Masume Dana
- Listed as
- authorized agent-others, engineer, pmt consultant/expediter
- Firm
- Forell / Elsesser Engineers
- Based in
- San Francisco
- On San Francisco permits
- Apr 2005 to Jun 2010
46 permits since 2000 (pmt consultant/expediter on 25 permits, authorized agent-others on 20 permits, engineer on 1 permit): 35 completed, 6 never finaled, 5 expired or cancelled.
This is the city’s permit record, not a license check: the role and the number come from what was written on each permit (the number spelled one way). It does not show whether the license is current. How to read these records
Most recent permits
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Jun 14, 2010 | Completed final sign-off Jun 2011 | 660 Filbert St | Cahill Const Service Inc | strengthen (e) upper towers. work includes limited localized demo of (e) steel & concrete structure; in addition to new steel framing & concrete piers & walls. towers will be scaffolded to allow for non structural exterior crack repair & painting.Details
strengthen (e) upper towers. work includes limited localized demo of (e) steel & concrete structure; in addition to new steel framing & concrete piers & walls. towers will be scaffolded to allow for non structural exterior crack repair & painting. | $500,000 |
| Jun 11, 2010 | Never finaled issued Jun 2010, no final | 58 Geary St | Ggd Inc. | int. soft demo only in advance o t.i. currently in plan checking under p.a.#201004291378. no exterior or construction work. vacant space per ab-o17.Details
int. soft demo only in advance o t.i. currently in plan checking under p.a.#201004291378. no exterior or construction work. vacant space per ab-o17. | $5,000 |
| May 27, 2010 | Completed final sign-off Nov 2010 | 714 27th St | Caruso Construction Inc. | infill new recessed entry enclosed on 3 sides & a ceiling. add a new canopy above the entry to replace the trellis. replace (e) garage doors with new. no change to garage openingDetails
infill new recessed entry enclosed on 3 sides & a ceiling. add a new canopy above the entry to replace the trellis. replace (e) garage doors with new. no change to garage opening | $13,500 |
| May 14, 2010 | Expired or cancelled disapproved Nov 2018 | 2496 Filbert St | Peter Downey Construction Co., Inc. | retrofit of e legal nonconfirming detached garage, inclwidening of e garage door to 14'6". work incl replacing e slab footing&roof truss.add n planters on each side of garage door.no work on adjacent house.Details
retrofit of e legal nonconfirming detached garage, inclwidening of e garage door to 14'6". work incl replacing e slab footing&roof truss.add n planters on each side of garage door.no work on adjacent house. | $15,000 |
| Mar 23, 2010 | Completed final sign-off Apr 2010 | 2828 18th St | floors 2,3,4 - furniture isntallation only for offices, no pratition or construction work. no increase in office space.Details
floors 2,3,4 - furniture isntallation only for offices, no pratition or construction work. no increase in office space. | $20,000 | |
| Mar 15, 2010 | Completed final sign-off May 2010 | 548 04th St | in response to nov 201034002, inset the existing entry door so that the out swing is 18" max as allowed under dpw encroachment permit 01mse-460Details
in response to nov 201034002, inset the existing entry door so that the out swing is 18" max as allowed under dpw encroachment permit 01mse-460 | $3,500 | |
| Mar 10, 2010 | Completed final sign-off Apr 2010 | 1900 Bryant St | construct a (n) storage area in (e) basement. add 2-(n) walls to create storage area with overhead garage door for access. storage area is duplicate to (e) storage at 1st. flr. lighting & electrical under separate permit.Details
construct a (n) storage area in (e) basement. add 2-(n) walls to create storage area with overhead garage door for access. storage area is duplicate to (e) storage at 1st. flr. lighting & electrical under separate permit. | $2,000 | |
| Feb 12, 2010 | Completed final sign-off Jul 2010 | 3962 19th St | Saturn Construction Co | interior soft demo in advance of interior alteration permit. no exterior work.Details
interior soft demo in advance of interior alteration permit. no exterior work. | $3,000 |
| Jan 13, 2010 | Completed final sign-off Jan 2011 | 20 Hawthorne St | D.F.P.F Corp Dba Fine Line Construction | interior demo on ground floor in 2 areas. remove concrete equipment platform, remove e vauld brick wall. install temporary shoring and guardrail in advance of future tiDetails
