4 permits since 2000 (contractor on 3 permits, engineer on 1 permit): 2 completed, 1 in progress, 1 never finaled.
This is the city’s permit record, not a license check: the role and the number come from what was written on each permit (the number spelled one way). It does not show whether the license is current. Their ranked record as a contractor is on their contractor page. How to read these records
Most recent permits
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| May 15, 2026 | In progress issued May 2026 | 1525 Beach St | Eleven Engineering Inc | unit#1: bathroom remodel in kind. remove and replace bathroom fixtures like for like, no change to walls or floor plan. approx. 60 sq ft.Details
unit#1: bathroom remodel in kind. remove and replace bathroom fixtures like for like, no change to walls or floor plan. approx. 60 sq ft. | $20,000 |
| Sep 26, 2020 | Completed final sign-off Feb 2021 | 1625 North Point St | Eleven Engineering Inc | remove non-compliant deck & stairs at rear and replace with complaint deck in same location but reduced to be outside the required rear yard.Details
remove non-compliant deck & stairs at rear and replace with complaint deck in same location but reduced to be outside the required rear yard. | $15,000 |
| Mar 11, 2020 | Never finaled issued Aug 2020, no final | 3550 Cesar Chavez St | Eleven Engineering Inc | removal of 10000 gallon underground storage tank and fuel dispenser. work to be performed under permit with env health & fire. after removal, pit will be backfilled and surface replace in kind, no grade change or other alterations.Details
removal of 10000 gallon underground storage tank and fuel dispenser. work to be performed under permit with env health & fire. after removal, pit will be backfilled and surface replace in kind, no grade change or other alterations. | $85,050 |
| Jul 25, 2018 | Completed final sign-off Feb 2020 | 123 Marina Bl | Haley & Aldrich Construction Services | removal of slab and removal of approximately 12 inches of soil. replacment of soil and new slab. removal and replacement of approx 5 feet of soil from rear and front yard. maher n/a.Details
removal of slab and removal of approximately 12 inches of soil. replacment of soil and new slab. removal and replacement of approx 5 feet of soil from rear and front yard. maher n/a. | $100,000 |