Oct 2019 to Dec 2022

4 permits since 2000 (engineer on 4 permits): 3 completed, 1 in progress.

CompletedIn progressNever finaledExpired or cancelled

This is the city’s permit record, not a license check: the role and the number come from what was written on each permit (the number spelled one way). It does not show whether the license is current. How to read these records

Most recent permits

FiledOutcomeAddressContractorWork described on the permitDeclared cost
Dec 8, 2022In progress
issued Dec 2023
850 Turk StCahill Contractors Llc., Bobcomm Llc Dba Pacific Das Llc.priority processing - 100% affordable housing. to erect a 8-story, 92-dwelling units, type 1a mixed-used building.
Details
Permit
202212087884
Status
issued
Filed
Dec 8, 2022
Permit issued
Dec 1, 2023
Declared cost
$39,000,000
Address
850 Turk St

priority processing - 100% affordable housing. to erect a 8-story, 92-dwelling units, type 1a mixed-used building.

Open the permit page

$39,000,000
Mar 31, 2021Completed
final sign-off Nov 2025
730 Stanyan StCahill Contractors Llc., Cahill Hercules Buildeers Joint Venturenew 8-story building containing 175,426 square feet of residential uses above 12,556 square feet of ground floor commercial uses on vacant lot. the project will provide 160 100% affordable housing rental units.
Details
Permit
202103317637
Status
complete
Filed
Mar 31, 2021
Permit issued
Dec 28, 2022
Final sign-off
Nov 19, 2025
Declared cost
$60,000,000
Address
730 Stanyan St

new 8-story building containing 175,426 square feet of residential uses above 12,556 square feet of ground floor commercial uses on vacant lot. the project will provide 160 100% affordable housing rental units.

Open the permit page

$60,000,000
Oct 8, 2019Completed
final sign-off Jun 2026
151 Friedell StNibbi Bros Assoc Inc., Baines - Nibbi J V100% affordable housing at hunter's point ship yard, erect a five stories 45 units type 1 construction residential building.
Details
Permit
201910083908
Status
complete
Filed
Oct 8, 2019
Permit issued
Apr 23, 2020
Final sign-off
Jun 30, 2026
Declared cost
$20,000,000
Address
151 Friedell St

100% affordable housing at hunter's point ship yard, erect a five stories 45 units type 1 construction residential building.

Open the permit page

$20,000,000
Oct 8, 2019Completed
final sign-off Jun 2026
351 Friedell StNibbi Bros Assoc Inc., Baines - Nibbi J V100% affordable housing at hunter's point ship yard, erect a five stories 67 residential units type 1 max use building.
Details
Permit
201910083919
Status
complete
Filed
Oct 8, 2019
Permit issued
Apr 23, 2020
Final sign-off
Jun 30, 2026
Declared cost
$28,000,000
Address
351 Friedell St

100% affordable housing at hunter's point ship yard, erect a five stories 67 residential units type 1 max use building.

Open the permit page