering & Const Inc | in-kind chimney replacement existing and proposed is cinker brickDetails
in-kind chimney replacement existing and proposed is cinker brick | $20,000 |
| Feb 4, 2026 | In progress issued Feb 2026 | 130 Hazelwood Av | Fastnet Engineering & Const Inc | new rear yard site retaining walls up to 4'3" in height. provide guardrail where change in elevation is greater than 30". ref#: 202506209055Details
new rear yard site retaining walls up to 4'3" in height. provide guardrail where change in elevation is greater than 30". ref#: 202506209055 | $60,000 |
| Jun 20, 2025 | In progress issued Jul 2025 | 130 Hazelwood Av | Fastnet Engineering & Const Inc | 1st/f: add 2 bedrooms, exercise office rm & family rm, remodel bathroom. 2nd/f: add powder rm, remove wall btw kitchen & dining. remodel kitchen. structural strengthening of entire structureDetails
1st/f: add 2 bedrooms, exercise office rm & family rm, remodel bathroom. 2nd/f: add powder rm, remove wall btw kitchen & dining. remodel kitchen. structural strengthening of entire structure | $450,000 |
| Apr 22, 2025 | Completed final sign-off Aug 2025 | 486 Eureka St | Fastnet Engineering & Const Inc | remodel bathroom, no structural work, new fixtures, new tile, sheetrock. no removal of wallsDetails
remodel bathroom, no structural work, new fixtures, new tile, sheetrock. no removal of walls | $25,000 |
| Apr 22, 2025 | Completed final sign-off Aug 2025 | 484 Eureka St | Fastnet Engineering & Const Inc | remodel bathroom, no structural work, new fixtures, new tile, sheetrock. no removal of wallsDetails
remodel bathroom, no structural work, new fixtures, new tile, sheetrock. no removal of walls | $25,000 |
| Jan 17, 2025 | In progress issued Jan 2025 | 3833 Judah St | Fastnet Engineering & Const Inc | remodel (1) bathroom in kind. change tub to shower pan in the same location. no structural work. no change to floor layout. no change to wall layout.Details
remodel (1) bathroom in kind. change tub to shower pan in the same location. no structural work. no change to floor layout. no change to wall layout. | $16,000 |
| Sep 18, 2024 | Completed final sign-off Sep 2024 | 75 Esquina Dr | Fastnet Engineering & Const Inc | replace garage door. same size.Details
replace garage door. same size. | $4,000 |
| Jul 22, 2024 | In progress filed Jul 2024, not yet issued | 94 Wabash Tr | Fastnet Engineering & Const Inc | new 683sf adu at 1/f. replace all windows.Details
new 683sf adu at 1/f. replace all windows. | $100,000 |
| May 7, 2024 | Completed final sign-off Sep 2024 | 75 Esquina Dr | Fastnet Engineering & Const Inc | replace (2) windows visible from the street, windows will be wood with alum clad exterior. marvin made windows. remove all loose stucco and replace with new three coat stucco, approx 300 sq ft.Details
replace (2) windows visible from the street, windows will be wood with alum clad exterior. marvin made windows. remove all loose stucco and replace with new three coat stucco, approx 300 sq ft. | $30,000 |
| Mar 6, 2024 | Completed final sign-off Mar 2024 | 695 38th Av | Fastnet Engineering & Const Inc | to obtain final inspection for work approved under pa# 201203075530. all work is complete.Details
to obtain final inspection for work approved under pa# 201203075530. all work is complete. | |
| Aug 8, 2023 | Completed final sign-off Aug 2025 | 94 Wabash Tr | Fastnet Engineering & Const Inc | revision 202307202540 2nd fl kitchen, dining and living room remodel. 1st fl bath remodel and remove e non load bearing wall. add foundations at garageDetails
revision 202307202540 2nd fl kitchen, dining and living room remodel. 1st fl bath remodel and remove e non load bearing wall. add foundations at garage | $40,000 |
| Jul 20, 2023 | Completed final sign-off Aug 2025 | 94 Wabash Tr | Fastnet Engineering & Const Inc | dry rot repair of e fir joists, rafters, studs, sill plates and plywood as necessary. voluntary structural strengtheningDetails
dry rot repair of e fir joists, rafters, studs, sill plates and plywood as necessary. voluntary structural strengthening | $100,000 |
| Jun 21, 2023 | Completed final sign-off Jul 2023 | 1254 40th Av | Fastnet Engineering & Const Inc | repair dry rot to rear bedroom (2nd flr), south wall. replace ext finish to match (e) at south wall (not facing street)Details
repair dry rot to rear bedroom (2nd flr), south wall. replace ext finish to match (e) at south wall (not facing street) | $20,000 |