interior demo on ground floor in 2 areas. remove concrete equipment platform, remove e vauld brick wall. install temporary shoring and guardrail in advance of future ti | $5,000 |
| Jan 13, 2010 | Completed final sign-off May 2011 | 20 Hawthorne St | D.F.P.F Corp Dba Fine Line Construction | construct new interior 2 hr demising wall with 1 90 min rated metal door. no other work. space currently vacant. no occupancy upon completion.Details
construct new interior 2 hr demising wall with 1 90 min rated metal door. no other work. space currently vacant. no occupancy upon completion. | $5,000 |
| Jan 6, 2010 | Expired or cancelled cancelled Mar 2010 | 1141 Filbert St | install n 5'0 non combustible metal windscreen on top of new parapet wall on deck on unit 3 at western property line. no interior work. no other construction workDetails
install n 5'0 non combustible metal windscreen on top of new parapet wall on deck on unit 3 at western property line. no interior work. no other construction work | $5,000 | |
| Oct 16, 2009 | Expired or cancelled expired Jul 2014 | 2300 Chestnut St | P. L. Annuzzi, Inc. | remodel of (e) restaurant, new ramp for exterior 2nd egress. reconfigure (e) kitchen & wait station, relocate front entry door, add some new kitchen equipment, new pass-thru windows, new wine display. no expansion of building envelopeDetails
remodel of (e) restaurant, new ramp for exterior 2nd egress. reconfigure (e) kitchen & wait station, relocate front entry door, add some new kitchen equipment, new pass-thru windows, new wine display. no expansion of building envelope | $120,000 |
| Oct 9, 2009 | Completed final sign-off Nov 2009 | 251 Post St | Shawmut Woodworking & Supply Inc | erect non-electric, projecting, double faced sign. 2-blade signs - see attached dwgs.: 1-along post st.;5'-1"x1'-9". 1-along maiden lane; 8'5-1/2"x1'-9".Details
erect non-electric, projecting, double faced sign. 2-blade signs - see attached dwgs.: 1-along post st.;5'-1"x1'-9". 1-along maiden lane; 8'5-1/2"x1'-9". | $10,000 |
| Sep 25, 2009 | Never finaled issued Jan 2010, no final | 832 Folsom St | E B W Builders Inc | convert (e) vacant mechanical rm. into generator room on 3rd. floor. work includes (n) 1-hr. partitions, 1-hr. door, raised concrete pad. note: generator and fuel tank will be on seperate permit.Details
convert (e) vacant mechanical rm. into generator room on 3rd. floor. work includes (n) 1-hr. partitions, 1-hr. door, raised concrete pad. note: generator and fuel tank will be on seperate permit. | $95,000 |
| Sep 25, 2009 | Never finaled issued Nov 2009, no final | 3355 Pacific Av | Fma Builders | renovation of single family home including voluntary structural upgrade demo & (n) construction on all (3) flrs.; removal of rear fire escape, (n) lowered slab & (n) lever patio on first flr. rear. no change to fron or side facades, (n) windows at rear. no expansion to bldg. envelope.Details
renovation of single family home including voluntary structural upgrade demo & (n) construction on all (3) flrs.; removal of rear fire escape, (n) lowered slab & (n) lever patio on first flr. rear. no change to fron or side facades, (n) windows at rear. no expansion to bldg. envelope. | $1,500,000 |
| Sep 22, 2009 | Completed final sign-off Oct 2009 | 845 Market St | Dickinson Cameron Construction Company I | minor t.i. for (e) retail store in space # 121 on ground floor, work includes removal of 1 cash wrap, change in sales area fixtures, patch & paint areas thru-out, minor lighting changes. no change to mechanical or fire protection. no new wall construction.Details
minor t.i. for (e) retail store in space # 121 on ground floor, work includes removal of 1 cash wrap, change in sales area fixtures, patch & paint areas thru-out, minor lighting changes. no change to mechanical or fire protection. no new wall construction. | $10,000 |
| Sep 11, 2009 | Completed final sign-off Apr 2010 | 1141 Filbert St | Fma Builders | exterior landscape revisions only to pa# 2007-0302-5338-scope is to add water fountain to (e) planter, remove entry court at gate, change path to oval terrace to stepped stone walkway. no interior or building constructionDetails
exterior landscape revisions only to pa# 2007-0302-5338-scope is to add water fountain to (e) planter, remove entry court at gate, change path to oval terrace to stepped stone walkway. no interior or building construction | $10,000 |
