Pete Kelly
- Listed as
- architect, engineer
- Firm
- Western Allied Mechanical
- On San Francisco permits
- Dec 2006 to Jul 2017
5 permits since 2000 (engineer on 4 permits, architect on 1 permit): 4 completed, 1 expired or cancelled.
This is the city’s permit record, not a license check: the role and the number come from what was written on each permit (the number spelled one way). It does not show whether the license is current. How to read these records
Most recent permits
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Jul 11, 2017 | Completed final sign-off May 2018 | 530 Bush St | Western Allied Mechanical Inc. | remove and replace existing mech equipment with new including chiller, cooling tower, boiler, associated pumps and piping and ac unit and ductworkDetails
remove and replace existing mech equipment with new including chiller, cooling tower, boiler, associated pumps and piping and ac unit and ductwork | $1,200,000 |
| May 13, 2014 | Completed final sign-off Dec 2014 | 139 Townsend St | Western Allied Mechanical Inc. | commercial mechanical tenant improvement including installation of 6 new vav boxes & ductwork, (2) new 2-ton cooling only a/c units, (1) new 3-ton cooling only a/c unit & (1) new 4-ton split dx unit. n/a ordinance #155-13.Details
commercial mechanical tenant improvement including installation of 6 new vav boxes & ductwork, (2) new 2-ton cooling only a/c units, (1) new 3-ton cooling only a/c unit & (1) new 4-ton split dx unit. n/a ordinance #155-13. | $150,000 |
| Nov 7, 2013 | Completed final sign-off Jul 2014 | 55 Francisco St | Western Allied Mechanical Inc. | remove & replace existing water cooled chiller, cooling tower + associated pumps wiht new higher efficiency, but same capacity units. install new refigerant monitoring system + ventilation system for chiller room.Details
remove & replace existing water cooled chiller, cooling tower + associated pumps wiht new higher efficiency, but same capacity units. install new refigerant monitoring system + ventilation system for chiller room. | $450,000 |
| Jun 30, 2008 | Expired or cancelled expired Sep 2010 | 180 Howard St | Western Allied Mechanical Inc. | install ceiling hung air conditioning unit to telecom closet on the 5th floor. weight of ac unit 360 lbs.Details
install ceiling hung air conditioning unit to telecom closet on the 5th floor. weight of ac unit 360 lbs. | $20,000 |
| Dec 6, 2006 | Completed final sign-off Jul 2007 | 291 Geary St | Western Allied Mechanical Inc. | furnish & install 1 new 5-ton hvac unit on roof , modify ductwork per new tenant layout. original application #200607075964 per t.i.Details
furnish & install 1 new 5-ton hvac unit on roof , modify ductwork per new tenant layout. original application #200607075964 per t.i. | $58,900 |