| Jun 5, 2023 | Completed final sign-off Jul 2023 | 3833 Judah St | Fastnet Engineering & Const Inc | rear only: repair/replace dry rot (1x6) under stucco, new 3/4in plywood & new stucco. approx 400sf. no structural work. rear wallDetails
rear only: repair/replace dry rot (1x6) under stucco, new 3/4in plywood & new stucco. approx 400sf. no structural work. rear wall | $8,000 |
| Jun 1, 2023 | Completed final sign-off Aug 2025 | 94 Wabash Tr | Fastnet Engineering & Const Inc | to comply w/ nov# 202307313. repair reconstruct chimney in its entirety due to damage from car impact.Details
to comply w/ nov# 202307313. repair reconstruct chimney in its entirety due to damage from car impact. | $20,000 |
| Apr 12, 2023 | Never finaled issued Apr 2023, no final | 1526 29th Av | Fastnet Engineering & Const Inc | replace front stairs dry rot framing, remove (e) terazzo stair, pour new concrete footing re-install (e) terazzo stepsDetails
replace front stairs dry rot framing, remove (e) terazzo stair, pour new concrete footing re-install (e) terazzo steps | $25,000 |
| Mar 29, 2023 | Completed final sign-off Jun 2023 | 1526 29th Av | Fastnet Engineering & Const Inc | remove cracked stucco from front facade of building approx 200 sq ft. replace rotted framing where needed. all (e) wood trim to remain. replace in kind. no window replacement.Details
remove cracked stucco from front facade of building approx 200 sq ft. replace rotted framing where needed. all (e) wood trim to remain. replace in kind. no window replacement. | $20,000 |
| Dec 30, 2022 | In progress issued Jun 2024 | 485 36th Av | Fastnet Engineering & Const Inc | remove (e) 2nd floor study. new 2-story rear addition.remove (e) 2/f kitchen/dining room wall. remove and replace (e) windows.Details
remove (e) 2nd floor study. new 2-story rear addition.remove (e) 2/f kitchen/dining room wall. remove and replace (e) windows. | $150,000 |
| Nov 16, 2022 | Completed final sign-off Mar 2024 | 695 38th Av | Fastnet Engineering & Const Inc | to obtain final inspection for work approved under pa #201411181736. all work is complete.Details
to obtain final inspection for work approved under pa #201411181736. all work is complete. | |
| Oct 13, 2022 | Completed final sign-off Jan 2026 | 420 Diamond St | Fastnet Engineering & Const Inc | structural repairs @ ground floor studio. replace (e) rear window & patio door not visible from public right of way. replace (e) deck membrane & tile. (n) window & door in-kind.Details
structural repairs @ ground floor studio. replace (e) rear window & patio door not visible from public right of way. replace (e) deck membrane & tile. (n) window & door in-kind. | $48,000 |
| Aug 25, 2022 | Completed final sign-off Oct 2024 | 433 Upper Tr | Fastnet Engineering & Const Inc | unit #2: rev pa202104017734 complete remodel work (kitchen & 2 bathroom remodel under previous permit) for unit 2 only. enlarge rear cantilever deck.Details
unit #2: rev pa202104017734 complete remodel work (kitchen & 2 bathroom remodel under previous permit) for unit 2 only. enlarge rear cantilever deck. | $8,000 |
| Aug 2, 2022 | Completed final sign-off Apr 2025 | 90 Hazelwood Av | Fastnet Engineering & Const Inc | relocate 1st fl bedroom, add bedroom to 1st fl. remodel 1st fl bath and add family room. (n) exterior opening to be wood aluminium clad.Details
relocate 1st fl bedroom, add bedroom to 1st fl. remodel 1st fl bath and add family room. (n) exterior opening to be wood aluminium clad. | $65,000 |
| May 24, 2022 | Expired or cancelled cancelled Jan 2026 | 1638 44th Av | Fastnet Engineering & Const Inc | new full bath & bedroom on 1st floor.Details
new full bath & bedroom on 1st floor. | $20,000 |
| Feb 7, 2022 | Completed final sign-off Apr 2022 | 484 Eureka St | Fastnet Engineering & Const Inc | remodel kitchen, cabinets, counters, fixtures floor, new recessed lighting. no structural work.Details
remodel kitchen, cabinets, counters, fixtures floor, new recessed lighting. no structural work. | $15,000 |
| Aug 24, 2021 | Never finaled issued Oct 2021, no final | 2768 35th Av | Fastnet Engineering & Const Inc | add new bedroom, bathroom & family room to existing 1st floor.Details
add new bedroom, bathroom & family room to existing 1st floor. | $92,000 |