| Sep 4, 2009 | Completed final sign-off Feb 2010 | 1800 Pacific Av | Fine Line Group Inc | to check water damage at stem walls, full height walls , & balcony handrails: interior non-structural exoloratory demo in units 801, 806, 1003, 201, and 102 in adavance of separate reno. permit for 802 for repair of fire damage. area of work approx. 100 sf total.Details
to check water damage at stem walls, full height walls , & balcony handrails: interior non-structural exoloratory demo in units 801, 806, 1003, 201, and 102 in adavance of separate reno. permit for 802 for repair of fire damage. area of work approx. 100 sf total. | $5,000 |
| Aug 26, 2009 | Completed final sign-off Dec 2009 | 835 Market St | James Agresta Carpentry | structural work only for raised floor in portion of t.i. under previously approved p.a. #2009/0807/4388 in unit #100Details
structural work only for raised floor in portion of t.i. under previously approved p.a. #2009/0807/4388 in unit #100 | $7,500 |
| Aug 11, 2009 | Completed final sign-off Oct 2009 | 470 Pacific Av | Terra Nova Industries | rev. to pa# 2009.04.17.6554 (ti) and 2008.0729.3717 (struc), 2009.05.18.8624 (mech) to document changes made during constr. the drawings under this permit constitute the as built condition to show doors, kitchen ducting, lightinbg, mep changes. no exterior workDetails
rev. to pa# 2009.04.17.6554 (ti) and 2008.0729.3717 (struc), 2009.05.18.8624 (mech) to document changes made during constr. the drawings under this permit constitute the as built condition to show doors, kitchen ducting, lightinbg, mep changes. no exterior work | $10,000 |
| Aug 7, 2009 | Completed final sign-off Mar 2010 | 835 Market St | James Agresta Carpentry | t.i. for new retail store in sf centre. exterior work. fire protection under separate permit.Details
t.i. for new retail store in sf centre. exterior work. fire protection under separate permit. | $370,000 |
| Jul 20, 2009 | Completed final sign-off Apr 2010 | 3336 Steiner St | Alsterlind Construction Inc. | int. non-structural demo in advance of t.i. wnder p.a.#2008/1015/4271. no exterior or construction work. exploratory work only.Details
int. non-structural demo in advance of t.i. wnder p.a.#2008/1015/4271. no exterior or construction work. exploratory work only. | $3,000 |
| Jul 13, 2009 | Completed final sign-off Jan 2011 | 1941 Leavenworth St | Moroso Construction Inc | remove exterior stair structure. build new interior stairway. add new roof deck. alter interior rooms.Details
remove exterior stair structure. build new interior stairway. add new roof deck. alter interior rooms. | $400,000 |
| Jun 24, 2009 | Completed final sign-off May 2010 | 3299 Baker St | Paul Ryan Associates | clarification to approved app 200808209595. building being designated a state historic resource per chbc secion 8-101 and 8218. railings will be replaced with 32" avove finish surface of balconies and staircase to match e historical conditions. picket spacing at entry stairway to match e spacing ofDetails
clarification to approved app 200808209595. building being designated a state historic resource per chbc secion 8-101 and 8218. railings will be replaced with 32" avove finish surface of balconies and staircase to match e historical conditions. picket spacing at entry stairway to match e spacing of | |
| Jun 24, 2009 | Completed final sign-off Apr 2010 | 3299 Baker St | Paul Ryan Associates | clarification to approved pa# 2008.06.04.3598 that permits a new roof deck with roof access via a sliding skylight instead of a staircase with roof penthouse. sliding skylight was approved under ab 057. this permit is to illustrate details of sliding skylightDetails
clarification to approved pa# 2008.06.04.3598 that permits a new roof deck with roof access via a sliding skylight instead of a staircase with roof penthouse. sliding skylight was approved under ab 057. this permit is to illustrate details of sliding skylight | |
| Jun 15, 2009 | Completed final sign-off Jun 2010 | 3052 Pacific Av | Peter Downey Construction Co., Inc. | install 2 new concrete pads & cmu wall at eastside of property. no work on house, all exteriorDetails
install 2 new concrete pads & cmu wall at eastside of property. no work on house, all exterior | $5,000 |
| Jun 12, 2009 | Completed final sign-off Oct 2009 | 733 Front St | Gotham Bay Construction | divide (e) office space (lot 9) into 2 seperate offices with (n) partitions, doors , int,windows. breakroom, fixtures, finishes.Details
divide (e) office space (lot 9) into 2 seperate offices with (n) partitions, doors , int,windows. breakroom, fixtures, finishes. | $117,500 |