| May 26, 2021 | Never finaled issued May 2021, no final | 834 37th Av | Fastnet Engineering & Const Inc | repair dry rot at rear of building approx 200 sq ftDetails
repair dry rot at rear of building approx 200 sq ft | $20,000 |
| Dec 29, 2020 | Expired or cancelled expired May 2026 | 484 Eureka St | Fastnet Engineering & Const Inc | new 397 sq. ft. roof deck.Details
new 397 sq. ft. roof deck. | $30,000 |
| Sep 24, 2020 | Completed final sign-off May 2021 | 452 43rd Av | Fastnet Engineering & Const Inc | enclose lightwell on 1/f & add (n) roof to enclosureDetails
enclose lightwell on 1/f & add (n) roof to enclosure | $35,000 |
| Jan 24, 2020 | Completed final sign-off May 2021 | 452 43rd Av | Fastnet Engineering & Const Inc | remodel kitchen & bath in rear for apt 452a.Details
remodel kitchen & bath in rear for apt 452a. | $36,000 |
| Dec 10, 2019 | Completed final sign-off Feb 2020 | 1522 29th Av | Fastnet Engineering & Const Inc | repair approx 400 sqft of dryrot at rear elevation of building, replace wood siding with wood sidingDetails
repair approx 400 sqft of dryrot at rear elevation of building, replace wood siding with wood siding | $10,000 |
| Dec 10, 2019 | Completed final sign-off Feb 2020 | 484 Eureka St | Fastnet Engineering & Const Inc | to comply with physical inspection report #cc-8394Details
to comply with physical inspection report #cc-8394 | |
| Dec 10, 2019 | Completed final sign-off Feb 2020 | 484 Eureka St | Fastnet Engineering & Const Inc | to obtain final inspection for work approved under pa 200207221968. all work is completeDetails
to obtain final inspection for work approved under pa 200207221968. all work is complete | |
| Dec 4, 2019 | Completed final sign-off Nov 2020 | 28 15th Av | Fastnet Engineering & Const Inc | dry rot repair to front of house, stucco replacement, new aluminum-clad wood windows, no change to size or configuration. colonial detail to remain.Details
dry rot repair to front of house, stucco replacement, new aluminum-clad wood windows, no change to size or configuration. colonial detail to remain. | $30,000 |
| Nov 27, 2019 | Completed final sign-off Feb 2020 | 417 Spruce St | Fastnet Engineering & Const Inc | remodel existing hair salon & convert kitchen into break room & storage.Details
remodel existing hair salon & convert kitchen into break room & storage. | $10,000 |
| Sep 16, 2019 | Never finaled issued Sep 2019, no final | 3621 20th St | Fastnet Engineering & Const Inc | new kitcen cabinets and counter. new bath and shower value. interior work only. no change of floor planDetails
new kitcen cabinets and counter. new bath and shower value. interior work only. no change of floor plan | $12,000 |
| Sep 16, 2019 | Never finaled issued Sep 2019, no final | 1648 Bacon St | Fastnet Engineering & Const Inc | new kithcen cabinets and appliances, new hardwood floors, change wall finishes, new can lights in living room and kitchen. sheetrock garageDetails
new kithcen cabinets and appliances, new hardwood floors, change wall finishes, new can lights in living room and kitchen. sheetrock garage | $40,000 |
| Apr 4, 2019 | Never finaled issued Apr 2019, no final | 200 Brannan St | Fastnet Engineering & Const Inc | unit 407: new laminate flooring, new lighting, patch sheetrock, maintain fire-rating.Details
unit 407: new laminate flooring, new lighting, patch sheetrock, maintain fire-rating. | $20,000 |
| Feb 20, 2019 | Never finaled issued Jul 2019, no final | 1648 Bacon St | Fastnet Engineering & Const Inc | new roof deck at 3rd floor at front of houseDetails
new roof deck at 3rd floor at front of house | $40,000 |
| Oct 10, 2018 | Completed final sign-off Feb 2019 | 542 16th Av | Fastnet Engineering & Const Inc | inkind repair/replace of front stucco siding and damaged wood elements due to dry rot no change to existing design features. work visible from street. approx 500 sqft.Details
inkind repair/replace of front stucco siding and damaged wood elements due to dry rot no change to existing design features. work visible from street. approx 500 sqft. | $20,000 |
| Aug 16, 2018 | Completed final sign-off Jun 2019 | 481 14th Av | Fastnet Engineering & Const Inc | voluntary structural strengthening of first floor. n/a for maher.Details
voluntary structural strengthening of first floor. n/a for maher. | $60,000 |
| Aug 13, 2018 | Completed final sign-off Aug 2018 | 224 Caselli Av | Fastnet Engineering & Const Inc | replace <50% of front stair wood construction replace in-kind.Details