| Jun 2, 2009 | Completed final sign-off Aug 2009 | 55 Cyril Magnin St | Plant Construction Company Lp | revision to pa# 2009-0519-8711-scope of work is reduction of scope: installation of only 1 glass awning/canopy at hotel entry instead of 3 awnings, no other workDetails
revision to pa# 2009-0519-8711-scope of work is reduction of scope: installation of only 1 glass awning/canopy at hotel entry instead of 3 awnings, no other work | |
| May 26, 2009 | Never finaled issued Sep 2009, no final | 347 Liberty St | Van Der Sterre Construction | interior alteration increasing size of (e) garage, install new elevator from garage to upper two levels, enlarge (e) kitchen and renovate kitchen/bath/laundry at 1st floor. add new elevator access at 2nd floor.Details
interior alteration increasing size of (e) garage, install new elevator from garage to upper two levels, enlarge (e) kitchen and renovate kitchen/bath/laundry at 1st floor. add new elevator access at 2nd floor. | $500,000 |
| May 21, 2009 | Never finaled issued May 2009, no final | 2130 Fulton St | Preston Pipelines Inc | replace (e) underground storm drain line and install one (n) fire hydrant at university of san francisco campus as shown on drawings. obtain appropriate "state industrial safety permit(s)" as refered above on this application.Details
replace (e) underground storm drain line and install one (n) fire hydrant at university of san francisco campus as shown on drawings. obtain appropriate "state industrial safety permit(s)" as refered above on this application. | $75,000 |
| May 21, 2009 | Never finaled issued May 2009, no final | 2130 Fulton St | Preston Pipelines Inc | replace a portion of the (e) underground steam line with a new steam line as shown on drawings. obtain approriate " state industrial safety permits" as referenced above on this application.Details
replace a portion of the (e) underground steam line with a new steam line as shown on drawings. obtain approriate " state industrial safety permits" as referenced above on this application. | $75,000 |
| May 20, 2009 | Completed final sign-off Feb 2010 | 1520 Lyon St | Moroso Construction Inc | replace extg wood retaining wall at east and south property lines with new concrete retaining wall. this permit revises previously approved app #200812239148 to reduce cost.Details
replace extg wood retaining wall at east and south property lines with new concrete retaining wall. this permit revises previously approved app #200812239148 to reduce cost. | |
| May 19, 2009 | Completed final sign-off Aug 2009 | 55 Cyril Magnin St | Plant Construction Company Lp | remove 3 (e) awnings above entry to hotel. retain (e) steel structure.install 3 (n) glass awnings as shown on drawing. signage under awnings separate permit.Details
remove 3 (e) awnings above entry to hotel. retain (e) steel structure.install 3 (n) glass awnings as shown on drawing. signage under awnings separate permit. | $25,000 |
| May 12, 2009 | Completed final sign-off Sep 2009 | 967 Howard St | Paul Ryan Associates | to clarify information on approved pa#200805131944. to remove corten panels on facade & install (n) stainless steel panels as shown on drawings.Details
to clarify information on approved pa#200805131944. to remove corten panels on facade & install (n) stainless steel panels as shown on drawings. | |
| Apr 17, 2009 | Completed final sign-off Aug 2009 | 55 Cyril Magnin St | Plant Construction Company Lp | occupant load only for fire department public assembly p-142 permit. ti for hotel floor 1-4 on previously approved pa# 2008/09/29/2908.Details
occupant load only for fire department public assembly p-142 permit. ti for hotel floor 1-4 on previously approved pa# 2008/09/29/2908. | |
| Apr 17, 2009 | Completed final sign-off Oct 2009 | 470 Pacific Av | Fine Line Group Inc | remodel (e) restaurant; work includes (n) partitions, fixtures, finishes, equipment, (n) lighting & mechanical. minor slab infill. fire protection and sprinklers under separate permit, no exterior work. new type i & 2 hoods and kitchen configuration.Details
remodel (e) restaurant; work includes (n) partitions, fixtures, finishes, equipment, (n) lighting & mechanical. minor slab infill. fire protection and sprinklers under separate permit, no exterior work. new type i & 2 hoods and kitchen configuration. | $300,000 |