replace <50% of front stair wood construction replace in-kind. | $5,000 |
| Jul 2, 2018 | Completed final sign-off Oct 2018 | 1253 Willard St | Fastnet Engineering & Const Inc | bathroom remodel, half bath remodel, no structural work neededDetails
bathroom remodel, half bath remodel, no structural work needed | $20,000 |
| Apr 3, 2018 | Completed final sign-off Aug 2018 | 484 Eureka St | Fastnet Engineering & Const Inc | remove/repair/replace stucco at front facade retaining detailing, repair dry rot as needed, repair roof at lightwell at north property line, replace drain lines.Details
remove/repair/replace stucco at front facade retaining detailing, repair dry rot as needed, repair roof at lightwell at north property line, replace drain lines. | $30,000 |
| Jan 17, 2018 | Completed final sign-off Jun 2018 | 44 15th Av | Fastnet Engineering & Const Inc | dry rot repair to front of bldg. remove stucco and 1x8 sheeting, replace w/ 1/2" plywood & new stucco approx 300 sq ft.Details
dry rot repair to front of bldg. remove stucco and 1x8 sheeting, replace w/ 1/2" plywood & new stucco approx 300 sq ft. | $20,000 |
| Jan 4, 2018 | Completed final sign-off Oct 2018 | 646 42nd Av | Fastnet Engineering & Const Inc | remodel kitchen and (1) bathroom & (1) closet. new electrical outlets in kitchen, bath and living room, new lighting in kitchen led lights. no structural work needed.Details
remodel kitchen and (1) bathroom & (1) closet. new electrical outlets in kitchen, bath and living room, new lighting in kitchen led lights. no structural work needed. | $30,000 |
| Nov 17, 2017 | Completed final sign-off Aug 2021 | 34 Point Lobos Av | Fastnet Engineering & Const Inc | vertical addition, add 3rd story over existing roof, master bedroom, bath, closet, and computer room, two desks. remodel existing kitchen.Details
vertical addition, add 3rd story over existing roof, master bedroom, bath, closet, and computer room, two desks. remodel existing kitchen. | $80,000 |
| Sep 11, 2017 | Completed final sign-off May 2019 | 301 Monterey Bl | Fastnet Engineering & Const Inc | soft story upgarde of first floor per ab-106, 107 and chapter 4d of sfbc and chapter 34 of cbc 2016Details
soft story upgarde of first floor per ab-106, 107 and chapter 4d of sfbc and chapter 34 of cbc 2016 | $44,000 |
| Sep 6, 2017 | Completed final sign-off Sep 2017 | 37 Belcher St | Fastnet Engineering & Const Inc | repair rear stairs, replace 2 stair treads and 1 4x4 pt post. less than 50%Details
repair rear stairs, replace 2 stair treads and 1 4x4 pt post. less than 50% | $1,000 |
| Jul 28, 2017 | Completed final sign-off Jul 2017 | 562 40th Av | Fastnet Engineering & Const Inc | revise to pa#20040322981 to document reduced scope of work. only 4 windows of the 6 windows were replaced. ref. renewed pa#201608104693,Details
revise to pa#20040322981 to document reduced scope of work. only 4 windows of the 6 windows were replaced. ref. renewed pa#201608104693, | |
| Jun 28, 2017 | Completed final sign-off Sep 2017 | 1249 Willard St | Fastnet Engineering & Const Inc | foundation replacement @ rear pop outDetails
foundation replacement @ rear pop out | $10,000 |
| Jun 26, 2017 | Completed final sign-off Sep 2017 | 1249 Willard St | Fastnet Engineering & Const Inc | repair dryrott at rear porch area, replace approx 300sf of lapsiding, replace plywood flooring at portch, replace exterior doors at 1251 and 1253 condo's.Details
repair dryrott at rear porch area, replace approx 300sf of lapsiding, replace plywood flooring at portch, replace exterior doors at 1251 and 1253 condo's. | $15,000 |
| Apr 21, 2017 | Completed final sign-off Oct 2019 | 452 43rd Av | Fastnet Engineering & Const Inc | remove aprox 100 sq ft of stucco to repair dry rot on the west facing and south facing sides of house, replace stucco to match existing finish. visible to street.Details
remove aprox 100 sq ft of stucco to repair dry rot on the west facing and south facing sides of house, replace stucco to match existing finish. visible to street. | $20,000 |
| Dec 22, 2016 | Completed final sign-off May 2017 | 41 Franklin St | Fastnet Engineering & Const Inc | remodel of (e) restaurant landlord under sep bld permit has seismically upgraded the bsmt masonry foundation walls with concrete walls/footing/str columns. bsmt is to have dry good/fridge storage & food prep. grnd flr w/kitchen/cooking ware washing and service along with dining area, (e) 1 full bathDetails