| Apr 3, 2009 | Completed final sign-off Nov 2009 | 251 Post St | Shawmut Woodworking & Supply Inc | install new retail facade at ground level on maiden lane and on post street. interior t.i. under seperate permit.seperate permit required for alteration of fire department connection.Details
install new retail facade at ground level on maiden lane and on post street. interior t.i. under seperate permit.seperate permit required for alteration of fire department connection. | $47,000 |
| Mar 31, 2009 | Completed final sign-off May 2010 | 800 Market St | Fine Line Group Inc | m.e.p work for new retail store in basement, 1st, 2nd & 3rd floor. t.i. permit with full ada compliance on pa# 2008-1219-8917, m.e.p. work only. fire protection under seperate permitDetails
m.e.p work for new retail store in basement, 1st, 2nd & 3rd floor. t.i. permit with full ada compliance on pa# 2008-1219-8917, m.e.p. work only. fire protection under seperate permit | $65,000 |
| Mar 23, 2009 | Completed final sign-off May 2010 | 800 Market St | Fine Line Group Inc | structural work, installation of elevator in ground floor, retail space previously approved under appl. 200812198917. purpose of this permit to allow construction of elevator in advance of full t.i. permit. no exterior or other work.Details
structural work, installation of elevator in ground floor, retail space previously approved under appl. 200812198917. purpose of this permit to allow construction of elevator in advance of full t.i. permit. no exterior or other work. | |
| Mar 23, 2009 | Completed final sign-off Feb 2010 | 66 Page St | Plant Construction Company Lp | revision to 200809161710: addition of pyrostop glazing to proposed hallway at level b, level 1, and level 2Details
revision to 200809161710: addition of pyrostop glazing to proposed hallway at level b, level 1, and level 2 | $2,000 |
| Mar 18, 2009 | Completed final sign-off Nov 2009 | 100 Buena Vista Tr | Canyon Construction | lanscaping work in rear yard only. work includes n retaining walls,paving, outdoor lighting planting. no constuction on e building.Details
lanscaping work in rear yard only. work includes n retaining walls,paving, outdoor lighting planting. no constuction on e building. | $25,000 |
| Feb 25, 2009 | Expired or cancelled cancelled Jun 2010 | 3732 20th St | Moroso Construction Inc | as built revisions to approved app #200603166811,200606023053,200607126366,200608280764,200707126662,200608311102 scope of work for these plans includes determining if subject building is an existing 3 or 4 story building.Details
as built revisions to approved app #200603166811,200606023053,200607126366,200608280764,200707126662,200608311102 scope of work for these plans includes determining if subject building is an existing 3 or 4 story building. | $75,000 |
| Dec 19, 2008 | Completed final sign-off May 2010 | 800 Market St | t.i. for new retail store on 1st., 2nd., 3rd. floors & basement. work includes installation of (n) egress stair (n) elevator (n) fixtures, finishes, furniture, millwork. (n) storefront section @ bldg. corner. mepincluded in this permit. fire protection under separate permits.Details
t.i. for new retail store on 1st., 2nd., 3rd. floors & basement. work includes installation of (n) egress stair (n) elevator (n) fixtures, finishes, furniture, millwork. (n) storefront section @ bldg. corner. mepincluded in this permit. fire protection under separate permits. | $850,000 | |
| Sep 10, 2007 | Completed final sign-off Nov 2007 | 540 09th St | install (n) 10' rool up door in rear service entry. also, int. non structural demo on g/f to clear sales floor area. no other work. lighting, mech. unchanged.Details
install (n) 10' rool up door in rear service entry. also, int. non structural demo on g/f to clear sales floor area. no other work. lighting, mech. unchanged. | $5,000 | |
| May 15, 2007 | Completed final sign-off Aug 2007 | 1825 Sacramento St | t.i. on 3rd floor, minor door & partition changes, changes to ceiling, lighting & mechanical, addition to power & data. no exterior work, fire protection under seperate permit.Details
t.i. on 3rd floor, minor door & partition changes, changes to ceiling, lighting & mechanical, addition to power & data. no exterior work, fire protection under seperate permit. | $83,000 | |
| Apr 15, 2005 | Expired or cancelled expired Jan 2007 | 2307 Scott St | voluntary structural strengthening on 2nd & 3rd floors of (e) structure including new moment framesDetails
voluntary structural strengthening on 2nd & 3rd floors of (e) structure including new moment frames | $27,000 |