remodel of (e) restaurant landlord under sep bld permit has seismically upgraded the bsmt masonry foundation walls with concrete walls/footing/str columns. bsmt is to have dry good/fridge storage & food prep. grnd flr w/kitchen/cooking ware washing and service along with dining area, (e) 1 full bath | $300,000 |
| Dec 5, 2016 | Completed final sign-off Jan 2017 | 1249 Willard St | Fastnet Engineering & Const Inc | replace missing corbels to match remaining corbels along underside of cornice at front. strengthen remaining corbels as needed. general maintanance to cornice repair/replace portions in-kind. no visible changes. restoration of missin corbels.Details
replace missing corbels to match remaining corbels along underside of cornice at front. strengthen remaining corbels as needed. general maintanance to cornice repair/replace portions in-kind. no visible changes. restoration of missin corbels. | $6,000 |
| Jun 28, 2016 | Completed final sign-off May 2017 | 41 Franklin St | Fastnet Engineering & Const Inc | voluntary structural strengthening to the basement & 1st flr at the (e) vacant unit 41 located at the northern one third segment of structure located at the corner of oak & franklin streetsDetails
voluntary structural strengthening to the basement & 1st flr at the (e) vacant unit 41 located at the northern one third segment of structure located at the corner of oak & franklin streets | $145,000 |
| Jun 24, 2016 | Completed final sign-off Sep 2016 | 199 Gough St | Fastnet Engineering & Const Inc | resubmittal for health dept. ref pa 2016-0525-8369Details
resubmittal for health dept. ref pa 2016-0525-8369 | |
| Jun 9, 2016 | Completed final sign-off Oct 2016 | 87 Seal Rock Dr | Fastnet Engineering & Const Inc | 100 sq feet dry rot, repair stucco in front bldg. new electrical service and install new lighting. in entry way, 4 new led can's. provide manual shut off for such lightingDetails
100 sq feet dry rot, repair stucco in front bldg. new electrical service and install new lighting. in entry way, 4 new led can's. provide manual shut off for such lighting | $20,000 |
| May 25, 2016 | Completed final sign-off Sep 2016 | 199 Gough St | Fastnet Engineering & Const Inc | relocate some electrical outlets and some plumbing fixtures. install new extraction hood over cooking area. ul 300 separte permitDetails
relocate some electrical outlets and some plumbing fixtures. install new extraction hood over cooking area. ul 300 separte permit | $30,000 |
| Mar 4, 2016 | Completed final sign-off Apr 2018 | 55 Child St | Fastnet Engineering & Const Inc | demo stucco to explore dry rot. building permit will be obtained to correct problem later - at rear nov visible from street.Details
demo stucco to explore dry rot. building permit will be obtained to correct problem later - at rear nov visible from street. | $5,000 |
| Feb 25, 2016 | Completed final sign-off Jun 2016 | 146 Brewster St | Fastnet Engineering & Const Inc | bathroom remodel. new light fixtures throughout the house. remove hall closet. new kitchen sink and faucet. changing (e) skylight in hall 4'x3'Details
bathroom remodel. new light fixtures throughout the house. remove hall closet. new kitchen sink and faucet. changing (e) skylight in hall 4'x3' | $40,000 |
| Dec 1, 2015 | Completed final sign-off Dec 2017 | 1670 Clay St | Fastnet Engineering & Const Inc | proposed addition of 2 new units @ ground floor as part of soft story seismic retrofit. unit# 1: add studio. unit# 2: add 1 bedroom & 1 bathroom. all work to be performed within (e) boundary of the building. ** maher: n/a **Details
proposed addition of 2 new units @ ground floor as part of soft story seismic retrofit. unit# 1: add studio. unit# 2: add 1 bedroom & 1 bathroom. all work to be performed within (e) boundary of the building. ** maher: n/a ** | $55,000 |
| Oct 1, 2015 | Never finaled issued Oct 2015, no final | 456 43rd Av | Fastnet Engineering & Const Inc | inkind replacement of wood true-divided-lite windows with teak wood due to dry rot and repair stucco surrounding the window; the windows will match the exact same 20-lite mullion pattern. no bedroom windows. low eig.Details
inkind replacement of wood true-divided-lite windows with teak wood due to dry rot and repair stucco surrounding the window; the windows will match the exact same 20-lite mullion pattern. no bedroom windows. low eig. | $20,000 |
| Aug 18, 2015 | Completed final sign-off Dec 2017 | 1670 Clay St | Fastnet Engineering & Const Inc | proposed seismic strenghening of first floor to comply w/sf soft story ordiance per chapter 34b. all work limited to 1st floor. all work within bldg boundary.Details
proposed seismic strenghening of first floor to comply w/sf soft story ordiance per chapter 34b. all work limited to 1st floor. all work within bldg boundary. | $150,000 |
| Jul 28, 2015 | Never finaled issued Jul 2015, no final | 34 Point Lobos Av | Fastnet Engineering & Const Inc | replace 5 windows and new stucco remove siding and replace with stucco on the west side inkind all windows will be wood aluminum clad casement.Details
replace 5 windows and new stucco remove siding and replace with stucco on the west side inkind all windows will be wood aluminum clad casement. | $10,000 |
| Jun 30, 2015 | Never finaled issued Jun 2015, no final | 626 33rd Av | Fastnet Engineering & Const Inc | replace rear wood stair inkind with p.t. df 12 treads. no plans. current stair rotted less than 50%.Details
replace rear wood stair inkind with p.t. df 12 treads. no plans. current stair rotted less than 50%. | $4,000 |
| May 12, 2015 | Completed final sign-off Jul 2015 | 162 Hickory St | Fastnet Engineering & Const Inc | bathroom remodel, replace 3 base board heater, shower unit & tile,new hardwood floors, 3rd flr residence (private) pastor & family only.Details
bathroom remodel, replace 3 base board heater, shower unit & tile,new hardwood floors, 3rd flr residence (private) pastor & family only. | $30,000 |
| May 1, 2015 | Never finaled issued May 2015, no final | 415 Spruce St | Fastnet Engineering & Const Inc | replace six curved windows - single hung bent cottage style. wod inside and outside. paint white with ogee lugs.Details
replace six curved windows - single hung bent cottage style. wod inside and outside. paint white with ogee lugs. | $30,500 |
| Apr 27, 2015 | Never finaled issued Apr 2015, no final | 464 43rd Av | Fastnet Engineering & Const Inc | replace 66 windows on east & north sides of building, with milgard white vinyl title 24 complaint windows clad wood. not visible from street, same size & location, no rough opening changes. u-factor for all new windows shall not exceed 0.32. 15-18"x18",15-48"x48",15-48"x52",15-52"x42" & 6-56"x48".Details
replace 66 windows on east & north sides of building, with milgard white vinyl title 24 complaint windows clad wood. not visible from street, same size & location, no rough opening changes. u-factor for all new windows shall not exceed 0.32. 15-18"x18",15-48"x48",15-48"x52",15-52"x42" & 6-56"x48". | $18,000 |
| Feb 23, 2015 | Completed final sign-off Mar 2015 | 41 Franklin St | Fastnet Engineering & Const Inc | cover 8 vent's on property line to comply with nov #201389481Details
cover 8 vent's on property line to comply with nov #201389481 | $6,000 |
| Feb 18, 2015 | Expired or cancelled expired Aug 2017 | 464 43rd Av | Fastnet Engineering & Const Inc | unit 202: some dryrot repair/bathroom new shower valve, replace bathtub/new tile, 6' x 8'.Details
unit 202: some dryrot repair/bathroom new shower valve, replace bathtub/new tile, 6' x 8'. | $15,000 |
| Jan 5, 2015 | Completed final sign-off Feb 2015 | 2006 Lombard St | Fastnet Engineering & Const Inc | repair existing rear egress in kind. comply with nov 201403221Details
repair existing rear egress in kind. comply with nov 201403221 | $6,000 |
| Nov 18, 2014 | Expired or cancelled expired Mar 2024 | 695 38th Av | Fastnet Engineering & Const Inc | soft story upgrade of ground floor. other rational design.Details
soft story upgrade of ground floor. other rational design. | $20,000 |
| Nov 3, 2014 | Never finaled issued Nov 2014, no final | 43 Presidio Av | Fastnet Engineering & Const Inc | remove (e) stucco from west side of building & replace with new; work in rear of building, repair in-kind/minor dry rot repair in-kind.Details
remove (e) stucco from west side of building & replace with new; work in rear of building, repair in-kind/minor dry rot repair in-kind. | $10,000 |
| Jul 1, 2014 | Expired or cancelled expired Jun 2026 | 539 Noe St | Fastnet Engineering & Const Inc | new counter top & two cabinets with two electrical outlets, change faucet in kitchen, not full kitchen remodel.Details
new counter top & two cabinets with two electrical outlets, change faucet in kitchen, not full kitchen remodel. | $6,000 |
| May 20, 2014 | Completed final sign-off Jan 2015 | 1400 Castro St | Fastnet Engineering & Const Inc | #100- chang of occupancy at first floor, interior tenant improvements, provide one accessible restroom at 1/f. mechanical & electrical on future seperate permit.Details
#100- chang of occupancy at first floor, interior tenant improvements, provide one accessible restroom at 1/f. mechanical & electrical on future seperate permit. | $45,000 |
| Jan 23, 2014 | Completed final sign-off Feb 2014 | 1235 Sanchez St | Fastnet Engineering & Const Inc | dry rot repair to south side of buildingDetails
dry rot repair to south side of building | $3,000 |
| Dec 13, 2013 | Never finaled issued Dec 2013, no final | 1235 Sanchez St | Fastnet Engineering & Const Inc | comply w/nov #201331981 - replace stair in kind, amend stair & landing from property line, remove plexiglass from lightwell, close window at 1st floor east elevation. close proeprty line windows at east elevation at 3rd floor.Details
comply w/nov #201331981 - replace stair in kind, amend stair & landing from property line, remove plexiglass from lightwell, close window at 1st floor east elevation. close proeprty line windows at east elevation at 3rd floor. | $4,000 |
| Jun 21, 2013 | Completed final sign-off Aug 2013 | 4229 18th St | Fastnet Engineering & Const Inc | change of use from ebay store to yoga studio. bathroom, ada upgradeDetails
change of use from ebay store to yoga studio. bathroom, ada upgrade | $35,000 |
| May 7, 2013 | Completed final sign-off Jun 2013 | 1642 23rd Av | Fastnet Engineering & Const Inc | dry rot repair, stucco, paint, roof drain pipe. south facing side, visible from street.Details
dry rot repair, stucco, paint, roof drain pipe. south facing side, visible from street. | $1,500 |
| Apr 8, 2013 | Completed final sign-off Apr 2014 | 1102 Anza St | Fastnet Engineering & Const Inc | voluntary seismic strengthening of 1st floor. soft story per ab-094.Details
voluntary seismic strengthening of 1st floor. soft story per ab-094. | $30,000 |
| Feb 7, 2013 | Completed final sign-off Oct 2015 | 695 38th Av | Fastnet Engineering & Const Inc | replace windows on east side, double glazed, wood/libregas, u-factor = .40, fiberglass white, patch stucco, visible from street.Details
replace windows on east side, double glazed, wood/libregas, u-factor = .40, fiberglass white, patch stucco, visible from street. | $20,000 |
| Oct 15, 2012 | Completed final sign-off Nov 2012 | 695 38th Av | Fastnet Engineering & Const Inc | repair dry rot on west facing side, replace windows, double glazed, u-factor. replace stucco & siding, not visible from the streetDetails
repair dry rot on west facing side, replace windows, double glazed, u-factor. replace stucco & siding, not visible from the street | $20,000 |
| Jul 16, 2012 | Completed final sign-off Nov 2012 | 695 38th Av | Fastnet Engineering & Const Inc | repair dry rot on balboa street side, approx. 50% of wall, replace 4 windows in kind, visable from street, double glazed windows, max u-factor 0.40.Details
repair dry rot on balboa street side, approx. 50% of wall, replace 4 windows in kind, visable from street, double glazed windows, max u-factor 0.40. | $14,000 |
| Jun 4, 2012 | Never finaled issued Jun 2012, no final | 3710 Balboa St | Fastnet Engineering & Const Inc | dry rot, replace external plywood & 2 doors. replace stucco, visible from the street, front of building. approx 500 sq ft areaDetails
dry rot, replace external plywood & 2 doors. replace stucco, visible from the street, front of building. approx 500 sq ft area | $8,000 |
| May 2, 2012 | Completed final sign-off May 2012 | 7434 Geary Bl | Fastnet Engineering & Const Inc | replace in kind rear stairs on east rear corner of building, less than 50%Details
replace in kind rear stairs on east rear corner of building, less than 50% | $5,000 |
| Mar 7, 2012 | Expired or cancelled expired Mar 2024 | 695 38th Av | Fastnet Engineering & Const Inc | comply with nov# 201292673-1) partial voluntary seismic strengthening at 1st floor garage area. 2)partial repair/replace of extg foundation and framing.Details
comply with nov# 201292673-1) partial voluntary seismic strengthening at 1st floor garage area. 2)partial repair/replace of extg foundation and framing. | $20,000 |
| Feb 14, 2012 | Completed final sign-off Nov 2012 | 695 38th Av | Fastnet Engineering & Const Inc | repair damage to east side framing & stucco, repair dry rot area= 200 sq.ft. repair in kind to comply with nov #201292673 dated 2/10/2012. no structural work.Details
repair damage to east side framing & stucco, repair dry rot area= 200 sq.ft. repair in kind to comply with nov #201292673 dated 2/10/2012. no structural work. | $10,000 |
| Oct 17, 2011 | Completed final sign-off Nov 2011 | 43 Cole St | Fastnet Engineering & Const Inc | repair crack in retaining wall with plates as per planDetails
repair crack in retaining wall with plates as per plan | $3,000 |
| Oct 17, 2011 | Completed final sign-off Feb 2013 | 101 Point Lobos Av | Fastnet Engineering & Const Inc | unit #201: remodel existing kitchen and bathroom. n kitchen cabinets and n shower, demo e lath & plaster in kitchen & bathroom, n electrical & plumbing in kitchen & bathroom. no wall relocation. all n sheetrock shall be 5/8" type x gypsum board.Details
unit #201: remodel existing kitchen and bathroom. n kitchen cabinets and n shower, demo e lath & plaster in kitchen & bathroom, n electrical & plumbing in kitchen & bathroom. no wall relocation. all n sheetrock shall be 5/8" type x gypsum board. | $20,000 |
| May 20, 2011 | Expired or cancelled expired Mar 2014 | 153 07th Av | Fastnet Engineering & Const Inc | renovate existing 4th floor space (storage) convert to master bedroom & bath, new roof deck, 2 new dormers, replace windows & new sprinkler at 4th floor.Details
renovate existing 4th floor space (storage) convert to master bedroom & bath, new roof deck, 2 new dormers, replace windows & new sprinkler at 4th floor. | $29,000 |
| Dec 2, 2010 | Expired or cancelled expired Aug 2018 | 15 Sotelo Av | Fastnet Engineering & Const Inc | install 2 beams on 1st floor, 2 beams in master bath over window, 1 beam in basement.Details
install 2 beams on 1st floor, 2 beams in master bath over window, 1 beam in basement. | $3,000 |
| Nov 16, 2010 | Completed final sign-off Nov 2011 | 101 Point Lobos Av | Fastnet Engineering & Const Inc | unit #301: remove kitchen cabinets, lath and plaster, bathroom, replace kitchen cabinets, new bathroom including new shower, all existing walls to remainDetails
unit #301: remove kitchen cabinets, lath and plaster, bathroom, replace kitchen cabinets, new bathroom including new shower, all existing walls to remain | $10,000 |
| Jul 19, 2010 | Never finaled issued Jul 2010, no final | 34 Point Lobos Av | Fastnet Engineering & Const Inc | to obtain final inspection for work approved uneder pa # 200808219699. all work is complete.Details
to obtain final inspection for work approved uneder pa # 200808219699. all work is complete. | |
| Jul 19, 2010 | Never finaled issued Jul 2010, no final | 34 Point Lobos Av | Fastnet Engineering & Const Inc | replace (e) deck & fence. fence is less than 6ft & deck is on grade level 11" above finish grade. fence is on 3 sides, 50 linear feet. area: 100 sq. ft for the deck.Details
replace (e) deck & fence. fence is less than 6ft & deck is on grade level 11" above finish grade. fence is on 3 sides, 50 linear feet. area: 100 sq. ft for the deck. | $3,000 |
| Apr 8, 2010 | Completed final sign-off Jul 2010 | 101 Point Lobos Av | Fastnet Engineering & Const Inc | drill & epoxy 5/8 threaded rod into (e) concrete decortile corbles to attach them securely to the the face of bldg., fix and patch drill holes and paint. (ref. appl.#201003299151).Details
drill & epoxy 5/8 threaded rod into (e) concrete decortile corbles to attach them securely to the the face of bldg., fix and patch drill holes and paint. (ref. appl.#201003299151). | $40,000 |
| Mar 29, 2010 | Completed final sign-off Jul 2010 | 101 Point Lobos Av | Fastnet Engineering & Const Inc | exploratory demo to document spalling concrete. repair permit to followDetails
exploratory demo to document spalling concrete. repair permit to follow | $10,000 |
| Aug 25, 2009 | Completed final sign-off Oct 2009 | 71 Melrose Av | Fastnet Engineering & Const Inc | remove dry rot in walls and replace it with pressure treated wood & stucco. remove existing brick steps and replace with slate tile (repair less than 50%).Details
remove dry rot in walls and replace it with pressure treated wood & stucco. remove existing brick steps and replace with slate tile (repair less than 50%). | $7,000 |